50H PV Haidemühl
• 50Hertz
726Total MWh
46Measures
9 MWAvg Power
46Curtailments
0Ramp-ups
Data: 2026-04-01 to 2026-09-30
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2026-09-30 | 1 | 8 |
| 2026-09-28 | 1 | 24 |
| 2026-09-22 | 1 | 14 |
| 2026-09-21 | 1 | 2 |
| 2026-09-16 | 1 | 2 |
| 2026-09-15 | 1 | 21 |
| 2026-08-31 | 1 | 3 |
| 2026-08-15 | 1 | 20 |
| 2026-08-14 | 1 | 32 |
| 2026-08-13 | 1 | 8 |
| 2026-08-12 | 1 | 12 |
| 2026-08-11 | 1 | 6 |
| 2026-08-03 | 1 | 30 |
| 2026-06-26 | 1 | 46 |
| 2026-06-25 | 1 | 9 |
| 2026-06-24 | 1 | 11 |
| 2026-06-23 | 1 | 53 |
| 2026-06-22 | 1 | 11 |
| 2026-06-17 | 1 | 38 |
| 2026-06-16 | 1 | 36 |
| 2026-06-15 | 2 | 17 |
| 2026-06-11 | 1 | 6 |
| 2026-06-09 | 1 | 14 |
| 2026-06-08 | 1 | 22 |
| 2026-06-02 | 1 | 10 |
| 2026-05-29 | 1 | 3 |
| 2026-05-28 | 1 | 4 |
| 2026-05-22 | 1 | 6 |
| 2026-05-19 | 1 | 10 |
| 2026-05-18 | 2 | 33 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2026-09-30 | 50Hertz | negative | 10 | 8 | 09:September-11:September |
| 2026-09-28 | 50Hertz | negative | 9 | 24 | 08:September-13:September |
| 2026-09-22 | 50Hertz | negative | 7 | 14 | 10:September-13:September |
| 2026-09-21 | 50Hertz | negative | 7 | 2 | 10:September-10:September |
| 2026-09-16 | 50Hertz | negative | 6 | 2 | 10:September-11:September |
| 2026-09-15 | 50Hertz | negative | 10 | 21 | 08:September-10:September |
| 2026-08-31 | 50Hertz | negative | 6 | 3 | 14:August-15:August |
| 2026-08-15 | 50Hertz | negative | 11 | 20 | 13:August-14:August |
| 2026-08-14 | 50Hertz | negative | 13 | 32 | 09:August-14:August |
| 2026-08-13 | 50Hertz | negative | 11 | 8 | 07:August-08:August |
| 2026-08-12 | 50Hertz | negative | 12 | 12 | 08:August-09:August |
| 2026-08-11 | 50Hertz | negative | 8 | 6 | 14:August-15:August |
| 2026-08-03 | 50Hertz | negative | 15 | 30 | 09:August-11:August |
| 2026-06-26 | 50Hertz | negative | 10 | 46 | 08:June-16:June |
| 2026-06-25 | 50Hertz | negative | 12 | 9 | 09:June-09:June |
| 2026-06-24 | 50Hertz | negative | 11 | 11 | 08:June-09:June |
| 2026-06-23 | 50Hertz | negative | 11 | 53 | 09:June-14:June |
| 2026-06-22 | 50Hertz | negative | 11 | 11 | 09:June-10:June |
| 2026-06-17 | 50Hertz | negative | 10 | 38 | 08:June-13:June |
| 2026-06-16 | 50Hertz | negative | 10 | 36 | 07:June-11:June |
| 2026-06-15 | 50Hertz | negative | 7 | 11 | 11:June-12:June |
| 2026-06-15 | 50Hertz | negative | 6 | 6 | 10:June-14:June |
| 2026-06-11 | 50Hertz | negative | 8 | 6 | 10:June-10:June |
| 2026-06-09 | 50Hertz | negative | 5 | 14 | 11:June-14:June |
| 2026-06-08 | 50Hertz | negative | 11 | 22 | 08:June-10:June |
| 2026-06-02 | 50Hertz | negative | 8 | 10 | 09:June-10:June |
| 2026-05-29 | 50Hertz | negative | 13 | 3 | 10:May-10:May |
| 2026-05-28 | 50Hertz | negative | 4 | 4 | 08:May-09:May |
| 2026-05-22 | 50Hertz | negative | 9 | 6 | 07:May-07:May |
| 2026-05-19 | 50Hertz | negative | 10 | 10 | 08:May-09:May |
| 2026-05-18 | 50Hertz | negative | 10 | 15 | 11:May-13:May |
| 2026-05-18 | 50Hertz | negative | 10 | 18 | 08:May-09:May |
| 2026-05-16 | 50Hertz | negative | 8 | 25 | 08:May-15:May |
| 2026-05-12 | 50Hertz | negative | 7 | 27 | 11:May-15:May |
| 2026-05-04 | 50Hertz | negative | 9 | 11 | 09:May-12:May |
| 2026-05-03 | 50Hertz | negative | 9 | 27 | 06:May-09:May |
| 2026-04-27 | 50Hertz | negative | 11 | 18 | 07:April-09:April |
| 2026-04-26 | 50Hertz | negative | 7 | 5 | 06:April-07:April |
| 2026-04-26 | 50Hertz | negative | 6 | 10 | 05:April-07:April |
| 2026-04-23 | 50Hertz | negative | 8 | 12 | 06:April-08:April |
| 2026-04-23 | 50Hertz | negative | 8 | 12 | 06:April-08:April |
| 2026-04-22 | 50Hertz | negative | 9 | 11 | 08:April-09:April |
| 2026-04-22 | 50Hertz | negative | 9 | 11 | 08:April-09:April |
| 2026-04-18 | 50Hertz | negative | 10 | 28 | 08:April-15:April |
| 2026-04-13 | 50Hertz | negative | 2 | 2 | 06:April-08:April |
| 2026-04-01 | 50Hertz | negative | 6 | 16 | 08:April-14:April |
Frequently Asked Questions
What is the redispatch history of 50H PV Haidemühl?
50H PV Haidemühl is a Erneuerbar power plant in the 50Hertz grid zone. It has received 46 redispatch instructions totaling 726 MWh since 2026-04-01.
Why is 50H PV Haidemühl frequently redispatched?
Plants in the 50Hertz zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.