← 2026-09-15

Wednesday, September 16, 2026

2026-09-17 →
3,969MWh Curtailed
4,385MWh Ramped Up
€1.35MEst. Cost
270 MWPeak Positive

Day-Ahead Spot: 90-269 €/MWh (avg 183)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TenneT DE negative 18 24,517
TransnetBW positive 17 20,810
TenneT DE positive 7 17,661
Amprion positive 10 17,076
50Hertz negative 28 9,292
TransnetBW negative 6 8,358
Amprion negative 3 1,091
50Hertz positive 4 276

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
ReserveKW Zolling 5 TenneT DE Konventionell positive 287 6,895 22:September-22:September
HAMMUENTROP_20 Amprion Konventionell positive 277 6,155 22:September-20:September
Börse TransnetBW Sonstiges negative 319 4,790 05:September-20:September
Reservekraftwerk Altbach/Deizisau Block 1 TransnetBW Konventionell positive 319 4,790 05:September-20:September
ReserveKW Zolling 5 TenneT DE Konventionell positive 257 4,755 03:September-22:September
WEISWEILER_G Amprion Konventionell positive 253 4,739 23:September-18:September
Börse TenneT DE Sonstiges positive 874 4,368 10:September-15:September
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 370 4,076 22:September-09:September
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 426 3,944 06:September-15:September
Börse TenneT DE Sonstiges negative 237 3,918 03:September-22:September
UW Büttel TenneT DE Erneuerbar negative 493 3,697 08:September-15:September
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 223 3,458 23:September-20:September
Grosskraftwerk Mannheim Block 7 TransnetBW Konventionell positive 127 3,042 22:September-22:September
Börse TransnetBW Sonstiges negative 127 3,042 22:September-22:September
KMW_KW3 Amprion Konventionell positive 258 2,065 07:September-15:September
UW Büttel TenneT DE Erneuerbar negative 357 2,052 15:September-22:September
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 196 2,010 07:September-22:September
BAG NWAK-Cluster 03 Bergrheinfeld-Schweinfurt TenneT DE Erneuerbar negative 400 2,000 09:September-14:September
WEISWEILER_G Amprion Konventionell positive 235 1,700 07:September-15:September
Lippendorf 50Hertz Konventionell negative 540 1,620 06:September-09:September
WEISWEILER_H Amprion Konventionell positive 209 1,515 07:September-15:September
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 377 1,508 05:September-09:September
BAG NWAK-Cluster 01 Mechlenreuth TenneT DE Erneuerbar negative 300 1,500 09:September-14:September
BAG NWAK-Cluster 02 Oberhaid-Redwitz TenneT DE Erneuerbar negative 300 1,500 09:September-14:September
Rostock Kohlekraftwerk 50Hertz Konventionell negative 123 1,229 23:September-22:September
UW Büttel TenneT DE Erneuerbar negative 181 1,085 22:September-04:September
Marbach GT 4 (bnBm) TransnetBW Konventionell positive 272 1,020 07:September-11:September
ReserveKW Staudinger 4 TenneT DE Konventionell positive 369 1,015 22:September-00:September
Grosskraftwerk Mannheim Block 7 TransnetBW Konventionell positive 96 955 08:September-20:September
illwerke vkw AG TransnetBW Sonstiges positive 272 951 15:September-21:September
UW Dörpen-West TenneT DE Erneuerbar negative 174 915 09:September-15:September
50H OWP Baltic Eagle 50Hertz Erneuerbar negative 123 770 07:September-14:September
Rostock Kohlekraftwerk 50Hertz Konventionell negative 110 660 06:September-15:September
Irsching 4 TenneT DE Konventionell negative 121 606 22:September-03:September
KMW_KW3 Amprion Konventionell positive 95 596 08:September-14:September
50H PV Witznitz 50Hertz Erneuerbar negative 81 568 08:September-15:September
WALSUM_10 Amprion Konventionell negative 124 528 23:September-03:September
illwerke vkw AG TransnetBW Sonstiges positive 211 527 05:September-07:September
UW Diele TenneT DE Erneuerbar negative 158 475 14:September-17:September
illwerke vkw AG TransnetBW Sonstiges positive 182 455 14:September-16:September
Hannover-Linden GuD TenneT DE Konventionell positive 87 433 16:September-21:September
Heizkraftwerk Altbach/Deizisau Block 2 TransnetBW Konventionell negative 102 408 22:September-02:September
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 250 375 07:September-09:September
Boxberg (Standort) 50Hertz Konventionell negative 183 366 06:September-08:September
WALSUM_10 Amprion Konventionell negative 80 338 08:September-15:September
UW Dörpen-West TenneT DE Erneuerbar negative 74 316 23:September-04:September
AVA Cluster Dipperz TenneT DE Erneuerbar negative 63 314 09:September-14:September
50H OWP Arcadis Ost 1 50Hertz Erneuerbar negative 60 313 08:September-14:September
Grosskraftwerk Mannheim Block 6 TransnetBW Konventionell positive 59 293 09:September-14:September
UW Emden-Ost TenneT DE Erneuerbar negative 65 276 10:September-15:September

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.41M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-09-16?

On 2026-09-16, estimated redispatch costs were approximately €1.35 million. This includes €0.4M for renewable curtailment compensation and €0.93M for conventional ramp-up costs.

Which power plants were most affected on 2026-09-16?

The most affected plant was ReserveKW Zolling 5 (TenneT DE) with 6,895 MWh of positive redispatch.

What was the electricity spot price on 2026-09-16?

The EPEX Day-Ahead spot price for DE_LU ranged from 90 to 269 €/MWh with an average of 183 €/MWh.