2,946MWh Curtailed
3,089MWh Ramped Up
€0.75MEst. Cost
210 MWPeak Positive
Day-Ahead Spot: 53-180 €/MWh (avg 114)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| Amprion | positive | 36 | 59,446 |
| 50Hertz | negative | 51 | 56,505 |
| TenneT DE | positive | 17 | 12,129 |
| TransnetBW | positive | 9 | 11,244 |
| TenneT DE | negative | 5 | 6,096 |
| Amprion | negative | 8 | 3,331 |
| TransnetBW | negative | 4 | 859 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 651 | 9,117 | 08:April-22:April |
| Knapsack 1 | Amprion | Konventionell | positive | 504 | 9,079 | 04:April-22:April |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 606 | 8,482 | 08:April-22:April |
| Börse | TenneT DE | Sonstiges | positive | 705 | 5,642 | 14:April-22:April |
| Netzreservekraftwerk BERGKAMEN_A | Amprion | Konventionell | positive | 357 | 5,272 | 07:April-22:April |
| HERDECKE_H6 | Amprion | Konventionell | positive | 294 | 5,148 | 04:April-22:April |
| NIEHL-II | Amprion | Konventionell | positive | 246 | 4,916 | 02:April-22:April |
| Emsland Block C | Amprion | Konventionell | positive | 295 | 4,724 | 06:April-22:April |
| 50H OWP Baltic Eagle | 50Hertz | negative | 281 | 4,359 | 04:April-22:April | |
| Rostock Kohlekraftwerk | 50Hertz | Konventionell | negative | 212 | 4,238 | 02:April-22:April |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 347 | 4,164 | 06:April-18:April |
| Emsland Block B | Amprion | Konventionell | positive | 252 | 4,153 | 05:April-22:April |
| GERSTEINW_G (KapRes) | Amprion | Konventionell | positive | 206 | 3,806 | 03:April-22:April |
| Irsching 4 | TenneT DE | Konventionell | negative | 229 | 3,660 | 06:April-22:April |
| Reservekraftwerk Altbach/Deizisau Block 1 | TransnetBW | Konventionell | positive | 308 | 3,468 | 03:April-15:April |
| Jänschwalde (Standort) | 50Hertz | Konventionell | negative | 193 | 2,698 | 07:April-22:April |
| 50H OWP Arkona | 50Hertz | negative | 254 | 2,666 | 06:April-21:April | |
| KMW_KW3 | Amprion | Konventionell | positive | 381 | 2,666 | 08:April-15:April |
| 50H Berlin Lichterfelde | 50Hertz | Konventionell | negative | 132 | 2,506 | 02:April-22:April |
| 50H OWP Arcadis Ost 1 | 50Hertz | negative | 166 | 2,455 | 04:April-22:April | |
| Knapsack 1 | Amprion | Konventionell | positive | 414 | 2,276 | 09:April-14:April |
| 50H OWP Wikinger | 50Hertz | negative | 189 | 2,170 | 06:April-21:April | |
| HAMMUENTROP_20 | Amprion | Konventionell | positive | 255 | 2,102 | 07:April-16:April |
| GERSTEINW_F (KapRes) | Amprion | Konventionell | positive | 127 | 1,876 | 03:April-18:April |
| Lippendorf | 50Hertz | Konventionell | negative | 203 | 1,827 | 09:April-22:April |
| Netzreservekraftwerk Bexbach A | Amprion | Konventionell | positive | 369 | 1,752 | 15:April-20:April |
| Irsching 5 | TenneT DE | Konventionell | negative | 97 | 1,752 | 04:April-22:April |
| Netzreservekraftwerk Bexbach A | Amprion | Konventionell | positive | 225 | 1,688 | 07:April-15:April |
| ReserveKW Staudinger 5 | TenneT DE | Konventionell | positive | 210 | 1,684 | 07:April-15:April |
| Jänschwalde (Standort) | 50Hertz | Konventionell | negative | 124 | 1,617 | 09:April-22:April |
| Netzreservekraftwerk KMW 2 DT | Amprion | Konventionell | positive | 138 | 1,592 | 10:April-22:April |
| Knapsack 1 | Amprion | Konventionell | positive | 473 | 1,538 | 22:April-10:April |
| Netzreservekraftwerk Bexbach A | Amprion | Konventionell | positive | 284 | 1,420 | 12:April-17:April |
| Schkopau | 50Hertz | Konventionell | negative | 98 | 1,180 | 07:April-22:April |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 190 | 1,138 | 05:April-16:April |
| 50H PV Witznitz | 50Hertz | negative | 134 | 1,070 | 06:April-16:April | |
| 50H Berlin Lichterfelde | 50Hertz | Konventionell | negative | 88 | 1,052 | 22:April-12:April |
| Linden GKL GT 1 | TenneT DE | Konventionell | positive | 63 | 996 | 06:April-22:April |
| Lippendorf | 50Hertz | Konventionell | negative | 124 | 990 | 08:April-16:April |
| GUD_HERNE_6 | Amprion | Konventionell | positive | 197 | 986 | 10:April-15:April |
| Niederrad 1 | TenneT DE | Konventionell | positive | 40 | 969 | 22:April-22:April |
| 50H OWP Baltic 1+2 | 50Hertz | negative | 190 | 952 | 11:April-16:April | |
| WALSUM_10 | Amprion | Konventionell | negative | 271 | 950 | 08:April-11:April |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 150 | 900 | 09:April-15:April |
| Schkopau | 50Hertz | Konventionell | negative | 95 | 856 | 13:April-22:April |
| WEISWEILER_G | Amprion | Konventionell | negative | 127 | 855 | 08:April-18:April |
| Frankfurt West 4 | TenneT DE | Konventionell | positive | 60 | 840 | 06:April-20:April |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 171 | 771 | 15:April-19:April |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 82 | 757 | 04:April-18:April |
| 50H UW Bertikow | 50Hertz | negative | 142 | 744 | 11:April-21:April |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.23M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-04-13?
On 2026-04-13, estimated redispatch costs were approximately €0.75 million. This includes €0.29M for renewable curtailment compensation and €0.44M for conventional ramp-up costs.
Which power plants were most affected on 2026-04-13?
The most affected plant was Schwarze Pumpe (Standort) (50Hertz) with 9,117 MWh of negative redispatch.
What was the electricity spot price on 2026-04-13?
The EPEX Day-Ahead spot price for DE_LU ranged from 53 to 180 €/MWh with an average of 114 €/MWh.