50H OWP Wikinger

Erneuerbar • 50Hertz

250,336Total MWh
502Measures
104 MWAvg Power
502Curtailments
0Ramp-ups

Data: 2024-01-04 to 2026-11-13

Daily Redispatch Volume

DateMeasuresTotal MWh
2026-11-13 2 2,143
2026-10-26 1 2
2026-10-25 1 700
2026-10-24 2 1,860
2026-10-20 1 209
2026-10-19 1 90
2026-10-13 1 150
2026-10-07 1 28
2026-10-06 2 437
2026-10-01 1 1,056
2026-09-30 2 751
2026-09-29 1 135
2026-09-28 2 1,069
2026-09-26 1 425
2026-09-24 1 9
2026-09-22 2 59
2026-09-21 1 3,408
2026-09-20 2 2,686
2026-09-18 1 194
2026-09-16 2 316
2026-09-15 1 83
2026-09-09 1 95
2026-09-08 1 406
2026-09-06 2 1,533
2026-09-05 2 1,783
2026-09-04 2 1,146
2026-09-01 2 246
2026-08-31 1 6
2026-08-28 1 3,025
2026-08-27 1 1,018

Recent Measures

DateTSODirAvg MWMWhTime
2026-11-13 50Hertz negative 186 93 21:November-21:November
2026-11-13 50Hertz negative 293 2,050 07:November-14:November
2026-10-26 50Hertz negative 9 2 18:October-19:October
2026-10-25 50Hertz negative 311 700 16:October-19:October
2026-10-24 50Hertz negative 291 1,164 22:October-02:October
2026-10-24 50Hertz negative 348 696 06:October-08:October
2026-10-20 50Hertz negative 70 209 17:October-22:October
2026-10-19 50Hertz negative 180 90 10:October-10:October
2026-10-13 50Hertz negative 75 150 12:October-14:October
2026-10-07 50Hertz negative 22 28 10:October-12:October
2026-10-06 50Hertz negative 15 19 11:October-12:October
2026-10-06 50Hertz negative 104 418 08:October-12:October
2026-10-01 50Hertz negative 249 1,056 09:October-15:October
2026-09-30 50Hertz negative 139 625 09:September-14:September
2026-09-30 50Hertz negative 84 126 09:September-11:September
2026-09-29 50Hertz negative 27 135 10:September-15:September
2026-09-28 50Hertz negative 49 196 08:September-14:September
2026-09-28 50Hertz negative 175 873 08:September-13:September
2026-09-26 50Hertz negative 106 425 08:September-12:September
2026-09-24 50Hertz negative 35 9 13:September-14:September
2026-09-22 50Hertz negative 8 21 10:September-13:September
2026-09-22 50Hertz negative 19 38 08:September-10:September
2026-09-21 50Hertz negative 341 3,408 06:September-16:September
2026-09-20 50Hertz negative 107 429 22:September-04:September
2026-09-20 50Hertz negative 282 2,257 06:September-22:September
2026-09-18 50Hertz negative 194 194 08:September-09:September
2026-09-16 50Hertz negative 50 62 09:September-11:September
2026-09-16 50Hertz negative 54 254 08:September-14:September
2026-09-15 50Hertz negative 42 83 08:September-10:September
2026-09-09 50Hertz negative 76 95 08:September-11:September
2026-09-08 50Hertz negative 96 406 08:September-13:September
2026-09-06 50Hertz negative 200 401 13:September-15:September
2026-09-06 50Hertz negative 206 1,132 06:September-12:September
2026-09-05 50Hertz negative 292 1,169 16:September-22:September
2026-09-05 50Hertz negative 205 614 05:September-08:September
2026-09-04 50Hertz negative 248 743 11:September-14:September
2026-09-04 50Hertz negative 146 403 08:September-11:September
2026-09-01 50Hertz negative 100 50 11:September-12:September
2026-09-01 50Hertz negative 87 196 08:September-11:September
2026-08-31 50Hertz negative 25 6 14:August-15:August
2026-08-28 50Hertz negative 303 3,025 06:August-16:August
2026-08-27 50Hertz negative 145 1,018 08:August-15:August
2026-08-15 50Hertz negative 32 259 07:August-15:August
2026-08-14 50Hertz negative 22 110 08:August-14:August
2026-08-10 50Hertz negative 91 91 14:August-15:August
2026-07-31 50Hertz negative 14 43 08:July-12:July
2026-07-27 50Hertz negative 22 22 08:July-09:July
2026-07-22 50Hertz negative 151 151 16:July-17:July
2026-07-08 50Hertz negative 108 861 08:July-16:July
2026-07-05 50Hertz negative 186 93 05:July-05:July

Frequently Asked Questions

What is the redispatch history of 50H OWP Wikinger?

50H OWP Wikinger is a Erneuerbar power plant in the 50Hertz grid zone. It has received 502 redispatch instructions totaling 250,336 MWh since 2024-01-04.

Why is 50H OWP Wikinger frequently redispatched?

Plants in the 50Hertz zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.