← 2026-09-25

Saturday, September 26, 2026

2026-09-27 →
3,012MWh Curtailed
3,649MWh Ramped Up
€1.23MEst. Cost
251 MWPeak Positive

Day-Ahead Spot: 2-251 €/MWh (avg 149)

TSO Breakdown

TSODirectionMeasuresTotal MWh
50Hertz negative 29 10,784
Amprion positive 7 3,370
TenneT DE negative 6 3,277
TenneT DE positive 8 1,064
TransnetBW positive 3 507
Amprion negative 1 340
50Hertz positive 2 195
TransnetBW negative 1 46

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
BAG NWAK-Cluster 03 Bergrheinfeld-Schweinfurt TenneT DE Erneuerbar negative 400 2,000 08:September-13:September
Emsland Block D Amprion Konventionell positive 246 1,845 07:September-15:September
50H PV Witznitz 50Hertz Erneuerbar negative 239 1,255 08:September-14:September
50H_AVA_CR_WOL 50Hertz Erneuerbar negative 263 1,182 07:September-12:September
50H OWP Baltic Eagle 50Hertz Erneuerbar negative 138 792 06:September-12:September
Lippendorf 50Hertz Konventionell negative 202 756 06:September-15:September
50H_AVA_CR_STW 50Hertz Erneuerbar negative 176 703 08:September-12:September
50H_AVA_CR_FOE 50Hertz Erneuerbar negative 158 553 08:September-12:September
KMW_KW3 Amprion Konventionell positive 209 522 06:September-09:September
BAG NWAK-Cluster 17 Altheim TenneT DE Erneuerbar negative 100 500 08:September-13:September
BAG NWAK-Cluster 16 Regensburg-Sittling TenneT DE Erneuerbar negative 100 500 08:September-13:September
50H_EDIS_CR_PAS 50Hertz Erneuerbar negative 164 450 09:September-12:September
50H OWP Wikinger 50Hertz Erneuerbar negative 106 425 08:September-12:September
50H OWP Windanker 50Hertz Erneuerbar negative 103 412 08:September-12:September
50H_TEN_CR_M2_VIB 50Hertz Erneuerbar negative 232 406 10:September-12:September
50H_MNS_CR_KLM 50Hertz Erneuerbar negative 180 406 08:September-11:September
NIEHL-II Amprion Konventionell positive 160 399 07:September-09:September
50H OWP Arcadis Ost 1 50Hertz Erneuerbar negative 92 367 08:September-12:September
Datteln_4 Amprion Konventionell negative 170 340 13:September-15:September
50H_MNS_CR_LAU_Nord 50Hertz Erneuerbar negative 146 328 08:September-11:September
50H_MNS_CR_JSN 50Hertz Erneuerbar negative 139 314 08:September-11:September
Braunschweig HKWM GT31 TenneT DE Konventionell positive 56 306 06:September-12:September
illwerke vkw AG TransnetBW Sonstiges positive 100 300 16:September-19:September
HUCKINGEN_A Amprion Konventionell positive 100 300 16:September-19:September
50H_MNS_CR_MA_Nord 50Hertz Erneuerbar negative 132 296 08:September-11:September
Lippendorf 50Hertz Konventionell negative 144 289 07:September-09:September
50H OWP Arkona 50Hertz Erneuerbar negative 69 275 08:September-12:September
50H_EDIS_CR_SOW_Sued 50Hertz Erneuerbar negative 88 262 09:September-12:September
BAG NWAK-Cluster 04 Aschaffenburg TenneT DE Erneuerbar negative 50 250 08:September-13:September
50H_MNS_CR_ADB 50Hertz Erneuerbar negative 163 244 09:September-11:September
50H EE Bartow 50Hertz Erneuerbar negative 56 237 07:September-13:September
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 157 236 07:September-15:September
Braunschweig GT TenneT DE Konventionell positive 42 234 07:September-12:September
Hannover-Linden GuD TenneT DE Konventionell positive 50 225 07:September-11:September
50H_MNS_CR_LAU_Sued 50Hertz Erneuerbar negative 90 202 08:September-11:September
50H_MNS_CR_MA_Sued 50Hertz Erneuerbar negative 86 194 08:September-11:September
KNAPSACK_20 Amprion Konventionell positive 165 165 07:September-08:September
50H Hamburg Wedel1 50Hertz Konventionell positive 48 145 09:September-12:September
Grosskraftwerk Mannheim Block 9 TransnetBW Konventionell positive 94 140 08:September-09:September
Braunschweig HKWN GT TenneT DE Konventionell positive 20 108 06:September-12:September
Braunschweig DT TenneT DE Konventionell positive 15 85 06:September-12:September
Datteln_4 Amprion Konventionell positive 85 85 08:September-09:September
Hannover-Linden GuD TenneT DE Konventionell positive 31 78 06:September-09:September
50H_EDIS_CR_SOW_Nord 50Hertz Erneuerbar negative 40 70 09:September-11:September
50H UW Bertikow 50Hertz Erneuerbar negative 18 70 08:September-12:September
illwerke vkw AG TransnetBW Sonstiges positive 132 66 08:September-08:September
Börse Amprion Konventionell positive 215 54 08:September-08:September
50H Hamburg Tiefstack 2 HKW SK 50Hertz Konventionell positive 50 50 10:September-11:September
Börse TransnetBW Sonstiges negative 23 46 06:September-12:September
50H_EDIS_CR_LHG 50Hertz Erneuerbar negative 20 35 09:September-11:September

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.37M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-09-26?

On 2026-09-26, estimated redispatch costs were approximately €1.23 million. This includes €0.3M for renewable curtailment compensation and €0.65M for conventional ramp-up costs.

Which power plants were most affected on 2026-09-26?

The most affected plant was BAG NWAK-Cluster 03 Bergrheinfeld-Schweinfurt (TenneT DE) with 2,000 MWh of negative redispatch.

What was the electricity spot price on 2026-09-26?

The EPEX Day-Ahead spot price for DE_LU ranged from 2 to 251 €/MWh with an average of 149 €/MWh.