Braunschweig DT
Konventionell • TenneT DE
1,860Total MWh
28Measures
12 MWAvg Power
0Curtailments
28Ramp-ups
Data: 2024-08-08 to 2026-05-18
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2026-05-18 | 3 | 272 |
| 2026-05-14 | 3 | 153 |
| 2026-03-19 | 1 | 37 |
| 2026-03-13 | 1 | 85 |
| 2026-03-07 | 1 | 72 |
| 2026-03-06 | 1 | 70 |
| 2026-03-05 | 1 | 130 |
| 2025-12-21 | 1 | 75 |
| 2025-12-09 | 1 | 21 |
| 2025-11-29 | 1 | 125 |
| 2025-11-27 | 2 | 153 |
| 2025-11-14 | 1 | 54 |
| 2025-11-03 | 2 | 216 |
| 2025-11-02 | 1 | 50 |
| 2025-09-28 | 1 | 50 |
| 2025-05-30 | 1 | 4 |
| 2025-04-24 | 1 | 10 |
| 2024-12-07 | 1 | 47 |
| 2024-11-23 | 2 | 178 |
| 2024-08-14 | 1 | 34 |
| 2024-08-08 | 1 | 21 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2026-05-18 | TenneT DE | positive | 19 | 91 | 06:May-11:May |
| 2026-05-18 | TenneT DE | positive | 19 | 91 | 06:May-11:May |
| 2026-05-18 | TenneT DE | positive | 19 | 91 | 06:May-11:May |
| 2026-05-14 | TenneT DE | positive | 15 | 51 | 06:May-09:May |
| 2026-05-14 | TenneT DE | positive | 15 | 51 | 06:May-09:May |
| 2026-05-14 | TenneT DE | positive | 15 | 51 | 06:May-09:May |
| 2026-03-19 | TenneT DE | positive | 11 | 37 | 08:March-11:March |
| 2026-03-13 | TenneT DE | positive | 15 | 85 | 09:March-14:March |
| 2026-03-07 | TenneT DE | positive | 15 | 72 | 08:March-12:March |
| 2026-03-06 | TenneT DE | positive | 10 | 70 | 08:March-15:March |
| 2026-03-05 | TenneT DE | positive | 19 | 130 | 08:March-15:March |
| 2025-12-21 | TenneT DE | positive | 7 | 75 | 04:December-17:December |
| 2025-12-09 | TenneT DE | positive | 6 | 21 | 19:December-22:December |
| 2025-11-29 | TenneT DE | positive | 6 | 125 | 23:November-23:November |
| 2025-11-27 | TenneT DE | positive | 13 | 88 | 23:November-06:November |
| 2025-11-27 | TenneT DE | positive | 7 | 65 | 05:November-16:November |
| 2025-11-14 | TenneT DE | positive | 8 | 54 | 23:November-05:November |
| 2025-11-03 | TenneT DE | positive | 20 | 176 | 23:November-08:November |
| 2025-11-03 | TenneT DE | positive | 10 | 40 | 19:November-23:November |
| 2025-11-02 | TenneT DE | positive | 10 | 50 | 01:November-06:November |
| 2025-09-28 | TenneT DE | positive | 13 | 50 | 08:September-12:September |
| 2025-05-30 | TenneT DE | positive | 4 | 4 | 00:May-01:May |
| 2025-04-24 | TenneT DE | positive | 3 | 10 | 08:April-11:April |
| 2024-12-07 | TenneT DE | positive | 15 | 47 | 04:December-07:December |
| 2024-11-23 | TenneT DE | positive | 22 | 159 | 23:November-06:November |
| 2024-11-23 | TenneT DE | positive | 13 | 19 | 21:November-23:November |
| 2024-08-14 | TenneT DE | positive | 6 | 34 | 07:August-13:August |
| 2024-08-08 | TenneT DE | positive | 10 | 21 | 23:August-01:August |
Frequently Asked Questions
What is the redispatch history of Braunschweig DT?
Braunschweig DT is a Konventionell power plant in the TenneT DE grid zone. It has received 28 redispatch instructions totaling 1,860 MWh since 2024-08-08.
Why is Braunschweig DT frequently redispatched?
Plants in the TenneT DE zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.