← 2026-09-05

Sunday, September 6, 2026

2026-09-07 →
2,395MWh Curtailed
2,704MWh Ramped Up
€0.91MEst. Cost
240 MWPeak Positive

Day-Ahead Spot: -2-240 €/MWh (avg 110)

TSO Breakdown

TSODirectionMeasuresTotal MWh
Amprion positive 10 14,533
TenneT DE negative 4 11,910
50Hertz negative 15 5,775
Amprion negative 5 5,563
TransnetBW negative 5 5,297
TransnetBW positive 7 4,105
TenneT DE positive 4 2,062
50Hertz positive 1 50

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 412 9,882 22:September-22:September
KNAPSACK_20 Amprion Konventionell positive 256 6,148 22:September-22:September
KMW_KW3 Amprion Konventionell positive 239 4,962 22:September-19:September
NEURATH_G Amprion Konventionell negative 172 4,134 22:September-22:September
Grosskraftwerk Mannheim Block 9 TransnetBW Konventionell negative 176 3,295 22:September-22:September
illwerke vkw AG TransnetBW Sonstiges positive 165 2,641 22:September-22:September
Emsland Block C Amprion Konventionell positive 208 1,459 22:September-05:September
NEURATH_G Amprion Konventionell negative 209 1,356 15:September-22:September
Irsching 5 TenneT DE Konventionell positive 186 1,348 22:September-05:September
KNAPSACK_20 Amprion Konventionell positive 207 1,244 16:September-22:September
Börse TransnetBW Sonstiges negative 140 1,156 22:September-21:September
50H OWP Wikinger 50Hertz Erneuerbar negative 206 1,132 06:September-12:September
Rostock Kohlekraftwerk 50Hertz Konventionell negative 111 1,025 23:September-16:September
UW Dörpen-West TenneT DE Erneuerbar negative 249 994 22:September-02:September
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 346 951 19:September-22:September
50H OWP Arkona 50Hertz Erneuerbar negative 134 807 08:September-14:September
Irsching 5 TenneT DE Konventionell positive 222 668 19:September-22:September
Grosskraftwerk Mannheim Block 9 TransnetBW Konventionell negative 111 667 16:September-22:September
Börse TransnetBW Sonstiges positive 96 482 22:September-20:September
50H_AVA_CR_WOL 50Hertz Erneuerbar negative 164 450 06:September-08:September
illwerke vkw AG TransnetBW Sonstiges positive 83 415 17:September-22:September
50H OWP Wikinger 50Hertz Erneuerbar negative 200 401 13:September-15:September
50H_AVA_CR_STW 50Hertz Erneuerbar negative 160 400 06:September-08:September
50H PV Witznitz 50Hertz Erneuerbar negative 200 399 13:September-15:September
50H OWP Baltic Eagle 50Hertz Erneuerbar negative 86 386 08:September-14:September
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 91 364 00:September-04:September
KNAPSACK_20 Amprion Konventionell positive 60 240 18:September-22:September
50H_AVA_CR_FOE 50Hertz Erneuerbar negative 100 225 06:September-08:September
Boxberg (Standort) 50Hertz Konventionell negative 97 194 00:September-02:September
50H_EDIS_CR_WU_NORD 50Hertz Erneuerbar negative 94 188 07:September-09:September
WALSUM_10 Amprion Konventionell positive 89 178 22:September-00:September
illwerke vkw AG TransnetBW Sonstiges positive 113 169 15:September-17:September
Börse TransnetBW Sonstiges negative 57 142 03:September-22:September
KNAPSACK_20 Amprion Konventionell positive 70 140 20:September-22:September
Emsland Block C Amprion Konventionell positive 118 118 21:September-22:September
50H UW Bertikow 50Hertz Erneuerbar negative 45 113 06:September-09:September
Börse TenneT DE Sonstiges negative 66 82 19:September-20:September
Schkopau 50Hertz Konventionell positive 50 50 23:September-00:September
CHEMIEPARK_MARL_KRAFTWERKE Amprion Konventionell negative 9 46 17:September-22:September
Umspannwerk Goldshöfe/Rotensohl TransnetBW Erneuerbar negative 21 37 10:September-12:September
50H UW Putlitz 50Hertz Erneuerbar negative 21 32 06:September-08:September
Irsching 5 TenneT DE Konventionell positive 40 30 21:September-22:September
CHEMIEPARK_MARL_KRAFTWERKE Amprion Konventionell positive 28 28 07:September-08:September
EGM_DTS Amprion Sonstiges negative 5 26 17:September-22:September
illwerke vkw AG TransnetBW Sonstiges positive 22 22 07:September-08:September
Braunschweig HKWN GT TenneT DE Konventionell positive 16 16 07:September-08:September
GAMOR_ROEMER Amprion Konventionell positive 10 16 15:September-17:September
50H UW Wustermark 50Hertz Erneuerbar negative 28 14 06:September-07:September
HKW Aalen TransnetBW Konventionell positive 12 12 16:September-17:September
50H Hamburg MMB BHKW PtH 50Hertz Konventionell negative 9 9 00:September-01:September

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.27M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-09-06?

On 2026-09-06, estimated redispatch costs were approximately €0.91 million. This includes €0.24M for renewable curtailment compensation and €0.38M for conventional ramp-up costs.

Which power plants were most affected on 2026-09-06?

The most affected plant was Wilhelmshaven (ENGIE) (TenneT DE) with 9,882 MWh of negative redispatch.

What was the electricity spot price on 2026-09-06?

The EPEX Day-Ahead spot price for DE_LU ranged from -2 to 240 €/MWh with an average of 110 €/MWh.