GAMOR_ROEMER
Konventionell • Amprion
77Total MWh
4Measures
10 MWAvg Power
0Curtailments
4Ramp-ups
Data: 2024-04-02 to 2026-09-06
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2026-09-06 | 1 | 16 |
| 2025-07-02 | 1 | 40 |
| 2024-07-10 | 1 | 15 |
| 2024-04-02 | 1 | 6 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2026-09-06 | Amprion | positive | 10 | 16 | 15:September-17:September |
| 2025-07-02 | Amprion | positive | 10 | 40 | 16:July-20:July |
| 2024-07-10 | Amprion | positive | 10 | 15 | 06:July-07:July |
| 2024-04-02 | Amprion | positive | 8 | 6 | 05:April-06:April |
Frequently Asked Questions
What is the redispatch history of GAMOR_ROEMER?
GAMOR_ROEMER is a Konventionell power plant in the Amprion grid zone. It has received 4 redispatch instructions totaling 77 MWh since 2024-04-02.
Why is GAMOR_ROEMER frequently redispatched?
Plants in the Amprion zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.