← 2026-10-12

Tuesday, October 13, 2026

2026-10-14 →
3,243MWh Curtailed
4,425MWh Ramped Up
€1.33MEst. Cost
310 MWPeak Positive

Day-Ahead Spot: 110-248 €/MWh (avg 157)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TenneT DE negative 37 104,546
Amprion positive 29 58,458
TenneT DE positive 9 27,462
50Hertz negative 32 21,104
TransnetBW positive 2 6,812
50Hertz positive 3 1,268
Amprion negative 2 1,227

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
UW Dörpen-West TenneT DE Erneuerbar negative 1676 30,169 04:October-22:October
Börse TenneT DE Sonstiges positive 942 16,019 22:October-22:October
UW Diele TenneT DE Erneuerbar negative 853 16,001 03:October-22:October
UW Dörpen-West TenneT DE Erneuerbar negative 1751 10,506 22:October-04:October
GUD_HERNE_6 Amprion Konventionell positive 569 7,969 08:October-22:October
UW Emden-Ost TenneT DE Erneuerbar negative 603 7,839 04:October-22:October
LAUSWARD_GUDF Amprion Konventionell positive 385 6,645 22:October-15:October
Wilhelmshaven TenneT DE Konventionell negative 587 6,599 22:October-09:October
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 576 6,332 22:October-09:October
UW Diele TenneT DE Erneuerbar negative 1031 6,184 22:October-04:October
Emsland Block D Amprion Konventionell positive 734 5,876 22:October-06:October
UW Emden-Ost TenneT DE Erneuerbar negative 941 5,644 22:October-04:October
LAUSWARD_GUDF Amprion Konventionell positive 335 5,441 00:October-22:October
UW Büttel TenneT DE Erneuerbar negative 462 4,616 04:October-22:October
WEISWEILER_H Amprion Konventionell positive 365 4,467 22:October-11:October
GUD_HERNE_6 Amprion Konventionell positive 530 3,710 22:October-05:October
Rostock Kohlekraftwerk 50Hertz Konventionell negative 220 3,525 06:October-22:October
Emsland Block B Amprion Konventionell positive 241 3,371 02:October-16:October
Irsching 4 TenneT DE Konventionell positive 385 2,884 14:October-22:October
Irsching 4 TenneT DE Konventionell positive 309 2,859 22:October-07:October
HAMMUENTROP_20 Amprion Konventionell positive 271 2,715 22:October-08:October
WEISWEILER_G Amprion Konventionell positive 260 2,602 22:October-12:October
Irsching 5 TenneT DE Konventionell positive 235 2,588 03:October-22:October
Emsland Block C Amprion Konventionell positive 296 2,370 22:October-22:October
Lippendorf 50Hertz Konventionell negative 372 2,231 22:October-11:October
KNAPSACK_20 Amprion Konventionell positive 293 2,124 22:October-05:October
BAG NWAK-Cluster 17 Altheim TenneT DE Erneuerbar negative 300 2,100 08:October-15:October
Boxberg (Standort) 50Hertz Konventionell negative 322 1,933 23:October-12:October
BAG NWAK-Cluster 16a Regensburg-Sittling TenneT DE Erneuerbar negative 226 1,862 08:October-16:October
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 262 1,572 08:October-22:October
Irsching 5 TenneT DE Konventionell positive 217 1,411 23:October-06:October
UW Büttel TenneT DE Erneuerbar negative 400 1,400 18:October-22:October
WEISWEILER_G Amprion Konventionell positive 173 1,381 08:October-16:October
AVA Cluster Voslapp TenneT DE Erneuerbar negative 248 1,300 16:October-22:October
Irsching 5 TenneT DE Konventionell positive 355 1,244 22:October-01:October
Boxberg (Standort) 50Hertz Konventionell negative 153 1,224 08:October-22:October
LAUSWARD_GUDF Amprion Konventionell positive 135 1,215 02:October-22:October
NIEHL-31-GUD Amprion Konventionell positive 170 1,189 02:October-22:October
UW Büttel TenneT DE Erneuerbar negative 196 1,176 22:October-04:October
GUD_HERNE_6 Amprion Konventionell positive 290 1,158 00:October-04:October
UW Diele TenneT DE Erneuerbar negative 278 1,110 00:October-04:October
AVA Cluster Voslapp TenneT DE Erneuerbar negative 150 1,088 22:October-05:October
Schkopau 50Hertz Konventionell positive 216 1,079 09:October-14:October
50H Berlin Marzahn 50Hertz Konventionell negative 78 1,014 22:October-15:October
Lippendorf 50Hertz Konventionell negative 118 1,006 08:October-22:October
UW Büttel TenneT DE Erneuerbar negative 400 1,000 11:October-14:October
LAUSWARD_GUDF Amprion Konventionell positive 82 982 08:October-22:October
HAMMUENTROP_20 Amprion Konventionell positive 131 916 07:October-20:October
50H Berlin Mitte 50Hertz Konventionell negative 70 906 22:October-15:October
Kiel (Küstenkraftwerk gesamt) TenneT DE Konventionell negative 113 904 03:October-18:October

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.4M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-10-13?

On 2026-10-13, estimated redispatch costs were approximately €1.33 million. This includes €0.32M for renewable curtailment compensation and €0.83M for conventional ramp-up costs.

Which power plants were most affected on 2026-10-13?

The most affected plant was UW Dörpen-West (TenneT DE) with 30,169 MWh of negative redispatch.

What was the electricity spot price on 2026-10-13?

The EPEX Day-Ahead spot price for DE_LU ranged from 110 to 248 €/MWh with an average of 157 €/MWh.