← 2026-09-08

Wednesday, September 9, 2026

2026-09-10 →
3,381MWh Curtailed
3,764MWh Ramped Up
€1.23MEst. Cost
223 MWPeak Positive

Day-Ahead Spot: 56-220 €/MWh (avg 144)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TenneT DE negative 44 48,731
TransnetBW positive 30 32,430
Amprion positive 34 26,191
50Hertz negative 26 25,117
TenneT DE positive 7 18,206
Amprion negative 12 17,410
TransnetBW negative 5 11,744
50Hertz positive 1 94

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
UW Dörpen-West TenneT DE Erneuerbar negative 542 9,618 04:September-22:September
Börse TenneT DE Sonstiges positive 777 8,938 07:September-22:September
UW Diele TenneT DE Erneuerbar negative 382 6,203 04:September-22:September
Reservekraftwerk Heilbronn Block 7 TransnetBW Konventionell positive 619 6,031 22:September-07:September
Reservekraftwerk Heilbronn Block 7 TransnetBW Konventionell positive 478 5,141 11:September-22:September
NEURATH_G Amprion Konventionell negative 200 4,800 22:September-22:September
NEURATH_F Amprion Konventionell negative 200 4,800 22:September-22:September
Börse TenneT DE Sonstiges positive 930 4,651 22:September-03:September
Börse TransnetBW Sonstiges negative 434 4,228 22:September-07:September
ReserveKW Zolling 5 TenneT DE Konventionell positive 251 4,020 22:September-14:September
Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 4 TransnetBW Konventionell positive 286 3,998 08:September-22:September
Börse TransnetBW Sonstiges negative 367 3,941 11:September-22:September
NIEDERAUSSEM_K Amprion Konventionell negative 160 3,840 22:September-22:September
Boxberg (Standort) 50Hertz Konventionell negative 277 3,603 04:September-22:September
Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 4 TransnetBW Konventionell positive 294 3,600 22:September-22:September
Grosskraftwerk Mannheim Block 9 TransnetBW Konventionell negative 181 3,521 22:September-22:September
AVA Cluster Twistetal TenneT DE Erneuerbar negative 251 3,325 08:September-22:September
NIEHL-II Amprion Konventionell positive 185 3,322 22:September-16:September
UW Büttel TenneT DE Erneuerbar negative 317 2,454 23:September-06:September
Jänschwalde (Standort) 50Hertz Konventionell negative 304 2,432 04:September-22:September
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 195 2,390 02:September-17:September
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 372 2,234 22:September-10:September
HAMMUENTROP_20 Amprion Konventionell positive 256 2,108 22:September-09:September
UW Diele TenneT DE Erneuerbar negative 335 2,008 22:September-04:September
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 186 1,998 06:September-16:September
Börse TenneT DE Sonstiges negative 203 1,983 22:September-14:September
illwerke vkw AG TransnetBW Sonstiges positive 215 1,936 06:September-22:September
HERDECKE_H6 Amprion Konventionell positive 213 1,915 22:September-07:September
HERDECKE_H6 Amprion Konventionell positive 283 1,913 14:September-21:September
Lippendorf 50Hertz Konventionell negative 476 1,906 22:September-09:September
SHN Cluster Heide West T411 T412 TenneT DE Erneuerbar negative 322 1,854 09:September-14:September
GUD_HERNE_6 Amprion Konventionell positive 272 1,836 15:September-22:September
UW Dörpen-West TenneT DE Erneuerbar negative 384 1,825 16:September-21:September
Boxberg (Standort) 50Hertz Konventionell negative 361 1,803 22:September-10:September
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 272 1,769 23:September-05:September
Rostock Kohlekraftwerk 50Hertz Konventionell negative 136 1,765 22:September-22:September
UW Dörpen-West TenneT DE Erneuerbar negative 291 1,749 22:September-04:September
Emsland Block C Amprion Konventionell negative 250 1,747 15:September-22:September
Jänschwalde (Standort) 50Hertz Konventionell negative 265 1,588 22:September-09:September
Lippendorf 50Hertz Konventionell negative 481 1,562 23:September-02:September
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 288 1,512 22:September-03:September
Rostock Kohlekraftwerk 50Hertz Konventionell negative 154 1,501 00:September-09:September
illwerke vkw AG TransnetBW Sonstiges positive 328 1,475 16:September-21:September
AVA Cluster Lehrte TenneT DE Erneuerbar negative 217 1,462 09:September-15:September
Lippendorf 50Hertz Konventionell negative 481 1,442 06:September-09:September
NIEHL-31-GUD Amprion Konventionell positive 171 1,368 14:September-22:September
Rostock Kohlekraftwerk 50Hertz Konventionell negative 182 1,321 14:September-22:September
illwerke vkw AG TransnetBW Sonstiges positive 276 1,309 08:September-13:September
NIEHL-II Amprion Konventionell positive 135 1,218 13:September-22:September
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 162 1,215 07:September-22:September

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.37M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-09-09?

On 2026-09-09, estimated redispatch costs were approximately €1.23 million. This includes €0.34M for renewable curtailment compensation and €0.65M for conventional ramp-up costs.

Which power plants were most affected on 2026-09-09?

The most affected plant was UW Dörpen-West (TenneT DE) with 9,618 MWh of negative redispatch.

What was the electricity spot price on 2026-09-09?

The EPEX Day-Ahead spot price for DE_LU ranged from 56 to 220 €/MWh with an average of 144 €/MWh.