← 2026-09-09

Thursday, September 10, 2026

2026-09-11 →
3,813MWh Curtailed
4,812MWh Ramped Up
€1.71MEst. Cost
559 MWPeak Positive

Day-Ahead Spot: 62-585 €/MWh (avg 194)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TenneT DE negative 9 20,541
TransnetBW positive 17 16,406
Amprion positive 15 15,311
TransnetBW negative 2 4,250
50Hertz negative 13 3,655
TenneT DE positive 12 3,431
50Hertz positive 3 985
Amprion negative 8 960

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 510 8,160 22:September-14:September
UW Dörpen-West TenneT DE Erneuerbar negative 1116 6,698 22:September-04:September
Grosskraftwerk Mannheim Block 9 TransnetBW Konventionell negative 177 4,065 22:September-22:September
Reservekraftwerk Heilbronn Block 7 TransnetBW Konventionell positive 304 3,952 22:September-11:September
HERDECKE_H6 Amprion Konventionell positive 201 3,370 22:September-14:September
illwerke vkw AG TransnetBW Sonstiges positive 175 3,329 22:September-22:September
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 374 2,900 08:September-15:September
Emsland Block C Amprion Konventionell positive 192 2,397 22:September-10:September
Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 4 TransnetBW Konventionell positive 283 2,262 22:September-06:September
UW Diele TenneT DE Erneuerbar negative 353 2,116 22:September-04:September
Börse TransnetBW Sonstiges positive 179 1,477 13:September-22:September
HAMMUENTROP_20 Amprion Konventionell positive 268 1,475 22:September-04:September
BAG NWAK-Cluster 17 Altheim TenneT DE Erneuerbar negative 200 1,400 09:September-16:September
Emsland Block B Amprion Konventionell positive 201 1,358 00:September-06:September
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 339 1,357 18:September-22:September
Emsland Block B Amprion Konventionell positive 183 1,238 22:September-04:September
ReserveKW Zolling 5 TenneT DE Konventionell positive 109 1,112 22:September-08:September
GERSTEINW_F (KapRes) Amprion Konventionell positive 114 1,050 22:September-08:September
LAUSWARD_GUDF Amprion Konventionell positive 292 1,021 07:September-10:September
HERDECKE_H6 Amprion Konventionell positive 205 924 06:September-10:September
Hannover-Linden GuD TenneT DE Konventionell positive 115 918 22:September-06:September
Boxberg (Standort) 50Hertz Konventionell negative 148 890 09:September-15:September
illwerke vkw AG TransnetBW Sonstiges positive 171 856 07:September-22:September
ReserveKW Zolling 5 TenneT DE Konventionell positive 106 688 13:September-20:September
Schkopau 50Hertz Konventionell positive 128 642 16:September-21:September
Emsland Block C Amprion Konventionell positive 195 584 19:September-22:September
Schkopau 50Hertz Konventionell negative 179 537 06:September-09:September
Rostock Kohlekraftwerk 50Hertz Konventionell negative 132 528 09:September-13:September
Reservekraftwerk Heilbronn Block 7 TransnetBW Konventionell positive 213 480 06:September-09:September
Emsland Block C Amprion Konventionell positive 111 471 00:September-05:September
50H_EDIS_CR_SOW_Sued 50Hertz Erneuerbar negative 79 412 08:September-13:September
Lippendorf 50Hertz Konventionell negative 179 403 04:September-07:September
LAUSWARD_GUDF Amprion Konventionell positive 160 360 06:September-09:September
Emsland Block B Amprion Konventionell positive 102 356 18:September-22:September
50H Berlin Mitte 50Hertz Konventionell positive 97 339 17:September-21:September
WALSUM_10 Amprion Konventionell positive 120 330 10:September-12:September
HAMMUENTROP_20 Amprion Konventionell negative 141 318 19:September-21:September
NIEHL-31-GUD Amprion Konventionell positive 135 304 00:September-09:September
50H UW Bertikow 50Hertz Erneuerbar negative 130 293 07:September-12:September
UW Dörpen-West TenneT DE Erneuerbar negative 140 280 20:September-22:September
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 76 266 04:September-11:September
UW Emden-Ost TenneT DE Erneuerbar negative 50 250 22:September-03:September
HERDECKE_H6 Amprion Konventionell negative 82 245 18:September-21:September
illwerke vkw AG TransnetBW Sonstiges positive 161 241 07:September-09:September
Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 4 TransnetBW Konventionell positive 240 240 01:September-02:September
ReserveKW Zolling 5 TenneT DE Konventionell positive 104 208 20:September-22:September
Börse TransnetBW Sonstiges negative 53 185 08:September-19:September
UW Dörpen-West TenneT DE Erneuerbar negative 95 166 19:September-22:September
Emsland Block D Amprion Konventionell negative 80 161 19:September-21:September
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 90 157 07:September-11:September

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.51M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-09-10?

On 2026-09-10, estimated redispatch costs were approximately €1.71 million. This includes €0.38M for renewable curtailment compensation and €1.08M for conventional ramp-up costs.

Which power plants were most affected on 2026-09-10?

The most affected plant was Wilhelmshaven (ENGIE) (TenneT DE) with 8,160 MWh of negative redispatch.

What was the electricity spot price on 2026-09-10?

The EPEX Day-Ahead spot price for DE_LU ranged from 62 to 585 €/MWh with an average of 194 €/MWh.