3,988MWh Curtailed
4,832MWh Ramped Up
€1.72MEst. Cost
307 MWPeak Positive
Day-Ahead Spot: 122-326 €/MWh (avg 197)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| TenneT DE | negative | 10 | 9,422 |
| TransnetBW | positive | 11 | 8,337 |
| Amprion | positive | 10 | 3,390 |
| 50Hertz | negative | 7 | 2,309 |
| TenneT DE | positive | 5 | 1,164 |
| TransnetBW | negative | 2 | 818 |
| Amprion | negative | 1 | 698 |
| 50Hertz | positive | 3 | 138 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Reservekraftwerk Heilbronn Block 7 | TransnetBW | Konventionell | positive | 405 | 4,455 | 11:September-22:September |
| UW Dörpen-West | TenneT DE | negative | 606 | 4,244 | 04:September-11:September | |
| Jänschwalde (Standort) | 50Hertz | Konventionell | negative | 205 | 1,848 | 05:September-16:September |
| UW Emden-Ost | TenneT DE | negative | 373 | 1,400 | 00:September-04:September | |
| HERDECKE_H6 | Amprion | Konventionell | positive | 159 | 1,112 | 02:September-09:September |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 252 | 1,069 | 00:September-06:September |
| UW Emden-Ost | TenneT DE | negative | 250 | 1,000 | 04:September-08:September | |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 259 | 778 | 04:September-07:September |
| UW Diele | TenneT DE | negative | 184 | 736 | 04:September-08:September | |
| WALSUM_10 | Amprion | Konventionell | negative | 164 | 698 | 10:September-16:September |
| UW Diele | TenneT DE | negative | 195 | 682 | 00:September-04:September | |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 187 | 654 | 22:September-01:September |
| Grosskraftwerk Mannheim Block 9 | TransnetBW | Konventionell | negative | 187 | 654 | 22:September-01:September |
| KNAPSACK_20 | Amprion | Konventionell | positive | 167 | 585 | 00:September-04:September |
| HAMMUENTROP_20 | Amprion | Konventionell | positive | 105 | 577 | 00:September-07:September |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 165 | 576 | 00:September-03:September |
| Börse | TenneT DE | Sonstiges | negative | 300 | 525 | 13:September-15:September |
| Börse | TenneT DE | Sonstiges | positive | 300 | 525 | 10:September-11:September |
| UW Büttel | TenneT DE | negative | 333 | 500 | 05:September-06:September | |
| ReserveKW Zolling 5 | TenneT DE | Konventionell | positive | 150 | 450 | 04:September-07:September |
| Reservekraftwerk Heilbronn Block 7 | TransnetBW | Konventionell | positive | 96 | 430 | 03:September-07:September |
| KNAPSACK_20 | Amprion | Konventionell | positive | 192 | 288 | 07:September-09:September |
| NIEHL-31-GUD | Amprion | Konventionell | positive | 91 | 273 | 00:September-03:September |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 50 | 250 | 11:September-16:September |
| NIEHL-II | Amprion | Konventionell | positive | 61 | 168 | 00:September-03:September |
| Börse | TransnetBW | Sonstiges | negative | 50 | 163 | 08:September-16:September |
| Börse | TransnetBW | Sonstiges | positive | 128 | 160 | 00:September-04:September |
| Rostock Kohlekraftwerk | 50Hertz | Konventionell | negative | 80 | 160 | 02:September-09:September |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 55 | 150 | 12:September-14:September |
| HAMMUENTROP_20 | Amprion | Konventionell | positive | 100 | 150 | 00:September-02:September |
| Kiel (Küstenkraftwerk gesamt) | TenneT DE | Konventionell | negative | 110 | 110 | 05:September-06:September |
| NIEHL-31-GUD | Amprion | Konventionell | positive | 60 | 105 | 00:September-02:September |
| SW München KW-Pool | TenneT DE | Sonstiges | positive | 82 | 102 | 03:September-05:September |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 200 | 100 | 06:September-06:September |
| 50H Berlin Mitte | 50Hertz | Konventionell | positive | 42 | 85 | 02:September-04:September |
| WP Emsland | TenneT DE | negative | 25 | 74 | 00:September-03:September | |
| Heizkraftwerk_Pforzheim | TransnetBW | Konventionell | positive | 25 | 74 | 03:September-06:September |
| NIEHL-II | Amprion | Konventionell | positive | 20 | 70 | 00:September-04:September |
| NIEHL-II | Amprion | Konventionell | positive | 31 | 62 | 02:September-04:September |
| Börse | TenneT DE | Sonstiges | positive | 59 | 59 | 05:September-06:September |
| 50H Berlin Lichterfelde | 50Hertz | Konventionell | positive | 22 | 45 | 03:September-05:September |
| Börse | TenneT DE | Sonstiges | positive | 110 | 28 | 00:September-00:September |
| Reservekraftwerk Heilbronn Block 7 | TransnetBW | Konventionell | positive | 110 | 28 | 22:September-22:September |
| 50H InfraLeuna IKW | 50Hertz | Konventionell | negative | 20 | 20 | 15:September-16:September |
| Börse | TransnetBW | Sonstiges | positive | 17 | 13 | 15:September-15:September |
| Lippendorf | 50Hertz | Konventionell | negative | 12 | 12 | 07:September-08:September |
| 50H Berlin Mitte | 50Hertz | Konventionell | negative | 10 | 10 | 08:September-09:September |
| 50H Hamburg MMB BHKW PtH | 50Hertz | Konventionell | negative | 9 | 9 | 08:September-09:September |
| Börse | 50Hertz | Sonstiges | positive | 32 | 8 | 08:September-09:September |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.52M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-09-11?
On 2026-09-11, estimated redispatch costs were approximately €1.72 million. This includes €0.4M for renewable curtailment compensation and €1.1M for conventional ramp-up costs.
Which power plants were most affected on 2026-09-11?
The most affected plant was Reservekraftwerk Heilbronn Block 7 (TransnetBW) with 4,455 MWh of positive redispatch.
What was the electricity spot price on 2026-09-11?
The EPEX Day-Ahead spot price for DE_LU ranged from 122 to 326 €/MWh with an average of 197 €/MWh.