3,257MWh Curtailed
3,628MWh Ramped Up
€1.19MEst. Cost
294 MWPeak Positive
Day-Ahead Spot: 0-303 €/MWh (avg 141)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| TenneT DE | negative | 10 | 11,429 |
| 50Hertz | negative | 38 | 10,822 |
| Amprion | positive | 11 | 6,357 |
| TransnetBW | positive | 4 | 2,208 |
| TenneT DE | positive | 4 | 796 |
| TransnetBW | negative | 2 | 633 |
| Amprion | negative | 3 | 447 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| BAG NWAK-Cluster 03 Bergrheinfeld-Schweinfurt | TenneT DE | negative | 366 | 2,925 | 07:August-15:August | |
| 50H PV Witznitz | 50Hertz | negative | 315 | 2,286 | 06:August-14:August | |
| KMW_KW3 | Amprion | Konventionell | positive | 215 | 1,936 | 06:August-15:August |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 229 | 1,774 | 07:August-15:August |
| BAG NWAK-Cluster 06 Raitersaich | TenneT DE | negative | 216 | 1,725 | 07:August-15:August | |
| BAG NWAK-Cluster 02 Oberhaid-Redwitz | TenneT DE | negative | 216 | 1,725 | 07:August-15:August | |
| BAG NWAK-Cluster 17 Altheim | TenneT DE | negative | 181 | 1,450 | 07:August-15:August | |
| BAG NWAK-Cluster 16 Regensburg-Sittling | TenneT DE | negative | 150 | 1,200 | 07:August-15:August | |
| Emsland Block B | Amprion | Konventionell | positive | 184 | 1,057 | 03:August-09:August |
| Emsland Block C | Amprion | Konventionell | positive | 198 | 988 | 04:August-09:August |
| Börse | TenneT DE | Sonstiges | negative | 176 | 924 | 08:August-13:August |
| Schkopau | 50Hertz | Konventionell | negative | 190 | 901 | 03:August-08:August |
| BAG NWAK-Cluster 15 Pleinting | TenneT DE | negative | 100 | 800 | 07:August-15:August | |
| 50H_AVA_CR_WOL | 50Hertz | negative | 201 | 602 | 08:August-11:August | |
| KMW_KW3 | Amprion | Konventionell | positive | 120 | 601 | 08:August-14:August |
| BAG NWAK-Cluster 04 Aschaffenburg | TenneT DE | negative | 70 | 560 | 07:August-15:August | |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 132 | 527 | 05:August-09:August |
| Jänschwalde (Standort) | 50Hertz | Konventionell | negative | 171 | 513 | 06:August-09:August |
| Hannover-Linden GuD | TenneT DE | Konventionell | positive | 60 | 496 | 06:August-14:August |
| 50H_MNS_CR_KLM | 50Hertz | negative | 183 | 458 | 08:August-10:August | |
| 50H_AVA_CR_STW | 50Hertz | negative | 140 | 419 | 08:August-11:August | |
| Börse | TransnetBW | Sonstiges | negative | 125 | 408 | 04:August-15:August |
| Emsland Block C | Amprion | Konventionell | positive | 200 | 400 | 06:August-08:August |
| 50H_EDIS_CR_SOW_Sued | 50Hertz | negative | 76 | 400 | 08:August-14:August | |
| HAMMUENTROP_20 | Amprion | Konventionell | positive | 258 | 388 | 06:August-08:August |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 127 | 382 | 06:August-09:August |
| Schkopau | 50Hertz | Konventionell | negative | 95 | 380 | 04:August-08:August |
| 50H OWP Baltic Eagle | 50Hertz | negative | 74 | 371 | 08:August-14:August | |
| 50H_TEN_CR_M2_VIB | 50Hertz | negative | 181 | 362 | 08:August-10:August | |
| 50H_MNS_CR_PUL | 50Hertz | negative | 181 | 362 | 08:August-10:August | |
| Netzreservekraftwerk GTKW-DA-POOL | Amprion | Konventionell | positive | 60 | 358 | 08:August-14:August |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 113 | 339 | 05:August-08:August |
| 50H_MNS_CR_LAU_Nord | 50Hertz | negative | 116 | 320 | 08:August-10:August | |
| 50H_EDIS_CR_LV_WU | 50Hertz | negative | 96 | 288 | 11:August-14:August | |
| Datteln_4 | Amprion | Konventionell | negative | 282 | 282 | 08:August-09:August |
| 50H_MNS_CR_MA_Nord | 50Hertz | negative | 112 | 279 | 08:August-10:August | |
| UW Höpfingen | TransnetBW | negative | 100 | 225 | 09:August-12:August | |
| 50H OWP Arkona | 50Hertz | negative | 44 | 221 | 08:August-14:August | |
| 50H OWP Arcadis Ost 1 | 50Hertz | negative | 43 | 216 | 08:August-14:August | |
| WEISWEILER_H | Amprion | Konventionell | positive | 137 | 205 | 07:August-08:August |
| NIEHL-31-GUD | Amprion | Konventionell | positive | 102 | 204 | 06:August-08:August |
| 50H_MNS_CR_MA_Sued | 50Hertz | negative | 81 | 202 | 08:August-10:August | |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 67 | 200 | 17:August-20:August |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 49 | 196 | 04:August-08:August |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 86 | 172 | 06:August-08:August |
| NIEDERAUSSEM_K | Amprion | Konventionell | negative | 163 | 163 | 08:August-09:August |
| Gebersdorf GT | TenneT DE | Konventionell | positive | 53 | 159 | 17:August-20:August |
| Emsland Block B | Amprion | Konventionell | positive | 76 | 152 | 06:August-08:August |
| 50H_TEN_CR_M1_EI | 50Hertz | negative | 50 | 125 | 08:August-11:August | |
| Grosskraftwerk Mannheim Block 9 | TransnetBW | Konventionell | positive | 100 | 125 | 07:August-08:August |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.36M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-08-14?
On 2026-08-14, estimated redispatch costs were approximately €1.19 million. This includes €0.33M for renewable curtailment compensation and €0.62M for conventional ramp-up costs.
Which power plants were most affected on 2026-08-14?
The most affected plant was BAG NWAK-Cluster 03 Bergrheinfeld-Schweinfurt (TenneT DE) with 2,925 MWh of negative redispatch.
What was the electricity spot price on 2026-08-14?
The EPEX Day-Ahead spot price for DE_LU ranged from 0 to 303 €/MWh with an average of 141 €/MWh.