BAG NWAK-Cluster 06 Raitersaich
4,575Total MWh
4Measures
198 MWAvg Power
4Curtailments
0Ramp-ups
Data: 2025-04-20 to 2026-06-23
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2026-06-23 | 1 | 1,450 |
| 2026-05-26 | 1 | 475 |
| 2025-07-01 | 1 | 1,950 |
| 2025-04-20 | 1 | 700 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2026-06-23 | TenneT DE | negative | 290 | 1,450 | 08:June-13:June |
| 2026-05-26 | TenneT DE | negative | 100 | 475 | 08:May-13:May |
| 2025-07-01 | TenneT DE | negative | 300 | 1,950 | 07:July-14:July |
| 2025-04-20 | TenneT DE | negative | 100 | 700 | 07:April-14:April |
Frequently Asked Questions
What is the redispatch history of BAG NWAK-Cluster 06 Raitersaich?
BAG NWAK-Cluster 06 Raitersaich is a Erneuerbar power plant in the TenneT DE grid zone. It has received 4 redispatch instructions totaling 4,575 MWh since 2025-04-20.
Why is BAG NWAK-Cluster 06 Raitersaich frequently redispatched?
Plants in the TenneT DE zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.