← 2026-08-10

Tuesday, August 11, 2026

2026-08-12 →
2,526MWh Curtailed
2,755MWh Ramped Up
€0.88MEst. Cost
207 MWPeak Positive

Day-Ahead Spot: 0-205 €/MWh (avg 111)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TenneT DE negative 38 21,483
50Hertz negative 66 20,748
TransnetBW positive 12 17,428
Amprion positive 24 13,464
Amprion negative 4 4,468
TenneT DE positive 8 1,126
TransnetBW negative 4 450
50Hertz positive 2 10

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 455 6,141 02:August-16:August
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 455 6,141 02:August-16:August
UW Büttel TenneT DE Erneuerbar negative 312 3,896 02:August-15:August
UW Büttel TenneT DE Erneuerbar negative 312 3,896 02:August-15:August
50H PV Witznitz 50Hertz Erneuerbar negative 320 2,560 07:August-15:August
50H PV Witznitz 50Hertz Erneuerbar negative 320 2,560 07:August-15:August
KMW_KW3 Amprion Konventionell positive 238 2,497 06:August-16:August
KMW_KW3 Amprion Konventionell positive 238 2,497 06:August-16:August
NIEDERAUSSEM_K Amprion Konventionell positive 193 1,301 08:August-15:August
NIEDERAUSSEM_K Amprion Konventionell positive 193 1,301 08:August-15:August
illwerke vkw AG TransnetBW Sonstiges positive 317 1,268 04:August-08:August
illwerke vkw AG TransnetBW Sonstiges positive 317 1,268 04:August-08:August
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 433 1,191 05:August-08:August
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 433 1,191 05:August-08:August
Datteln_4 Amprion Konventionell negative 340 1,189 06:August-16:August
Datteln_4 Amprion Konventionell negative 340 1,189 06:August-16:August
BAG NWAK-Cluster 17 Altheim TenneT DE Erneuerbar negative 150 1,125 09:August-17:August
BAG NWAK-Cluster 15 Pleinting TenneT DE Erneuerbar negative 150 1,125 09:August-17:August
BAG NWAK-Cluster 17 Altheim TenneT DE Erneuerbar negative 150 1,125 09:August-17:August
BAG NWAK-Cluster 15 Pleinting TenneT DE Erneuerbar negative 150 1,125 09:August-17:August
NIEDERAUSSEM_K Amprion Konventionell negative 174 1,045 06:August-17:August
NIEDERAUSSEM_K Amprion Konventionell negative 174 1,045 06:August-17:August
BAG NWAK-Cluster 03 Bergrheinfeld-Schweinfurt TenneT DE Erneuerbar negative 250 1,000 06:August-10:August
BAG NWAK-Cluster 03 Bergrheinfeld-Schweinfurt TenneT DE Erneuerbar negative 250 1,000 06:August-10:August
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 216 866 04:August-08:August
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 216 866 04:August-08:August
SHN Cluster Heide West T411 T412 TenneT DE Erneuerbar negative 258 838 05:August-08:August
SHN Cluster Heide West T411 T412 TenneT DE Erneuerbar negative 258 838 05:August-08:August
Lippendorf 50Hertz Konventionell negative 271 813 04:August-07:August
Lippendorf 50Hertz Konventionell negative 271 813 04:August-07:August
BAG NWAK-Cluster 16 Regensburg-Sittling TenneT DE Erneuerbar negative 100 750 09:August-17:August
BAG NWAK-Cluster 16 Regensburg-Sittling TenneT DE Erneuerbar negative 100 750 09:August-17:August
Boxberg (Standort) 50Hertz Konventionell negative 248 746 05:August-08:August
Boxberg (Standort) 50Hertz Konventionell negative 248 746 05:August-08:August
illwerke vkw AG TransnetBW Sonstiges positive 172 730 16:August-21:August
illwerke vkw AG TransnetBW Sonstiges positive 172 730 16:August-21:August
Schkopau 50Hertz Konventionell negative 230 690 04:August-07:August
Schkopau 50Hertz Konventionell negative 230 690 04:August-07:August
KMW_KW3 Amprion Konventionell positive 236 648 05:August-08:August
KMW_KW3 Amprion Konventionell positive 236 648 05:August-08:August
WEISWEILER_H Amprion Konventionell positive 210 630 06:August-09:August
WEISWEILER_H Amprion Konventionell positive 210 630 06:August-09:August
50H_AVA_CR_STW 50Hertz Erneuerbar negative 233 525 06:August-08:August
50H_AVA_CR_STW 50Hertz Erneuerbar negative 233 525 06:August-08:August
50H_AVA_CR_WOL 50Hertz Erneuerbar negative 230 460 06:August-08:August
50H_AVA_CR_WOL 50Hertz Erneuerbar negative 230 460 06:August-08:August
Emsland Block B Amprion Konventionell positive 74 446 14:August-20:August
Emsland Block B Amprion Konventionell positive 74 446 14:August-20:August
Boxberg (Standort) 50Hertz Konventionell negative 217 434 15:August-17:August
Boxberg (Standort) 50Hertz Konventionell negative 217 434 15:August-17:August

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.26M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-08-11?

On 2026-08-11, estimated redispatch costs were approximately €0.88 million. This includes €0.25M for renewable curtailment compensation and €0.39M for conventional ramp-up costs.

Which power plants were most affected on 2026-08-11?

The most affected plant was Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 (TransnetBW) with 6,141 MWh of positive redispatch.

What was the electricity spot price on 2026-08-11?

The EPEX Day-Ahead spot price for DE_LU ranged from 0 to 205 €/MWh with an average of 111 €/MWh.