← 2026-08-12

Thursday, August 13, 2026

2026-08-14 →
3,538MWh Curtailed
3,750MWh Ramped Up
€1.25MEst. Cost
487 MWPeak Positive

Day-Ahead Spot: 0-487 €/MWh (avg 147)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TenneT DE negative 8 6,657
50Hertz negative 25 5,054
TenneT DE positive 6 2,404
Amprion positive 6 988
TransnetBW positive 2 673
TransnetBW negative 1 190
50Hertz positive 2 31

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
BAG NWAK-Cluster 03 Bergrheinfeld-Schweinfurt TenneT DE Erneuerbar negative 200 1,400 07:August-14:August
BAG NWAK-Cluster 17 Altheim TenneT DE Erneuerbar negative 150 1,275 07:August-16:August
BAG NWAK-Cluster 15 Pleinting TenneT DE Erneuerbar negative 150 1,275 07:August-16:August
50H PV Witznitz 50Hertz Erneuerbar negative 219 1,206 06:August-12:August
50H_TEN_CR_M2_VIB 50Hertz Erneuerbar negative 194 1,019 08:August-13:August
Hannover-Linden GuD TenneT DE Konventionell positive 94 968 04:August-14:August
BAG NWAK-Cluster 16 Regensburg-Sittling TenneT DE Erneuerbar negative 111 945 07:August-16:August
BAG NWAK-Cluster 02 Oberhaid-Redwitz TenneT DE Erneuerbar negative 100 700 07:August-14:August
BAG NWAK-Cluster 06 Raitersaich TenneT DE Erneuerbar negative 100 700 07:August-14:August
illwerke vkw AG TransnetBW Sonstiges positive 315 630 06:August-08:August
Wilhelmshaven (ENGIE) TenneT DE Konventionell positive 142 602 07:August-11:August
Braunschweig HKWM GT31 TenneT DE Konventionell positive 36 555 22:August-13:August
Boxberg (Standort) 50Hertz Konventionell negative 177 532 05:August-08:August
WEISWEILER_H Amprion Konventionell positive 105 395 07:August-11:August
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 62 312 22:August-15:August
Jänschwalde (Standort) 50Hertz Konventionell negative 145 290 06:August-08:August
50H_AVA_CR_STW 50Hertz Erneuerbar negative 66 265 08:August-12:August
50H Berlin Marzahn 50Hertz Konventionell negative 33 265 23:August-15:August
Braunschweig HKWM GT31 TenneT DE Konventionell positive 47 259 07:August-12:August
50H_TEN_CR_M1_EI 50Hertz Erneuerbar negative 50 250 08:August-14:August
Jänschwalde (Standort) 50Hertz Konventionell negative 240 240 07:August-08:August
50H PV Witznitz 50Hertz Erneuerbar negative 61 229 08:August-13:August
HERDECKE_H6 Amprion Konventionell positive 138 207 07:August-08:August
Börse TransnetBW Sonstiges negative 42 190 04:August-22:August
Boxberg (Standort) 50Hertz Konventionell negative 135 169 06:August-08:August
50H Berlin Marzahn 50Hertz Konventionell negative 51 152 06:August-09:August
HAMMUENTROP_20 Amprion Konventionell positive 95 143 06:August-08:August
WEISWEILER_H Amprion Konventionell positive 76 114 06:August-08:August
Boxberg (Standort) 50Hertz Konventionell negative 96 96 15:August-16:August
Lippendorf 50Hertz Konventionell negative 86 86 15:August-16:August
Schkopau 50Hertz Konventionell negative 75 75 06:August-07:August
Netzreservekraftwerk GTKW-DA-POOL Amprion Konventionell positive 33 66 06:August-08:August
Netzreservekraftwerk GTKW-DA-POOL Amprion Konventionell positive 9 63 22:August-13:August
Schkopau 50Hertz Konventionell negative 74 56 15:August-15:August
Eltmann TenneT DE Konventionell negative 40 50 06:August-08:August
Börse TransnetBW Sonstiges positive 19 43 05:August-11:August
Jänschwalde (Standort) 50Hertz Konventionell negative 38 38 15:August-16:August
Börse 50Hertz Sonstiges positive 38 29 22:August-15:August
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 48 24 15:August-16:August
50H Erfurt-Ost HKW GuD 50Hertz Konventionell negative 17 21 07:August-08:August
Börse TenneT DE Sonstiges positive 28 14 06:August-07:August
50H UW Bertikow 50Hertz Erneuerbar negative 12 12 07:August-08:August
50H Chemnitz 50Hertz Konventionell negative 11 11 07:August-08:August
50H PV Haidemühl 50Hertz Erneuerbar negative 11 8 07:August-08:August
50H OWP Baltic Eagle 50Hertz Erneuerbar negative 7 6 07:August-08:August
Braunschweig HKWM GT31 TenneT DE Konventionell positive 22 6 21:August-22:August
50H Köthen 50Hertz Konventionell negative 2 2 06:August-07:August
Börse 50Hertz Sonstiges positive 2 2 06:August-07:August
50H UW Putlitz 50Hertz Erneuerbar negative 3 2 07:August-08:August
50H OWP Arkona 50Hertz Erneuerbar negative 1 0 07:August-08:August

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.38M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-08-13?

On 2026-08-13, estimated redispatch costs were approximately €1.25 million. This includes €0.35M for renewable curtailment compensation and €0.66M for conventional ramp-up costs.

Which power plants were most affected on 2026-08-13?

The most affected plant was BAG NWAK-Cluster 03 Bergrheinfeld-Schweinfurt (TenneT DE) with 1,400 MWh of negative redispatch.

What was the electricity spot price on 2026-08-13?

The EPEX Day-Ahead spot price for DE_LU ranged from 0 to 487 €/MWh with an average of 147 €/MWh.