50H Chemnitz

Konventionell50Hertz

470Total MWh
13Measures
15 MWAvg Power
13Curtailments
0Ramp-ups

Data: 2025-11-18 to 2026-05-16

Daily Redispatch Volume

DateMeasuresTotal MWh
2026-05-16 3 90
2026-05-15 3 45
2026-05-14 3 120
2026-05-13 3 210
2025-11-18 1 5

Recent Measures

DateTSODirAvg MWMWhTime
2026-05-16 50Hertz negative 15 30 18:May-20:May
2026-05-16 50Hertz negative 15 30 18:May-20:May
2026-05-16 50Hertz negative 15 30 18:May-20:May
2026-05-15 50Hertz negative 15 15 03:May-04:May
2026-05-15 50Hertz negative 15 15 03:May-04:May
2026-05-15 50Hertz negative 15 15 03:May-04:May
2026-05-14 50Hertz negative 20 40 00:May-02:May
2026-05-14 50Hertz negative 20 40 00:May-02:May
2026-05-14 50Hertz negative 20 40 00:May-02:May
2026-05-13 50Hertz negative 14 70 08:May-13:May
2026-05-13 50Hertz negative 14 70 08:May-13:May
2026-05-13 50Hertz negative 14 70 08:May-13:May
2025-11-18 50Hertz negative 5 5 12:November-13:November

Frequently Asked Questions

What is the redispatch history of 50H Chemnitz?

50H Chemnitz is a Konventionell power plant in the 50Hertz grid zone. It has received 13 redispatch instructions totaling 470 MWh since 2025-11-18.

Why is 50H Chemnitz frequently redispatched?

Plants in the 50Hertz zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.