← 2026-06-11

Friday, June 12, 2026

2026-06-13 →
2,096MWh Curtailed
2,040MWh Ramped Up
€0.57MEst. Cost
135 MWPeak Positive

Day-Ahead Spot: 51-134 €/MWh (avg 95)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TransnetBW positive 18 20,457
TenneT DE negative 14 19,949
TenneT DE positive 11 19,317
Amprion positive 13 14,096
50Hertz negative 28 6,179
50Hertz positive 9 2,471
Amprion negative 6 756
TransnetBW negative 2 218

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
Börse TenneT DE Sonstiges positive 916 14,650 05:June-21:June
UW Büttel TenneT DE Erneuerbar negative 812 6,902 13:June-21:June
Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 TransnetBW Konventionell positive 322 3,869 10:June-22:June
Heizkraftwerk Altbach/Deizisau Block 2 TransnetBW Konventionell positive 272 3,125 03:June-15:June
UW Dörpen-West TenneT DE Erneuerbar negative 396 3,068 09:June-18:June
SHN Cluster Kiel Süd TenneT DE Erneuerbar negative 132 2,968 22:June-22:June
Emsland Block C Amprion Konventionell positive 275 2,748 09:June-19:June
Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 TransnetBW Konventionell positive 309 2,704 22:June-06:June
NEURATH_F Amprion Konventionell positive 241 2,466 23:June-22:June
Grosskraftwerk Mannheim Block 6 TransnetBW Konventionell positive 100 2,400 22:June-22:June
Boxberg (Standort) 50Hertz Konventionell negative 316 2,212 05:June-12:June
Irsching 4 TenneT DE Konventionell positive 291 2,113 11:June-18:June
Netzreservekraftwerk Bexbach A Amprion Konventionell positive 205 2,104 04:June-15:June
AVA Cluster Voslapp TenneT DE Erneuerbar negative 347 2,080 12:June-18:June
NIEHL-II Amprion Konventionell positive 187 1,968 11:June-21:June
Grosskraftwerk Mannheim Block 6 TransnetBW Konventionell positive 81 1,773 00:June-22:June
Netzreservekraftwerk Bexbach A Amprion Konventionell positive 247 1,728 15:June-22:June
Knapsack 1 Amprion Konventionell positive 394 1,577 15:June-19:June
UW Diele TenneT DE Erneuerbar negative 193 1,498 09:June-18:June
Heizkraftwerk Altbach/Deizisau Block 2 TransnetBW Konventionell positive 166 1,370 22:June-06:June
Heizkraftwerk Altbach/Deizisau Block 2 TransnetBW Konventionell positive 191 1,335 15:June-22:June
Grosskraftwerk Mannheim Block 7 TransnetBW Konventionell positive 88 1,315 07:June-22:June
Hannover-Linden GuD TenneT DE Konventionell positive 147 920 12:June-18:June
illwerke vkw AG TransnetBW Sonstiges positive 180 898 10:June-15:June
Boxberg (Standort) 50Hertz Konventionell negative 167 834 22:June-19:June
SHN Cluster Lübeck TenneT DE Erneuerbar negative 33 742 22:June-22:June
Schkopau 50Hertz Konventionell positive 123 740 13:June-19:June
UW Büttel TenneT DE Erneuerbar negative 154 732 22:June-05:June
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 117 700 05:June-11:June
Heizkraftwerk Stuttgart-Münster GT 88 TransnetBW Konventionell positive 52 620 05:June-17:June
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 305 610 20:June-22:June
Schwarze Pumpe (Standort) 50Hertz Konventionell positive 284 567 13:June-15:June
Irsching 4 TenneT DE Konventionell positive 175 525 14:June-17:June
AVA Cluster Lehrte TenneT DE Erneuerbar negative 163 490 15:June-18:June
SHN Cluster Heide West T411 T412 TenneT DE Erneuerbar negative 158 473 15:June-18:June
Heizkraftwerk Stuttgart-Münster GT 87 TransnetBW Konventionell positive 52 420 09:June-17:June
NIEDERAUSSEM_G Amprion Konventionell positive 126 409 13:June-16:June
Boxberg (Standort) 50Hertz Konventionell negative 200 400 20:June-22:June
50H Berlin Marzahn 50Hertz Konventionell negative 62 373 04:June-22:June
Boxberg (Standort) 50Hertz Konventionell positive 146 364 13:June-16:June
SHN Cluster Süderdonn T412 T413 TenneT DE Erneuerbar negative 101 353 14:June-18:June
Irsching 4 TenneT DE Konventionell positive 189 330 10:June-12:June
Netzreservekraftwerk Bexbach A Amprion Konventionell positive 143 322 06:June-09:June
Datteln_4 Amprion Konventionell negative 142 320 04:June-22:June
50H Berlin Marzahn 50Hertz Konventionell positive 57 285 13:June-19:June
Hannover-Linden GuD TenneT DE Konventionell positive 85 275 17:June-20:June
Datteln_4 Amprion Konventionell positive 272 272 14:June-15:June
NEURATH_F Amprion Konventionell negative 146 256 22:June-23:June
Schkopau 50Hertz Konventionell positive 81 243 07:June-17:June
Börse TransnetBW Sonstiges negative 28 203 00:June-19:June

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.17M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-06-12?

On 2026-06-12, estimated redispatch costs were approximately €0.57 million. This includes €0.21M for renewable curtailment compensation and €0.26M for conventional ramp-up costs.

Which power plants were most affected on 2026-06-12?

The most affected plant was Börse (TenneT DE) with 14,650 MWh of positive redispatch.

What was the electricity spot price on 2026-06-12?

The EPEX Day-Ahead spot price for DE_LU ranged from 51 to 134 €/MWh with an average of 95 €/MWh.