2,096MWh Curtailed
2,040MWh Ramped Up
€0.57MEst. Cost
135 MWPeak Positive
Day-Ahead Spot: 51-134 €/MWh (avg 95)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| TransnetBW | positive | 18 | 20,457 |
| TenneT DE | negative | 14 | 19,949 |
| TenneT DE | positive | 11 | 19,317 |
| Amprion | positive | 13 | 14,096 |
| 50Hertz | negative | 28 | 6,179 |
| 50Hertz | positive | 9 | 2,471 |
| Amprion | negative | 6 | 756 |
| TransnetBW | negative | 2 | 218 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Börse | TenneT DE | Sonstiges | positive | 916 | 14,650 | 05:June-21:June |
| UW Büttel | TenneT DE | negative | 812 | 6,902 | 13:June-21:June | |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 322 | 3,869 | 10:June-22:June |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 272 | 3,125 | 03:June-15:June |
| UW Dörpen-West | TenneT DE | negative | 396 | 3,068 | 09:June-18:June | |
| SHN Cluster Kiel Süd | TenneT DE | negative | 132 | 2,968 | 22:June-22:June | |
| Emsland Block C | Amprion | Konventionell | positive | 275 | 2,748 | 09:June-19:June |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 309 | 2,704 | 22:June-06:June |
| NEURATH_F | Amprion | Konventionell | positive | 241 | 2,466 | 23:June-22:June |
| Grosskraftwerk Mannheim Block 6 | TransnetBW | Konventionell | positive | 100 | 2,400 | 22:June-22:June |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 316 | 2,212 | 05:June-12:June |
| Irsching 4 | TenneT DE | Konventionell | positive | 291 | 2,113 | 11:June-18:June |
| Netzreservekraftwerk Bexbach A | Amprion | Konventionell | positive | 205 | 2,104 | 04:June-15:June |
| AVA Cluster Voslapp | TenneT DE | negative | 347 | 2,080 | 12:June-18:June | |
| NIEHL-II | Amprion | Konventionell | positive | 187 | 1,968 | 11:June-21:June |
| Grosskraftwerk Mannheim Block 6 | TransnetBW | Konventionell | positive | 81 | 1,773 | 00:June-22:June |
| Netzreservekraftwerk Bexbach A | Amprion | Konventionell | positive | 247 | 1,728 | 15:June-22:June |
| Knapsack 1 | Amprion | Konventionell | positive | 394 | 1,577 | 15:June-19:June |
| UW Diele | TenneT DE | negative | 193 | 1,498 | 09:June-18:June | |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 166 | 1,370 | 22:June-06:June |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 191 | 1,335 | 15:June-22:June |
| Grosskraftwerk Mannheim Block 7 | TransnetBW | Konventionell | positive | 88 | 1,315 | 07:June-22:June |
| Hannover-Linden GuD | TenneT DE | Konventionell | positive | 147 | 920 | 12:June-18:June |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 180 | 898 | 10:June-15:June |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 167 | 834 | 22:June-19:June |
| SHN Cluster Lübeck | TenneT DE | negative | 33 | 742 | 22:June-22:June | |
| Schkopau | 50Hertz | Konventionell | positive | 123 | 740 | 13:June-19:June |
| UW Büttel | TenneT DE | negative | 154 | 732 | 22:June-05:June | |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 117 | 700 | 05:June-11:June |
| Heizkraftwerk Stuttgart-Münster GT 88 | TransnetBW | Konventionell | positive | 52 | 620 | 05:June-17:June |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 305 | 610 | 20:June-22:June |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | positive | 284 | 567 | 13:June-15:June |
| Irsching 4 | TenneT DE | Konventionell | positive | 175 | 525 | 14:June-17:June |
| AVA Cluster Lehrte | TenneT DE | negative | 163 | 490 | 15:June-18:June | |
| SHN Cluster Heide West T411 T412 | TenneT DE | negative | 158 | 473 | 15:June-18:June | |
| Heizkraftwerk Stuttgart-Münster GT 87 | TransnetBW | Konventionell | positive | 52 | 420 | 09:June-17:June |
| NIEDERAUSSEM_G | Amprion | Konventionell | positive | 126 | 409 | 13:June-16:June |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 200 | 400 | 20:June-22:June |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 62 | 373 | 04:June-22:June |
| Boxberg (Standort) | 50Hertz | Konventionell | positive | 146 | 364 | 13:June-16:June |
| SHN Cluster Süderdonn T412 T413 | TenneT DE | negative | 101 | 353 | 14:June-18:June | |
| Irsching 4 | TenneT DE | Konventionell | positive | 189 | 330 | 10:June-12:June |
| Netzreservekraftwerk Bexbach A | Amprion | Konventionell | positive | 143 | 322 | 06:June-09:June |
| Datteln_4 | Amprion | Konventionell | negative | 142 | 320 | 04:June-22:June |
| 50H Berlin Marzahn | 50Hertz | Konventionell | positive | 57 | 285 | 13:June-19:June |
| Hannover-Linden GuD | TenneT DE | Konventionell | positive | 85 | 275 | 17:June-20:June |
| Datteln_4 | Amprion | Konventionell | positive | 272 | 272 | 14:June-15:June |
| NEURATH_F | Amprion | Konventionell | negative | 146 | 256 | 22:June-23:June |
| Schkopau | 50Hertz | Konventionell | positive | 81 | 243 | 07:June-17:June |
| Börse | TransnetBW | Sonstiges | negative | 28 | 203 | 00:June-19:June |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.17M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-06-12?
On 2026-06-12, estimated redispatch costs were approximately €0.57 million. This includes €0.21M for renewable curtailment compensation and €0.26M for conventional ramp-up costs.
Which power plants were most affected on 2026-06-12?
The most affected plant was Börse (TenneT DE) with 14,650 MWh of positive redispatch.
What was the electricity spot price on 2026-06-12?
The EPEX Day-Ahead spot price for DE_LU ranged from 51 to 134 €/MWh with an average of 95 €/MWh.