SHN Cluster Lübeck

ErneuerbarTenneT DE

9,618Total MWh
26Measures
70 MWAvg Power
26Curtailments
0Ramp-ups

Data: 2024-04-09 to 2026-04-20

Daily Redispatch Volume

DateMeasuresTotal MWh
2026-04-20 2 1,071
2025-11-11 1 549
2025-11-05 1 482
2025-11-03 1 1,050
2025-11-02 2 1,037
2025-11-01 1 129
2025-10-05 1 119
2025-08-05 2 1,223
2025-08-04 2 465
2025-08-03 1 93
2025-07-29 4 1,108
2025-07-28 1 480
2025-07-05 2 288
2025-06-12 2 362
2025-06-10 1 166
2025-05-29 1 444
2024-04-09 1 550

Recent Measures

DateTSODirAvg MWMWhTime
2026-04-20 TenneT DE negative 126 536 11:April-15:April
2026-04-20 TenneT DE negative 126 536 11:April-15:April
2025-11-11 TenneT DE negative 59 549 23:November-09:November
2025-11-05 TenneT DE negative 58 482 00:November-08:November
2025-11-03 TenneT DE negative 70 1,050 23:November-14:November
2025-11-02 TenneT DE negative 57 799 23:November-23:November
2025-11-02 TenneT DE negative 43 238 05:November-11:November
2025-11-01 TenneT DE negative 52 129 05:November-08:November
2025-10-05 TenneT DE negative 119 119 22:October-23:October
2025-08-05 TenneT DE negative 108 515 16:August-21:August
2025-08-05 TenneT DE negative 105 707 08:August-15:August
2025-08-04 TenneT DE negative 100 175 22:August-23:August
2025-08-04 TenneT DE negative 105 290 19:August-22:August
2025-08-03 TenneT DE negative 53 93 03:August-05:August
2025-07-29 TenneT DE negative 50 600 22:July-10:July
2025-07-29 TenneT DE negative 50 12 21:July-22:July
2025-07-29 TenneT DE negative 50 300 14:July-20:July
2025-07-29 TenneT DE negative 65 196 08:July-11:July
2025-07-28 TenneT DE negative 74 480 13:July-20:July
2025-07-05 TenneT DE negative 40 111 18:July-21:July
2025-07-05 TenneT DE negative 42 178 01:July-06:July
2025-06-12 TenneT DE negative 46 325 22:June-05:June
2025-06-12 TenneT DE negative 50 38 21:June-22:June
2025-06-10 TenneT DE negative 60 166 19:June-22:June
2025-05-29 TenneT DE negative 63 444 23:May-06:May
2024-04-09 TenneT DE negative 55 550 23:April-09:April

Frequently Asked Questions

What is the redispatch history of SHN Cluster Lübeck?

SHN Cluster Lübeck is a Erneuerbar power plant in the TenneT DE grid zone. It has received 26 redispatch instructions totaling 9,618 MWh since 2024-04-09.

Why is SHN Cluster Lübeck frequently redispatched?

Plants in the TenneT DE zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.