2,932MWh Curtailed
3,165MWh Ramped Up
€0.99MEst. Cost
277 MWPeak Positive
Day-Ahead Spot: 86-422 €/MWh (avg 152)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| Amprion | positive | 4 | 12,208 |
| Amprion | negative | 13 | 9,922 |
| TransnetBW | positive | 6 | 9,297 |
| TenneT DE | negative | 5 | 1,033 |
| 50Hertz | negative | 1 | 70 |
| 50Hertz | positive | 1 | 4 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Knapsack 1 | Amprion | Konventionell | negative | 771 | 6,938 | 22:June-07:June |
| Netzreservekraftwerk Bexbach A | Amprion | Konventionell | positive | 372 | 6,138 | 22:June-20:June |
| Netzreservekraftwerk Bexbach A | Amprion | Konventionell | positive | 495 | 5,815 | 10:June-22:June |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 347 | 3,038 | 13:June-22:June |
| Reservekraftwerk Altbach/Deizisau Block 1 | TransnetBW | Konventionell | positive | 310 | 3,025 | 22:June-07:June |
| Reservekraftwerk Altbach/Deizisau Block 1 | TransnetBW | Konventionell | positive | 245 | 1,590 | 13:June-22:June |
| NIEDERAUSSEM_G | Amprion | Konventionell | negative | 216 | 1,242 | 10:June-16:June |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 247 | 802 | 14:June-18:June |
| SHN Cluster Kiel Süd | TenneT DE | negative | 93 | 701 | 22:June-14:June | |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 257 | 642 | 22:June-00:June |
| WALSUM_10 | Amprion | Konventionell | negative | 215 | 591 | 13:June-16:June |
| NIEHL-31-GUD | Amprion | Konventionell | negative | 183 | 365 | 14:June-16:June |
| NIEDERAUSSEM_H | Amprion | Konventionell | negative | 126 | 251 | 13:June-16:June |
| Börse | Amprion | Konventionell | positive | 147 | 220 | 16:June-18:June |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 200 | 200 | 04:June-05:June |
| Knapsack 1 | Amprion | Konventionell | negative | 175 | 175 | 15:June-16:June |
| SHN Cluster Lübeck | TenneT DE | negative | 23 | 174 | 22:June-14:June | |
| HAMMUENTROP_20 | Amprion | Konventionell | negative | 106 | 106 | 22:June-23:June |
| UW Büttel | TenneT DE | negative | 119 | 89 | 22:June-22:June | |
| 50H_WEMA_CR_GOE | 50Hertz | negative | 40 | 70 | 11:June-13:June | |
| Börse | Amprion | Konventionell | negative | 122 | 61 | 15:June-19:June |
| NIEDERAUSSEM_K | Amprion | Konventionell | negative | 74 | 56 | 14:June-16:June |
| WEISWEILER_G | Amprion | Konventionell | negative | 100 | 50 | 15:June-16:June |
| GUD_HERNE_6 | Amprion | Konventionell | negative | 150 | 38 | 15:June-16:June |
| BIBLIS_GT (bnBm) | Amprion | Konventionell | positive | 14 | 35 | 08:June-14:June |
| UW Diele | TenneT DE | negative | 70 | 35 | 22:June-22:June | |
| UW Emden-Ost | TenneT DE | negative | 70 | 35 | 22:June-22:June | |
| CHEMIEPARK_MARL_KRAFTWERKE | Amprion | Konventionell | negative | 13 | 29 | 08:June-14:June |
| CHEMIEPARK_MARL_KRAFTWERKE | Amprion | Konventionell | negative | 40 | 20 | 14:June-16:June |
| Börse | 50Hertz | Sonstiges | positive | 5 | 4 | 23:June-03:June |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.3M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-06-01?
On 2026-06-01, estimated redispatch costs were approximately €0.99 million. This includes €0.29M for renewable curtailment compensation and €0.58M for conventional ramp-up costs.
Which power plants were most affected on 2026-06-01?
The most affected plant was Knapsack 1 (Amprion) with 6,938 MWh of negative redispatch.
What was the electricity spot price on 2026-06-01?
The EPEX Day-Ahead spot price for DE_LU ranged from 86 to 422 €/MWh with an average of 152 €/MWh.