2,306MWh Curtailed
2,466MWh Ramped Up
€0.73MEst. Cost
179 MWPeak Positive
Day-Ahead Spot: 16-195 €/MWh (avg 106)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| Amprion | positive | 12 | 9,736 |
| TransnetBW | positive | 8 | 5,383 |
| TenneT DE | negative | 14 | 5,123 |
| Amprion | negative | 12 | 3,631 |
| TransnetBW | negative | 3 | 409 |
| 50Hertz | positive | 1 | 5 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 266 | 3,194 | 22:June-10:June |
| Netzreservekraftwerk Bexbach A | Amprion | Konventionell | positive | 430 | 2,150 | 22:June-03:June |
| Knapsack 1 | Amprion | Konventionell | positive | 343 | 1,889 | 00:June-05:June |
| Datteln_4 | Amprion | Konventionell | negative | 266 | 1,862 | 22:June-07:June |
| NIEHL-II | Amprion | Konventionell | positive | 163 | 1,304 | 22:June-06:June |
| SHN Cluster Kiel Süd | TenneT DE | negative | 62 | 1,182 | 22:June-20:June | |
| Emsland Block C | Amprion | Konventionell | positive | 275 | 1,168 | 22:June-02:June |
| BAG NWAK-Cluster 15 Pleinting | TenneT DE | negative | 200 | 1,100 | 09:June-14:June | |
| BAG NWAK-Cluster 17 Altheim | TenneT DE | negative | 200 | 1,100 | 09:June-14:June | |
| Emsland Block B | Amprion | Konventionell | positive | 196 | 980 | 22:June-03:June |
| Emsland Block C | Amprion | Konventionell | positive | 293 | 880 | 19:June-22:June |
| SHN Cluster Kiel Süd | TenneT DE | negative | 126 | 817 | 00:June-14:June | |
| Börse | Amprion | Konventionell | positive | 292 | 585 | 18:June-20:June |
| GUD_HERNE_6 | Amprion | Konventionell | negative | 141 | 565 | 22:June-03:June |
| LAUSWARD_GUDF | Amprion | Konventionell | negative | 133 | 500 | 22:June-04:June |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 84 | 482 | 00:June-05:June |
| NIEDERAUSSEM_K | Amprion | Konventionell | negative | 186 | 464 | 22:June-00:June |
| Kraftwerk Walheim GT D | TransnetBW | Konventionell | positive | 106 | 452 | 17:June-22:June |
| Börse | TransnetBW | Sonstiges | positive | 97 | 341 | 23:June-14:June |
| Netzreservekraftwerk GTKW-DA-POOL | Amprion | Konventionell | positive | 72 | 290 | 18:June-22:June |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 114 | 285 | 18:June-22:June |
| Netzreservekraftwerk Bexbach A | Amprion | Konventionell | positive | 250 | 250 | 21:June-22:June |
| illwerke vkw AG | TransnetBW | Sonstiges | negative | 232 | 232 | 22:June-02:June |
| Heizkraftwerk Stuttgart-Münster GT 87 | TransnetBW | Konventionell | positive | 53 | 225 | 17:June-21:June |
| Heizkraftwerk Stuttgart-Münster GT 88 | TransnetBW | Konventionell | positive | 52 | 210 | 17:June-21:June |
| SHN Cluster Lübeck | TenneT DE | negative | 31 | 203 | 00:June-14:June | |
| Heizkraftwerk Altbach/Deizisau GT E | TransnetBW | Konventionell | positive | 56 | 195 | 17:June-21:June |
| Reisach | TenneT DE | Sonstiges | negative | 81 | 142 | 23:June-00:June |
| SHN Cluster Lübeck | TenneT DE | negative | 7 | 138 | 22:June-20:June | |
| Börse | TransnetBW | Sonstiges | negative | 97 | 121 | 03:June-05:June |
| BASF-GESAMTEINSPEISG | Amprion | Konventionell | positive | 30 | 120 | 18:June-22:June |
| HERDECKE_H6 | Amprion | Konventionell | negative | 48 | 120 | 22:June-03:June |
| Kiel (Küstenkraftwerk gesamt) | TenneT DE | Konventionell | negative | 110 | 110 | 05:June-06:June |
| UW Dörpen-West | TenneT DE | negative | 109 | 109 | 05:June-06:June | |
| Börse | Amprion | Konventionell | positive | 188 | 94 | 00:June-00:June |
| UW Diele | TenneT DE | negative | 88 | 66 | 05:June-06:June | |
| Börse | TransnetBW | Sonstiges | negative | 22 | 56 | 23:June-10:June |
| UW Büttel | TenneT DE | negative | 98 | 49 | 05:June-05:June | |
| UW Büttel | TenneT DE | negative | 44 | 44 | 23:June-01:June | |
| Tanzmühle | TenneT DE | Sonstiges | negative | 24 | 42 | 23:June-00:June |
| CHEMIEPARK_MARL_KRAFTWERKE | Amprion | Konventionell | negative | 37 | 28 | 17:June-18:June |
| NIEHL-II | Amprion | Konventionell | positive | 26 | 26 | 21:June-22:June |
| GUD_HERNE_6 | Amprion | Konventionell | negative | 26 | 26 | 21:June-22:June |
| Emsland Block C | Amprion | Konventionell | negative | 89 | 22 | 17:June-18:June |
| UW Emden-Ost | TenneT DE | negative | 20 | 20 | 23:June-02:June | |
| HERDECKE_H6 | Amprion | Konventionell | negative | 15 | 15 | 17:June-18:June |
| LAUSWARD_GUDF | Amprion | Konventionell | negative | 56 | 14 | 17:June-18:June |
| INFRA_HOE_GTX8 | Amprion | Konventionell | negative | 18 | 9 | 17:June-18:June |
| EGM_DTS | Amprion | Sonstiges | negative | 12 | 6 | 17:June-18:June |
| Börse | 50Hertz | Sonstiges | positive | 7 | 5 | 06:June-11:June |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.22M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-06-05?
On 2026-06-05, estimated redispatch costs were approximately €0.73 million. This includes €0.23M for renewable curtailment compensation and €0.34M for conventional ramp-up costs.
Which power plants were most affected on 2026-06-05?
The most affected plant was Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 (TransnetBW) with 3,194 MWh of positive redispatch.
What was the electricity spot price on 2026-06-05?
The EPEX Day-Ahead spot price for DE_LU ranged from 16 to 195 €/MWh with an average of 106 €/MWh.