← 2026-07-07

Wednesday, July 8, 2026

2026-07-09 →
2,217MWh Curtailed
3,041MWh Ramped Up
€0.94MEst. Cost
185 MWPeak Positive

Day-Ahead Spot: 5-169 €/MWh (avg 101)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TenneT DE negative 29 54,375
50Hertz negative 34 33,836
Amprion positive 22 17,811
TransnetBW positive 14 8,313
TenneT DE positive 5 7,260
Amprion negative 6 1,406
50Hertz positive 6 207
TransnetBW negative 1 50

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
UW Büttel TenneT DE Erneuerbar negative 783 12,529 04:July-20:July
SHN Cluster Heide West T411 T412 TenneT DE Erneuerbar negative 596 6,410 06:July-16:July
SHN Cluster Klixbüll TenneT DE Erneuerbar negative 424 4,343 06:July-16:July
50H_EDIS_CR_WU_NORD 50Hertz Erneuerbar negative 341 4,088 06:July-18:July
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 342 3,842 10:July-21:July
50H_AVA_CR_STW 50Hertz Erneuerbar negative 375 3,379 06:July-15:July
50H_AVA_CR_WOL 50Hertz Erneuerbar negative 358 3,218 06:July-15:July
50H OWP Arkona 50Hertz Erneuerbar negative 346 3,201 05:July-16:July
Börse TenneT DE Sonstiges positive 798 3,190 22:July-02:July
50H OWP Baltic Eagle 50Hertz Erneuerbar negative 332 3,153 05:July-16:July
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 341 3,072 00:July-19:July
Börse TenneT DE Sonstiges positive 437 3,056 06:July-13:July
SHN Cluster Schuby West TenneT DE Erneuerbar negative 270 2,831 06:July-16:July
LAUSWARD_GUDF Amprion Konventionell positive 413 2,683 04:July-10:July
SHN Cluster Husum Nord TenneT DE Erneuerbar negative 329 2,632 06:July-14:July
50H_EDIS_CR_SOW_Sued 50Hertz Erneuerbar negative 255 2,612 06:July-16:July
HAMMUENTROP_20 Amprion Konventionell positive 307 2,460 08:July-16:July
50H PV Witznitz 50Hertz Erneuerbar negative 326 2,449 05:July-15:July
UW Emden-Ost TenneT DE Erneuerbar negative 288 2,308 08:July-16:July
NIEHL-31-GUD Amprion Konventionell positive 217 2,174 07:July-17:July
SHN Cluster Kiel Süd TenneT DE Erneuerbar negative 319 2,151 07:July-14:July
illwerke vkw AG TransnetBW Sonstiges positive 300 2,102 06:July-21:July
50H OWP Arcadis Ost 1 50Hertz Erneuerbar negative 217 2,060 05:July-16:July
AVA Cluster Mehringen TenneT DE Erneuerbar negative 190 1,998 06:July-16:July
UW Dörpen-West TenneT DE Erneuerbar negative 273 1,909 08:July-15:July
NEURATH_G Amprion Konventionell positive 220 1,868 07:July-16:July
GUD_HERNE_6 Amprion Konventionell positive 308 1,850 10:July-16:July
SHN Cluster Handewitt T414 T415 TenneT DE Erneuerbar negative 268 1,806 06:July-12:July
HAMMUENTROP_20 Amprion Konventionell positive 220 1,651 03:July-10:July
AVA Cluster Ohlensehlen TenneT DE Erneuerbar negative 160 1,642 06:July-16:July
AVA Cluster Alfstedt TenneT DE Erneuerbar negative 380 1,519 08:July-12:July
AVA Cluster Lehrte TenneT DE Erneuerbar negative 177 1,464 08:July-16:July
50H_EDIS_CR_PE 50Hertz Erneuerbar negative 188 1,406 06:July-13:July
50H UW Bertikow 50Hertz Erneuerbar negative 169 1,392 05:July-16:July
UW Diele TenneT DE Erneuerbar negative 189 1,323 08:July-15:July
UW Büttel TenneT DE Erneuerbar negative 367 1,193 17:July-20:July
SHN Cluster Kiel Süd TenneT DE Erneuerbar negative 259 1,100 12:July-16:July
50H_EDIS_CR_HND 50Hertz Erneuerbar negative 115 1,035 07:July-16:July
GUD_HERNE_6 Amprion Konventionell positive 223 1,004 10:July-15:July
AVA Cluster Twistetal TenneT DE Erneuerbar negative 159 913 12:July-18:July
WEISWEILER_H Amprion Konventionell positive 221 885 16:July-20:July
50H OWP Wikinger 50Hertz Erneuerbar negative 108 861 08:July-16:July
ReserveKW Staudinger 4 TenneT DE Konventionell positive 194 826 14:July-18:July
Heizkraftwerk Altbach/Deizisau Block 2 TransnetBW Konventionell positive 105 814 00:July-17:July
HAMMUENTROP_20 Amprion Konventionell positive 153 613 04:July-09:July
illwerke vkw AG TransnetBW Sonstiges positive 204 612 17:July-20:July
50H UW Putlitz 50Hertz Erneuerbar negative 54 598 05:July-16:July
Netzreservekraftwerk GTKW-DA-POOL Amprion Konventionell positive 70 560 08:July-16:July
WP Schafflund TenneT DE Erneuerbar negative 51 556 05:July-16:July
50H OWP Baltic 1+2 50Hertz Erneuerbar negative 134 536 09:July-15:July

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.28M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-07-08?

On 2026-07-08, estimated redispatch costs were approximately €0.94 million. This includes €0.22M for renewable curtailment compensation and €0.4M for conventional ramp-up costs.

Which power plants were most affected on 2026-07-08?

The most affected plant was UW Büttel (TenneT DE) with 12,529 MWh of negative redispatch.

What was the electricity spot price on 2026-07-08?

The EPEX Day-Ahead spot price for DE_LU ranged from 5 to 169 €/MWh with an average of 101 €/MWh.