1,263MWh Curtailed
1,823MWh Ramped Up
€0.63MEst. Cost
199 MWPeak Positive
Day-Ahead Spot: -1-150 €/MWh (avg 64)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| 50Hertz | negative | 25 | 13,349 |
| TenneT DE | positive | 3 | 7,306 |
| TenneT DE | negative | 9 | 6,259 |
| TransnetBW | positive | 3 | 2,000 |
| Amprion | positive | 3 | 1,803 |
| Amprion | negative | 1 | 690 |
| TransnetBW | negative | 1 | 553 |
| 50Hertz | positive | 1 | 52 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Börse | TenneT DE | Sonstiges | positive | 902 | 6,762 | 22:July-22:July |
| UW Büttel | TenneT DE | negative | 534 | 3,869 | 04:July-18:July | |
| 50H_EDIS_CR_WU | 50Hertz | negative | 348 | 3,475 | 07:July-17:July | |
| 50H_EDIS_CR_PAS | 50Hertz | negative | 238 | 2,852 | 06:July-18:July | |
| Grosskraftwerk Mannheim Block 6 | TransnetBW | Konventionell | positive | 82 | 1,892 | 23:July-22:July |
| 50H_EDIS_CR_LV_WU | 50Hertz | negative | 215 | 1,662 | 07:July-14:July | |
| GERSTEINW_F (KapRes) | Amprion | Konventionell | positive | 141 | 1,163 | 11:July-19:July |
| 50H_WEMA_CR_GOE | 50Hertz | negative | 131 | 1,050 | 07:July-15:July | |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 255 | 1,020 | 02:July-20:July |
| 50H_EDIS_CR_SOW_Sued | 50Hertz | negative | 129 | 938 | 10:July-17:July | |
| SHN Cluster Kiel Süd | TenneT DE | negative | 134 | 938 | 10:July-18:July | |
| NEURATH_F | Amprion | Konventionell | negative | 115 | 690 | 16:July-22:July |
| AVA Cluster Helmstedt | TenneT DE | negative | 109 | 625 | 06:July-12:July | |
| Börse | TransnetBW | Sonstiges | negative | 76 | 553 | 05:July-20:July |
| Hannover-Linden GuD | TenneT DE | Konventionell | positive | 98 | 488 | 17:July-22:July |
| Rostock Kohlekraftwerk | 50Hertz | Konventionell | negative | 121 | 483 | 18:July-22:July |
| NEURATH_F | Amprion | Konventionell | positive | 153 | 420 | 04:July-07:July |
| 50H_EDIS_CR_LHG | 50Hertz | negative | 96 | 338 | 12:July-16:July | |
| WP Schafflund | TenneT DE | negative | 42 | 250 | 05:July-17:July | |
| SHN Cluster Süderdonn T411 | TenneT DE | negative | 151 | 226 | 15:July-17:July | |
| Emsland Block C | Amprion | Konventionell | positive | 55 | 220 | 17:July-21:July |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 210 | 210 | 17:July-18:July |
| 50H_EDIS_CR_HND | 50Hertz | negative | 44 | 208 | 09:July-14:July | |
| 50H Dresden-Reick | 50Hertz | Konventionell | negative | 48 | 194 | 03:July-19:July |
| 50H_AVA_CR_FOE | 50Hertz | negative | 92 | 138 | 08:July-10:July | |
| 50H BASF Schwarzheide | 50Hertz | Konventionell | negative | 15 | 137 | 00:July-22:July |
| UW Büttel | TenneT DE | negative | 68 | 135 | 15:July-17:July | |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 48 | 97 | 17:July-19:July |
| 50H Halle-Dieselstr HKW-BlockC | 50Hertz | Konventionell | negative | 24 | 94 | 16:July-22:July |
| 50H OWP Wikinger | 50Hertz | negative | 186 | 93 | 05:July-05:July | |
| 50H UW Wessin | 50Hertz | negative | 29 | 88 | 04:July-17:July | |
| WP Schafflund | TenneT DE | negative | 28 | 85 | 01:July-04:July | |
| AVA Cluster Mehringen | TenneT DE | negative | 78 | 78 | 16:July-17:July | |
| Heizkraftwerk_Pforzheim | TransnetBW | Konventionell | positive | 12 | 72 | 01:July-20:July |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 80 | 60 | 22:July-22:July |
| Robert Frank 4 GT (KapRes) | TenneT DE | Konventionell | positive | 28 | 56 | 16:July-18:July |
| Börse | TenneT DE | Sonstiges | negative | 212 | 53 | 19:July-19:July |
| Börse | 50Hertz | Sonstiges | positive | 34 | 52 | 23:July-21:July |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 15 | 45 | 23:July-02:July |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 43 | 43 | 16:July-17:July |
| 50H Hamburg MMB BHKW PtH | 50Hertz | Konventionell | negative | 9 | 36 | 17:July-22:July |
| Börse | TransnetBW | Sonstiges | positive | 72 | 36 | 17:July-20:July |
| 50H UW Bertikow | 50Hertz | negative | 70 | 35 | 05:July-05:July | |
| 50H Rostock Marienehe | 50Hertz | Konventionell | negative | 26 | 26 | 18:July-19:July |
| 50H OWP Arkona | 50Hertz | negative | 31 | 23 | 04:July-05:July | |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 15 | 4 | 21:July-21:July |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.19M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-07-05?
On 2026-07-05, estimated redispatch costs were approximately €0.63 million. This includes €0.13M for renewable curtailment compensation and €0.17M for conventional ramp-up costs.
Which power plants were most affected on 2026-07-05?
The most affected plant was Börse (TenneT DE) with 6,762 MWh of positive redispatch.
What was the electricity spot price on 2026-07-05?
The EPEX Day-Ahead spot price for DE_LU ranged from -1 to 150 €/MWh with an average of 64 €/MWh.