2,268MWh Curtailed
2,567MWh Ramped Up
€0.88MEst. Cost
189 MWPeak Positive
Day-Ahead Spot: 1-156 €/MWh (avg 98)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| Amprion | positive | 27 | 48,927 |
| TenneT DE | negative | 16 | 35,071 |
| 50Hertz | negative | 18 | 34,046 |
| TenneT DE | positive | 3 | 18,076 |
| TransnetBW | positive | 8 | 7,884 |
| Amprion | negative | 4 | 2,768 |
| TransnetBW | negative | 2 | 462 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Börse | TenneT DE | Sonstiges | positive | 1025 | 15,625 | 22:July-22:July |
| WEISWEILER_H | Amprion | Konventionell | positive | 338 | 8,100 | 22:July-22:July |
| UW Dörpen-West | TenneT DE | negative | 477 | 6,913 | 04:July-18:July | |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 635 | 6,190 | 22:July-22:July |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 631 | 5,991 | 22:July-07:July |
| UW Büttel | TenneT DE | negative | 661 | 5,948 | 12:July-22:July | |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 478 | 5,738 | 22:July-22:July |
| 50H_EDIS_CR_PAS | 50Hertz | negative | 216 | 5,018 | 22:July-22:July | |
| WALSUM_10 | Amprion | Konventionell | positive | 368 | 4,880 | 22:July-22:July |
| AVA Cluster Voslapp | TenneT DE | negative | 364 | 4,000 | 09:July-20:July | |
| WEISWEILER_G | Amprion | Konventionell | positive | 420 | 3,987 | 12:July-22:July |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 477 | 3,817 | 14:July-22:July |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 616 | 3,697 | 16:July-22:July |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 587 | 3,521 | 16:July-22:July |
| WEISWEILER_G | Amprion | Konventionell | positive | 362 | 3,259 | 22:July-07:July |
| Lippendorf | 50Hertz | Konventionell | negative | 314 | 2,668 | 22:July-22:July |
| HAMMUENTROP_20 | Amprion | Konventionell | positive | 246 | 2,587 | 22:July-08:July |
| HAMMUENTROP_20 | Amprion | Konventionell | positive | 314 | 2,515 | 14:July-22:July |
| Emsland Block B | Amprion | Konventionell | positive | 183 | 2,465 | 22:July-22:July |
| Grosskraftwerk Mannheim Block 6 | TransnetBW | Konventionell | positive | 99 | 2,370 | 22:July-22:July |
| SHN Cluster Handewitt T414 T415 | TenneT DE | negative | 214 | 2,300 | 11:July-22:July | |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 183 | 2,239 | 22:July-22:July |
| Knapsack 1 | Amprion | Konventionell | positive | 404 | 2,224 | 16:July-22:July |
| Knapsack 1 | Amprion | Konventionell | positive | 315 | 2,202 | 15:July-22:July |
| Datteln_4 | Amprion | Konventionell | negative | 180 | 2,160 | 23:July-22:July |
| HERDECKE_H6 | Amprion | Konventionell | positive | 248 | 2,046 | 13:July-22:July |
| NIEHL-31-GUD | Amprion | Konventionell | positive | 202 | 1,922 | 12:July-22:July |
| Emsland Block B | Amprion | Konventionell | positive | 226 | 1,918 | 13:July-22:July |
| Grosskraftwerk Mannheim Block 7 | TransnetBW | Konventionell | positive | 159 | 1,788 | 10:July-22:July |
| GUD_HERNE_6 | Amprion | Konventionell | positive | 232 | 1,624 | 15:July-22:July |
| NIEHL-31-GUD | Amprion | Konventionell | positive | 201 | 1,606 | 22:July-06:July |
| BAG NWAK-Cluster 17 Altheim | TenneT DE | negative | 200 | 1,600 | 08:July-16:July | |
| ReserveKW Staudinger 4 | TenneT DE | Konventionell | positive | 211 | 1,582 | 14:July-22:July |
| Emsland Block C | Amprion | Konventionell | positive | 160 | 1,400 | 13:July-22:July |
| WEISWEILER_H | Amprion | Konventionell | positive | 304 | 1,370 | 17:July-22:July |
| Jänschwalde (Standort) | 50Hertz | Konventionell | negative | 146 | 1,350 | 22:July-22:July |
| SHN Cluster Heide West T411 T412 | TenneT DE | negative | 118 | 1,325 | 10:July-22:July | |
| Jänschwalde (Standort) | 50Hertz | Konventionell | negative | 191 | 1,146 | 16:July-22:July |
| WALSUM_10 | Amprion | Konventionell | positive | 364 | 1,092 | 19:July-22:July |
| 50H_EDIS_CR_PAS | 50Hertz | negative | 143 | 1,075 | 14:July-22:July | |
| Lippendorf | 50Hertz | Konventionell | negative | 210 | 1,050 | 16:July-22:July |
| SHN Cluster Süderdonn T412 T413 | TenneT DE | negative | 108 | 1,025 | 10:July-20:July | |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 145 | 940 | 15:July-22:July |
| UW Diele | TenneT DE | negative | 153 | 918 | 10:July-16:July | |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 152 | 910 | 16:July-22:July |
| Rostock Kohlekraftwerk | 50Hertz | Konventionell | negative | 221 | 884 | 18:July-22:July |
| Hannover-Linden GuD | TenneT DE | Konventionell | positive | 99 | 868 | 22:July-06:July |
| LAUSWARD_GUDF | Amprion | Konventionell | positive | 206 | 771 | 13:July-17:July |
| WEISWEILER_H | Amprion | Konventionell | positive | 180 | 675 | 18:July-22:July |
| NIEHL-31-GUD | Amprion | Konventionell | positive | 207 | 620 | 16:July-21:July |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.26M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-07-06?
On 2026-07-06, estimated redispatch costs were approximately €0.88 million. This includes €0.23M for renewable curtailment compensation and €0.33M for conventional ramp-up costs.
Which power plants were most affected on 2026-07-06?
The most affected plant was Börse (TenneT DE) with 15,625 MWh of positive redispatch.
What was the electricity spot price on 2026-07-06?
The EPEX Day-Ahead spot price for DE_LU ranged from 1 to 156 €/MWh with an average of 98 €/MWh.