3,243MWh Curtailed
2,979MWh Ramped Up
€0.82MEst. Cost
239 MWPeak Positive
Day-Ahead Spot: 90-236 €/MWh (avg 137)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| Amprion | negative | 6 | 3,611 |
| Amprion | positive | 3 | 3,051 |
| TransnetBW | positive | 3 | 2,878 |
| TenneT DE | negative | 3 | 2,220 |
| 50Hertz | negative | 4 | 1,580 |
| TenneT DE | positive | 5 | 955 |
| TransnetBW | negative | 1 | 205 |
| 50Hertz | positive | 1 | 6 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 286 | 1,646 | 04:April-13:April |
| Emsland Block C | Amprion | Konventionell | positive | 302 | 1,584 | 05:April-10:April |
| Emsland Block B | Amprion | Konventionell | positive | 217 | 1,305 | 05:April-11:April |
| Rostock Kohlekraftwerk | 50Hertz | Konventionell | negative | 160 | 1,278 | 04:April-12:April |
| WALSUM_10 | Amprion | Konventionell | negative | 259 | 1,231 | 08:April-13:April |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 317 | 1,190 | 12:April-15:April |
| NEURATH_F | Amprion | Konventionell | negative | 223 | 838 | 12:April-15:April |
| Irsching 5 | TenneT DE | Konventionell | negative | 181 | 816 | 06:April-10:April |
| Irsching 4 | TenneT DE | Konventionell | negative | 48 | 735 | 22:April-22:April |
| NIEDERAUSSEM_H | Amprion | Konventionell | negative | 155 | 696 | 08:April-13:April |
| Irsching 4 | TenneT DE | Konventionell | negative | 52 | 670 | 09:April-22:April |
| NIEDERAUSSEM_H | Amprion | Konventionell | negative | 141 | 353 | 12:April-15:April |
| HAMMUENTROP_20 | Amprion | Konventionell | negative | 126 | 345 | 06:April-09:April |
| Linden GKL GT 1 | TenneT DE | Konventionell | positive | 52 | 300 | 06:April-12:April |
| Niederrad 1 | TenneT DE | Konventionell | positive | 30 | 240 | 22:April-06:April |
| Börse | TransnetBW | Sonstiges | negative | 34 | 205 | 06:April-14:April |
| Gebersdorf GT | TenneT DE | Konventionell | positive | 60 | 180 | 04:April-07:April |
| Linden GKL DT | TenneT DE | Konventionell | positive | 31 | 169 | 07:April-12:April |
| HKW BARMEN 1 | Amprion | Konventionell | positive | 27 | 162 | 03:April-09:April |
| GUD_HERNE_6 | Amprion | Konventionell | negative | 49 | 148 | 06:April-09:April |
| 50H Berlin Lichterfelde | 50Hertz | Konventionell | negative | 45 | 135 | 06:April-09:April |
| 50H Rostock Marienehe | 50Hertz | Konventionell | negative | 37 | 112 | 05:April-09:April |
| Frankfurt West 3 | TenneT DE | Konventionell | positive | 9 | 66 | 08:April-15:April |
| 50H Hamburg Tiefstack 2 HKW SK | 50Hertz | Konventionell | negative | 55 | 55 | 07:April-08:April |
| Börse | TransnetBW | Sonstiges | positive | 55 | 41 | 06:April-13:April |
| Börse | 50Hertz | Sonstiges | positive | 9 | 6 | 03:April-04:April |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.25M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-04-14?
On 2026-04-14, estimated redispatch costs were approximately €0.82 million. This includes €0.32M for renewable curtailment compensation and €0.5M for conventional ramp-up costs.
Which power plants were most affected on 2026-04-14?
The most affected plant was illwerke vkw AG (TransnetBW) with 1,646 MWh of positive redispatch.
What was the electricity spot price on 2026-04-14?
The EPEX Day-Ahead spot price for DE_LU ranged from 90 to 236 €/MWh with an average of 137 €/MWh.