← 2026-04-13

Tuesday, April 14, 2026

2026-04-15 →
3,243MWh Curtailed
2,979MWh Ramped Up
€0.82MEst. Cost
239 MWPeak Positive

Day-Ahead Spot: 90-236 €/MWh (avg 137)

TSO Breakdown

TSODirectionMeasuresTotal MWh
Amprion negative 6 3,611
Amprion positive 3 3,051
TransnetBW positive 3 2,878
TenneT DE negative 3 2,220
50Hertz negative 4 1,580
TenneT DE positive 5 955
TransnetBW negative 1 205
50Hertz positive 1 6

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
illwerke vkw AG TransnetBW Sonstiges positive 286 1,646 04:April-13:April
Emsland Block C Amprion Konventionell positive 302 1,584 05:April-10:April
Emsland Block B Amprion Konventionell positive 217 1,305 05:April-11:April
Rostock Kohlekraftwerk 50Hertz Konventionell negative 160 1,278 04:April-12:April
WALSUM_10 Amprion Konventionell negative 259 1,231 08:April-13:April
illwerke vkw AG TransnetBW Sonstiges positive 317 1,190 12:April-15:April
NEURATH_F Amprion Konventionell negative 223 838 12:April-15:April
Irsching 5 TenneT DE Konventionell negative 181 816 06:April-10:April
Irsching 4 TenneT DE Konventionell negative 48 735 22:April-22:April
NIEDERAUSSEM_H Amprion Konventionell negative 155 696 08:April-13:April
Irsching 4 TenneT DE Konventionell negative 52 670 09:April-22:April
NIEDERAUSSEM_H Amprion Konventionell negative 141 353 12:April-15:April
HAMMUENTROP_20 Amprion Konventionell negative 126 345 06:April-09:April
Linden GKL GT 1 TenneT DE Konventionell positive 52 300 06:April-12:April
Niederrad 1 TenneT DE Konventionell positive 30 240 22:April-06:April
Börse TransnetBW Sonstiges negative 34 205 06:April-14:April
Gebersdorf GT TenneT DE Konventionell positive 60 180 04:April-07:April
Linden GKL DT TenneT DE Konventionell positive 31 169 07:April-12:April
HKW BARMEN 1 Amprion Konventionell positive 27 162 03:April-09:April
GUD_HERNE_6 Amprion Konventionell negative 49 148 06:April-09:April
50H Berlin Lichterfelde 50Hertz Konventionell negative 45 135 06:April-09:April
50H Rostock Marienehe 50Hertz Konventionell negative 37 112 05:April-09:April
Frankfurt West 3 TenneT DE Konventionell positive 9 66 08:April-15:April
50H Hamburg Tiefstack 2 HKW SK 50Hertz Konventionell negative 55 55 07:April-08:April
Börse TransnetBW Sonstiges positive 55 41 06:April-13:April
Börse 50Hertz Sonstiges positive 9 6 03:April-04:April

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.25M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-04-14?

On 2026-04-14, estimated redispatch costs were approximately €0.82 million. This includes €0.32M for renewable curtailment compensation and €0.5M for conventional ramp-up costs.

Which power plants were most affected on 2026-04-14?

The most affected plant was illwerke vkw AG (TransnetBW) with 1,646 MWh of positive redispatch.

What was the electricity spot price on 2026-04-14?

The EPEX Day-Ahead spot price for DE_LU ranged from 90 to 236 €/MWh with an average of 137 €/MWh.