2,449MWh Curtailed
3,435MWh Ramped Up
€1.06MEst. Cost
409 MWPeak Positive
Day-Ahead Spot: 29-406 €/MWh (avg 134)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| TenneT DE | negative | 24 | 23,112 |
| 50Hertz | negative | 46 | 21,416 |
| TransnetBW | positive | 8 | 8,737 |
| Amprion | positive | 14 | 6,486 |
| TenneT DE | positive | 6 | 1,976 |
| Amprion | negative | 4 | 1,652 |
| TransnetBW | negative | 2 | 619 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 367 | 3,031 | 06:June-14:June |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 367 | 3,031 | 06:June-14:June |
| BAG NWAK-Cluster 14 Schwandorf | TenneT DE | negative | 300 | 2,400 | 07:June-15:June | |
| BAG NWAK-Cluster 15 Pleinting | TenneT DE | negative | 300 | 2,400 | 07:June-15:June | |
| BAG NWAK-Cluster 14 Schwandorf | TenneT DE | negative | 300 | 2,400 | 07:June-15:June | |
| BAG NWAK-Cluster 15 Pleinting | TenneT DE | negative | 300 | 2,400 | 07:June-15:June | |
| 50H PV Witznitz | 50Hertz | negative | 260 | 2,078 | 07:June-17:June | |
| 50H PV Witznitz | 50Hertz | negative | 260 | 2,078 | 07:June-17:June | |
| BAG NWAK-Cluster 03 Bergrheinfeld-Schweinfurt | TenneT DE | negative | 300 | 1,950 | 07:June-13:June | |
| BAG NWAK-Cluster 03 Bergrheinfeld-Schweinfurt | TenneT DE | negative | 300 | 1,950 | 07:June-13:June | |
| KMW_KW3 | Amprion | Konventionell | positive | 270 | 1,754 | 09:June-15:June |
| KMW_KW3 | Amprion | Konventionell | positive | 270 | 1,754 | 09:June-15:June |
| BAG NWAK-Cluster 16 Regensburg-Sittling | TenneT DE | negative | 200 | 1,600 | 07:June-15:June | |
| BAG NWAK-Cluster 17 Altheim | TenneT DE | negative | 200 | 1,600 | 07:June-15:June | |
| BAG NWAK-Cluster 16 Regensburg-Sittling | TenneT DE | negative | 200 | 1,600 | 07:June-15:June | |
| BAG NWAK-Cluster 17 Altheim | TenneT DE | negative | 200 | 1,600 | 07:June-15:June | |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 433 | 1,298 | 06:June-09:June |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 433 | 1,298 | 06:June-09:June |
| 50H_AVA_CR_WOL | 50Hertz | negative | 241 | 1,025 | 07:June-11:June | |
| 50H_AVA_CR_WOL | 50Hertz | negative | 241 | 1,025 | 07:June-11:June | |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 169 | 970 | 09:June-16:June |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 169 | 970 | 09:June-16:June |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 313 | 938 | 06:June-09:June |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 313 | 938 | 06:June-09:June |
| 50H_TEN_CR_M2_VIB | 50Hertz | negative | 279 | 838 | 11:June-14:June | |
| 50H_TEN_CR_M2_VIB | 50Hertz | negative | 279 | 838 | 11:June-14:June | |
| 50H_MNS_CR_KLM | 50Hertz | negative | 171 | 812 | 09:June-14:June | |
| 50H_MNS_CR_KLM | 50Hertz | negative | 171 | 812 | 09:June-14:June | |
| 50H_AVA_CR_FOE | 50Hertz | negative | 147 | 588 | 07:June-11:June | |
| 50H_AVA_CR_FOE | 50Hertz | negative | 147 | 588 | 07:June-11:June | |
| Datteln_4 | Amprion | Konventionell | negative | 292 | 585 | 14:June-16:June |
| Datteln_4 | Amprion | Konventionell | negative | 292 | 585 | 14:June-16:June |
| Irsching 4 | TenneT DE | Konventionell | negative | 227 | 568 | 14:June-17:June |
| Irsching 4 | TenneT DE | Konventionell | negative | 227 | 568 | 14:June-17:June |
| 50H_AVA_CR_STW | 50Hertz | negative | 205 | 562 | 08:June-11:June | |
| 50H_AVA_CR_STW | 50Hertz | negative | 205 | 562 | 08:June-11:June | |
| 50H_MNS_CR_JSN | 50Hertz | negative | 113 | 535 | 09:June-14:June | |
| 50H_MNS_CR_JSN | 50Hertz | negative | 113 | 535 | 09:June-14:June | |
| 50H_MNS_CR_LAU_Nord | 50Hertz | negative | 142 | 425 | 11:June-14:June | |
| 50H_MNS_CR_LAU_Nord | 50Hertz | negative | 142 | 425 | 11:June-14:June | |
| HAMMUENTROP_20 | Amprion | Konventionell | positive | 207 | 414 | 07:June-09:June |
| HAMMUENTROP_20 | Amprion | Konventionell | positive | 207 | 414 | 07:June-09:June |
| AVA Cluster Helmstedt | TenneT DE | negative | 83 | 393 | 08:June-13:June | |
| AVA Cluster Helmstedt | TenneT DE | negative | 83 | 393 | 08:June-13:June | |
| Börse | TenneT DE | Sonstiges | positive | 389 | 389 | 18:June-19:June |
| Börse | TenneT DE | Sonstiges | positive | 389 | 389 | 18:June-19:June |
| Hannover-Linden GuD | TenneT DE | Konventionell | positive | 114 | 370 | 06:June-10:June |
| Hannover-Linden GuD | TenneT DE | Konventionell | positive | 114 | 370 | 06:June-10:June |
| KMW_KW3 | Amprion | Konventionell | positive | 237 | 355 | 07:June-09:June |
| KMW_KW3 | Amprion | Konventionell | positive | 237 | 355 | 07:June-09:June |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.32M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-06-26?
On 2026-06-26, estimated redispatch costs were approximately €1.06 million. This includes €0.24M for renewable curtailment compensation and €0.56M for conventional ramp-up costs.
Which power plants were most affected on 2026-06-26?
The most affected plant was illwerke vkw AG (TransnetBW) with 3,031 MWh of positive redispatch.
What was the electricity spot price on 2026-06-26?
The EPEX Day-Ahead spot price for DE_LU ranged from 29 to 406 €/MWh with an average of 134 €/MWh.