50H_AVA_CR_WK
• 50Hertz
597Total MWh
3Measures
70 MWAvg Power
3Curtailments
0Ramp-ups
Data: 2026-01-09 to 2026-04-18
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2026-04-18 | 1 | 317 |
| 2026-03-05 | 1 | 186 |
| 2026-01-09 | 1 | 94 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2026-04-18 | 50Hertz | negative | 53 | 317 | 08:April-14:April |
| 2026-03-05 | 50Hertz | negative | 62 | 186 | 09:March-12:March |
| 2026-01-09 | 50Hertz | negative | 94 | 94 | 16:January-17:January |
Frequently Asked Questions
What is the redispatch history of 50H_AVA_CR_WK?
50H_AVA_CR_WK is a Erneuerbar power plant in the 50Hertz grid zone. It has received 3 redispatch instructions totaling 597 MWh since 2026-01-09.
Why is 50H_AVA_CR_WK frequently redispatched?
Plants in the 50Hertz zone are frequently curtailed due to grid congestion from excess renewable generation in Northern Germany. This is part of Germany's structural North-South grid bottleneck.