2,701MWh Curtailed
2,983MWh Ramped Up
€0.97MEst. Cost
197 MWPeak Positive
Day-Ahead Spot: 41-196 €/MWh (avg 115)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| 50Hertz | negative | 35 | 16,283 |
| Amprion | positive | 12 | 13,405 |
| TenneT DE | positive | 12 | 11,116 |
| TenneT DE | negative | 4 | 4,260 |
| TransnetBW | positive | 5 | 2,124 |
| TransnetBW | negative | 1 | 278 |
| Amprion | negative | 3 | 213 |
| 50Hertz | positive | 1 | 200 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| LAUSWARD_GUDF | Amprion | Konventionell | positive | 365 | 3,921 | 06:June-16:June |
| Emsland Block B | Amprion | Konventionell | positive | 246 | 3,198 | 03:June-16:June |
| Irsching 4 | TenneT DE | Konventionell | positive | 325 | 2,681 | 07:June-15:June |
| Börse | TenneT DE | Sonstiges | negative | 308 | 2,468 | 22:June-22:June |
| ReserveKW Staudinger 4 | TenneT DE | Konventionell | positive | 313 | 2,428 | 22:June-22:June |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 442 | 2,212 | 05:June-10:June |
| HAMMUENTROP_20 | Amprion | Konventionell | positive | 195 | 2,144 | 06:June-17:June |
| Emsland Block C | Amprion | Konventionell | positive | 254 | 1,906 | 03:June-11:June |
| Hannover-Linden GuD | TenneT DE | Konventionell | positive | 158 | 1,899 | 02:June-14:June |
| Jänschwalde (Standort) | 50Hertz | Konventionell | negative | 161 | 1,776 | 04:June-16:June |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 412 | 1,648 | 06:June-10:June |
| ReserveKW Staudinger 4 | TenneT DE | Konventionell | positive | 260 | 1,560 | 16:June-22:June |
| Börse | TenneT DE | Sonstiges | negative | 260 | 1,560 | 16:June-22:June |
| 50H OWP Baltic Eagle | 50Hertz | negative | 155 | 1,314 | 05:June-16:June | |
| 50H PV Witznitz | 50Hertz | negative | 146 | 1,277 | 07:June-16:June | |
| 50H OWP Wikinger | 50Hertz | negative | 115 | 1,010 | 05:June-15:June | |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 98 | 975 | 02:June-16:June |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 300 | 900 | 17:June-20:June |
| GUD_HERNE_6 | Amprion | Konventionell | positive | 177 | 841 | 07:June-13:June |
| Lippendorf | 50Hertz | Konventionell | negative | 266 | 798 | 05:June-08:June |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 101 | 736 | 04:June-15:June |
| 50H_EDIS_CR_LV_WU | 50Hertz | negative | 110 | 630 | 09:June-15:June | |
| 50H OWP Arcadis Ost 1 | 50Hertz | negative | 90 | 566 | 07:June-15:June | |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 308 | 539 | 06:June-08:June |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 123 | 524 | 06:June-10:June |
| Itzehoe | TenneT DE | Konventionell | positive | 74 | 516 | 06:June-13:June |
| SW München KW-Pool | TenneT DE | Sonstiges | positive | 157 | 511 | 05:June-08:June |
| 50H OWP Arkona | 50Hertz | negative | 90 | 493 | 08:June-15:June | |
| Jänschwalde (Standort) | 50Hertz | Konventionell | negative | 151 | 453 | 06:June-09:June |
| Braunschweig HKWM GT31 | TenneT DE | Konventionell | positive | 56 | 420 | 05:June-13:June |
| Braunschweig GT | TenneT DE | Konventionell | positive | 43 | 364 | 05:June-13:June |
| 50H_AVA_CR_WOL | 50Hertz | negative | 200 | 350 | 11:June-13:June | |
| Irsching 4 | TenneT DE | Konventionell | positive | 142 | 318 | 08:June-10:June |
| Jänschwalde (Standort) | 50Hertz | Konventionell | negative | 105 | 316 | 14:June-17:June |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 126 | 315 | 14:June-16:June |
| WALSUM_10 | Amprion | Konventionell | positive | 136 | 306 | 07:June-09:June |
| Irsching 4 | TenneT DE | Konventionell | positive | 126 | 282 | 10:June-12:June |
| Börse | TransnetBW | Sonstiges | negative | 80 | 278 | 00:June-12:June |
| 50H UW Bertikow | 50Hertz | negative | 55 | 276 | 08:June-13:June | |
| Börse | Amprion | Konventionell | positive | 120 | 240 | 17:June-19:June |
| WALSUM_10 | Amprion | Konventionell | positive | 126 | 220 | 07:June-09:June |
| Datteln_4 | Amprion | Konventionell | positive | 217 | 217 | 09:June-10:June |
| 50H_EDIS_CR_HND | 50Hertz | negative | 44 | 208 | 09:June-14:June | |
| 50H PV Bartow | 50Hertz | negative | 43 | 202 | 07:June-13:June | |
| Börse | 50Hertz | Sonstiges | positive | 200 | 200 | 12:June-13:June |
| Lippendorf | 50Hertz | Konventionell | negative | 90 | 180 | 04:June-07:June |
| HUCKINGEN_A | Amprion | Konventionell | positive | 80 | 160 | 17:June-19:June |
| Börse | TenneT DE | Sonstiges | negative | 203 | 152 | 07:June-10:June |
| BIBLIS_GT (bnBm) | Amprion | Konventionell | positive | 203 | 152 | 07:June-08:June |
| 50H_EDIS_CR_WU | 50Hertz | negative | 50 | 125 | 10:June-13:June |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.29M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-06-16?
On 2026-06-16, estimated redispatch costs were approximately €0.97 million. This includes €0.27M for renewable curtailment compensation and €0.43M for conventional ramp-up costs.
Which power plants were most affected on 2026-06-16?
The most affected plant was LAUSWARD_GUDF (Amprion) with 3,921 MWh of positive redispatch.
What was the electricity spot price on 2026-06-16?
The EPEX Day-Ahead spot price for DE_LU ranged from 41 to 196 €/MWh with an average of 115 €/MWh.