← 2026-10-26

Tuesday, October 27, 2026

2026-10-28 →
2,639MWh Curtailed
3,953MWh Ramped Up
€1.12MEst. Cost
290 MWPeak Positive

Day-Ahead Spot: 39-273 €/MWh (avg 159)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TenneT DE negative 14 50,096
Amprion positive 18 16,311
Amprion negative 9 5,589
50Hertz positive 7 4,893
TransnetBW positive 6 4,265
50Hertz negative 10 4,234
TenneT DE positive 8 3,260
TransnetBW negative 3 381

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
UW Dörpen-West TenneT DE Erneuerbar negative 1264 18,954 05:October-20:October
Wilhelmshaven TenneT DE Konventionell negative 467 10,983 23:October-23:October
UW Diele TenneT DE Erneuerbar negative 520 7,145 05:October-18:October
GUD_HERNE_6 Amprion Konventionell positive 293 4,395 05:October-20:October
UW Emden-Ost TenneT DE Erneuerbar negative 366 3,657 05:October-17:October
Lippendorf 50Hertz Konventionell positive 862 3,446 01:October-05:October
Netzreservekraftwerk KMW 2 DT Amprion Konventionell positive 157 3,025 23:October-18:October
UW Büttel TenneT DE Erneuerbar negative 241 2,654 05:October-16:October
NIEHL-31-GUD Amprion Konventionell positive 219 2,296 04:October-15:October
UW Emden-Ost TenneT DE Erneuerbar negative 683 2,050 06:October-09:October
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 369 1,567 10:October-14:October
illwerke vkw AG TransnetBW Sonstiges positive 214 1,498 14:October-21:October
WALSUM_10 Amprion Konventionell negative 211 1,476 13:October-23:October
Grosskraftwerk Mannheim Block 9 TransnetBW Konventionell positive 175 1,401 00:October-08:October
NIEDERAUSSEM_G Amprion Konventionell negative 156 1,368 23:October-16:October
Irsching 4 TenneT DE Konventionell positive 317 1,346 01:October-05:October
Netzreservekraftwerk HERNE_4 Amprion Konventionell positive 125 1,252 08:October-18:October
Kiel (Küstenkraftwerk gesamt) TenneT DE Konventionell negative 111 1,053 05:October-22:October
Emsland Block C Amprion Konventionell positive 128 1,024 07:October-20:October
50H OWP Baltic Eagle 50Hertz Erneuerbar negative 246 983 01:October-05:October
UW Garrel-Ost alpha TenneT DE Erneuerbar negative 230 977 00:October-05:October
Knapsack 1 Amprion Konventionell positive 361 902 07:October-09:October
HERDECKE_H6 Amprion Konventionell positive 96 768 07:October-20:October
Knapsack 1 Amprion Konventionell negative 286 715 01:October-04:October
BAG NWAK-Cluster 17 Altheim TenneT DE Erneuerbar negative 150 712 10:October-15:October
Kiel (Küstenkraftwerk gesamt) TenneT DE Konventionell negative 89 666 23:October-18:October
NIEHL-31-GUD Amprion Konventionell negative 194 630 01:October-04:October
Emsland Block D Amprion Konventionell positive 210 629 09:October-14:October
Frankfurt West 4 TenneT DE Konventionell positive 63 626 08:October-18:October
Rostock Kohlekraftwerk 50Hertz Konventionell negative 76 610 07:October-22:October
AMP_WESTNETZ_TRIER_CR_WIND Amprion Erneuerbar negative 163 572 02:October-05:October
illwerke vkw AG TransnetBW Sonstiges positive 200 550 06:October-09:October
HAMMUENTROP_20 Amprion Konventionell positive 95 544 06:October-19:October
AMP_WESTNETZ_EIFEL_CR_WIND Amprion Erneuerbar negative 155 505 02:October-05:October
WP Emsland TenneT DE Erneuerbar negative 48 477 05:October-15:October
BAG NWAK-Cluster 16a Regensburg-Sittling TenneT DE Erneuerbar negative 109 438 11:October-15:October
Schkopau 50Hertz Konventionell positive 141 423 23:October-11:October
Heizkraftwerk Altbach/Deizisau Block 2 TransnetBW Konventionell positive 110 412 01:October-04:October
Rostock Kohlekraftwerk 50Hertz Konventionell positive 131 394 01:October-04:October
Frankfurt West 4 TenneT DE Konventionell positive 64 387 03:October-09:October
Netzreservekraftwerk GTKW-DA-POOL Amprion Konventionell positive 88 354 01:October-05:October
Rostock Kohlekraftwerk 50Hertz Konventionell positive 157 354 06:October-09:October
Börse TenneT DE Sonstiges positive 271 339 06:October-07:October
Rostock Kohlekraftwerk 50Hertz Konventionell negative 110 331 06:October-09:October
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 149 298 09:October-23:October
HKW BARMEN 1 Amprion Konventionell positive 25 296 04:October-16:October
SW München KW-Pool TenneT DE Sonstiges positive 96 288 06:October-09:October
Börse TransnetBW Sonstiges negative 109 272 08:October-21:October
HUCKINGEN_B Amprion Konventionell positive 100 250 06:October-09:October
Reservekraftwerk Altbach/Deizisau Block 1 TransnetBW Konventionell positive 112 225 03:October-05:October

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.34M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-10-27?

On 2026-10-27, estimated redispatch costs were approximately €1.12 million. This includes €0.26M for renewable curtailment compensation and €0.75M for conventional ramp-up costs.

Which power plants were most affected on 2026-10-27?

The most affected plant was UW Dörpen-West (TenneT DE) with 18,954 MWh of negative redispatch.

What was the electricity spot price on 2026-10-27?

The EPEX Day-Ahead spot price for DE_LU ranged from 39 to 273 €/MWh with an average of 159 €/MWh.