HUCKINGEN_B
Konventionell • Amprion
517Total MWh
2Measures
79 MWAvg Power
0Curtailments
2Ramp-ups
Data: 2025-07-02 to 2026-03-14
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2026-03-14 | 1 | 117 |
| 2025-07-02 | 1 | 400 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2026-03-14 | Amprion | positive | 58 | 117 | 08:March-10:March |
| 2025-07-02 | Amprion | positive | 100 | 400 | 16:July-20:July |
Frequently Asked Questions
What is the redispatch history of HUCKINGEN_B?
HUCKINGEN_B is a Konventionell power plant in the Amprion grid zone. It has received 2 redispatch instructions totaling 517 MWh since 2025-07-02.
Why is HUCKINGEN_B frequently redispatched?
Plants in the Amprion zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.