← 2026-03-13

Saturday, March 14, 2026

2026-03-15 →
2,749MWh Curtailed
2,903MWh Ramped Up
€0.87MEst. Cost
183 MWPeak Positive

Day-Ahead Spot: 82-192 €/MWh (avg 120)

TSO Breakdown

TSODirectionMeasuresTotal MWh
Amprion positive 15 21,198
50Hertz negative 43 19,461
TenneT DE positive 8 4,076
TenneT DE negative 5 3,646
TransnetBW positive 4 987
TransnetBW negative 2 821
50Hertz positive 1 10

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
Emsland Block D Amprion Konventionell positive 440 5,831 02:March-15:March
Schkopau 50Hertz Konventionell negative 350 4,204 03:March-15:March
HAMMUENTROP_10 Amprion Konventionell positive 310 3,565 04:March-15:March
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 379 3,412 05:March-15:March
HAMMUENTROP_20 Amprion Konventionell positive 327 3,022 06:March-15:March
Boxberg (Standort) 50Hertz Konventionell negative 306 2,452 05:March-13:March
Emsland Block C Amprion Konventionell positive 238 2,444 03:March-14:March
Irsching 5 TenneT DE Konventionell positive 231 2,308 05:March-15:March
BAG NWAK-Cluster 15 Pleinting TenneT DE Erneuerbar negative 300 1,500 09:March-14:March
Emsland Block D Amprion Konventionell positive 184 1,473 04:March-14:March
Emsland Block B Amprion Konventionell positive 182 1,362 02:March-10:March
Jänschwalde (Standort) 50Hertz Konventionell negative 226 1,129 06:March-11:March
WEISWEILER_VGTG3 Amprion Konventionell positive 169 1,016 06:March-12:March
Emsland Block C Amprion Konventionell positive 191 1,002 05:March-11:March
Rostock Kohlekraftwerk 50Hertz Konventionell negative 133 799 06:March-12:March
Jänschwalde (Standort) 50Hertz Konventionell negative 99 794 05:March-15:March
BAG NWAK-Cluster 13 Etzenricht TenneT DE Erneuerbar negative 200 750 10:March-14:March
BAG NWAK-Cluster 17 Altheim TenneT DE Erneuerbar negative 150 750 09:March-14:March
50H UW Bertikow 50Hertz Erneuerbar negative 157 626 09:March-13:March
BAG NWAK-Cluster 16 Regensburg-Sittling TenneT DE Erneuerbar negative 125 625 09:March-14:March
50H_TEN_CR_M2_VIB 50Hertz Erneuerbar negative 200 600 01:March-04:March
Rostock Kohlekraftwerk 50Hertz Konventionell negative 83 584 05:March-15:March
WEISWEILERVGT_H3 Amprion Konventionell positive 179 582 05:March-08:March
Irsching 5 TenneT DE Konventionell positive 104 545 05:March-10:March
Lippendorf 50Hertz Konventionell negative 105 523 02:March-08:March
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell negative 173 520 12:March-15:March
illwerke vkw AG TransnetBW Sonstiges positive 175 481 05:March-10:March
50H Berlin Marzahn 50Hertz Konventionell negative 43 468 02:March-14:March
50H OWP Wikinger 50Hertz Erneuerbar negative 65 452 05:March-13:March
Boxberg (Standort) 50Hertz Konventionell negative 101 405 05:March-14:March
50H PV Witznitz 50Hertz Erneuerbar negative 97 389 09:March-13:March
Linden GKL GT 3 TenneT DE Konventionell positive 57 372 05:March-11:March
50H Berlin Lichterfelde 50Hertz Konventionell negative 91 364 05:March-09:March
Linden GKL GT 1 TenneT DE Konventionell positive 56 364 05:March-11:March
Kraftwerk Walheim GT D TransnetBW Konventionell positive 117 351 08:March-11:March
50H Berlin Mitte 50Hertz Konventionell negative 64 322 05:March-10:March
WEISWEILERVGT_H3 Amprion Konventionell positive 157 314 08:March-10:March
Börse TransnetBW Sonstiges negative 93 301 06:March-15:March
Lippendorf 50Hertz Konventionell negative 156 273 04:March-07:March
50H OWP Baltic Eagle 50Hertz Erneuerbar negative 61 243 09:March-13:March
WEISWEILER_VGTG3 Amprion Konventionell positive 121 242 05:March-07:March
Linden GKL DT TenneT DE Konventionell positive 39 215 05:March-11:March
50H OWP Arkona 50Hertz Erneuerbar negative 71 213 08:March-13:March
50H UW Schönewalde 50Hertz Erneuerbar negative 36 207 04:March-14:March
50H InfraLeuna IKW 50Hertz Konventionell negative 18 162 02:March-14:March
50H Berlin Mitte 50Hertz Konventionell negative 36 142 06:March-10:March
HUCKINGEN_A Amprion Konventionell positive 58 117 08:March-10:March
HUCKINGEN_B Amprion Konventionell positive 58 117 08:March-10:March
Audorf TenneT DE Konventionell positive 50 100 05:March-07:March
Emden 4 GT (KapRes) TenneT DE Konventionell positive 50 100 08:March-10:March

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.26M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-03-14?

On 2026-03-14, estimated redispatch costs were approximately €0.87 million. This includes €0.27M for renewable curtailment compensation and €0.44M for conventional ramp-up costs.

Which power plants were most affected on 2026-03-14?

The most affected plant was Emsland Block D (Amprion) with 5,831 MWh of positive redispatch.

What was the electricity spot price on 2026-03-14?

The EPEX Day-Ahead spot price for DE_LU ranged from 82 to 192 €/MWh with an average of 120 €/MWh.