Audorf

KonventionellTenneT DE

3,936Total MWh
23Measures
52 MWAvg Power
0Curtailments
23Ramp-ups

Data: 2024-01-15 to 2026-05-03

Daily Redispatch Volume

DateMeasuresTotal MWh
2026-05-03 1 219
2026-04-27 1 100
2026-04-26 1 100
2026-04-23 2 125
2026-04-21 2 25
2026-04-18 1 50
2026-04-17 1 162
2026-04-13 1 170
2026-03-23 1 188
2026-03-14 1 100
2026-03-06 1 181
2026-03-05 1 88
2026-03-03 1 100
2026-02-18 1 112
2024-11-11 1 148
2024-10-19 1 114
2024-09-14 1 1,131
2024-08-14 1 352
2024-07-19 1 140
2024-06-20 1 125
2024-01-15 1 208

Recent Measures

DateTSODirAvg MWMWhTime
2026-05-03 TenneT DE positive 46 219 07:May-14:May
2026-04-27 TenneT DE positive 50 100 07:April-09:April
2026-04-26 TenneT DE positive 50 100 06:April-08:April
2026-04-23 TenneT DE positive 31 62 06:April-08:April
2026-04-23 TenneT DE positive 31 62 06:April-08:April
2026-04-21 TenneT DE positive 50 12 07:April-07:April
2026-04-21 TenneT DE positive 50 12 07:April-07:April
2026-04-18 TenneT DE positive 40 50 10:April-12:April
2026-04-17 TenneT DE positive 50 162 05:April-09:April
2026-04-13 TenneT DE positive 28 170 09:April-15:April
2026-03-23 TenneT DE positive 50 188 07:March-11:March
2026-03-14 TenneT DE positive 50 100 05:March-07:March
2026-03-06 TenneT DE positive 48 181 09:March-13:March
2026-03-05 TenneT DE positive 50 88 09:March-11:March
2026-03-03 TenneT DE positive 50 100 09:March-11:March
2026-02-18 TenneT DE positive 56 112 23:February-01:February
2024-11-11 TenneT DE positive 74 148 10:November-12:November
2024-10-19 TenneT DE positive 57 114 06:October-08:October
2024-09-14 TenneT DE positive 87 1,131 09:September-22:September
2024-08-14 TenneT DE positive 61 352 07:August-13:August
2024-07-19 TenneT DE positive 70 140 07:July-09:July
2024-06-20 TenneT DE positive 62 125 08:June-10:June
2024-01-15 TenneT DE positive 52 208 06:January-14:January

Frequently Asked Questions

What is the redispatch history of Audorf?

Audorf is a Konventionell power plant in the TenneT DE grid zone. It has received 23 redispatch instructions totaling 3,936 MWh since 2024-01-15.

Why is Audorf frequently redispatched?

Plants in the TenneT DE zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.