← 2026-04-20

Tuesday, April 21, 2026

2026-04-22 →
2,070MWh Curtailed
1,805MWh Ramped Up
€0.42MEst. Cost
150 MWPeak Positive

Day-Ahead Spot: -10-147 €/MWh (avg 86)

TSO Breakdown

TSODirectionMeasuresTotal MWh
50Hertz negative 89 24,864
Amprion positive 14 18,212
TenneT DE negative 4 1,564
TenneT DE positive 8 598
TransnetBW positive 2 548
TransnetBW negative 1 140

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
Knapsack 1 Amprion Konventionell positive 534 5,611 22:April-08:April
Knapsack 1 Amprion Konventionell positive 534 5,611 22:April-08:April
Boxberg (Standort) 50Hertz Konventionell negative 223 2,003 22:April-07:April
Boxberg (Standort) 50Hertz Konventionell negative 223 2,003 22:April-07:April
50H Berlin Marzahn 50Hertz Konventionell negative 142 1,985 22:April-22:April
50H Berlin Marzahn 50Hertz Konventionell negative 142 1,985 22:April-22:April
50H Berlin Mitte 50Hertz Konventionell negative 113 1,578 22:April-21:April
50H Berlin Mitte 50Hertz Konventionell negative 113 1,578 22:April-21:April
Emsland Block C Amprion Konventionell positive 270 1,420 04:April-09:April
Emsland Block C Amprion Konventionell positive 270 1,420 04:April-09:April
Boxberg (Standort) 50Hertz Konventionell negative 254 1,015 04:April-08:April
Boxberg (Standort) 50Hertz Konventionell negative 254 1,015 04:April-08:April
Jänschwalde (Standort) 50Hertz Konventionell negative 80 964 22:April-20:April
Jänschwalde (Standort) 50Hertz Konventionell negative 80 964 22:April-20:April
LAUSWARD_GUDF Amprion Konventionell positive 321 882 06:April-08:April
LAUSWARD_GUDF Amprion Konventionell positive 321 882 06:April-08:April
AVA Cluster Voslapp TenneT DE Erneuerbar negative 143 750 08:April-14:April
AVA Cluster Voslapp TenneT DE Erneuerbar negative 143 750 08:April-14:April
50H PV Witznitz 50Hertz Erneuerbar negative 242 726 12:April-15:April
50H PV Witznitz 50Hertz Erneuerbar negative 242 726 12:April-15:April
WALSUM_10 Amprion Konventionell positive 241 542 06:April-09:April
WALSUM_10 Amprion Konventionell positive 241 542 06:April-09:April
50H_EDIS_CR_PAS 50Hertz Erneuerbar negative 98 488 11:April-16:April
50H_EDIS_CR_PAS 50Hertz Erneuerbar negative 98 488 11:April-16:April
50H_EDIS_CR_SOW_Sued 50Hertz Erneuerbar negative 95 475 09:April-14:April
50H_EDIS_CR_SOW_Sued 50Hertz Erneuerbar negative 95 475 09:April-14:April
50H_EDIS_CR_PAS 50Hertz Erneuerbar negative 103 462 11:April-16:April
Knapsack 1 Amprion Konventionell positive 412 412 21:April-22:April
Knapsack 1 Amprion Konventionell positive 412 412 21:April-22:April
50H UW Bertikow 50Hertz Erneuerbar negative 135 404 12:April-15:April
50H UW Bertikow 50Hertz Erneuerbar negative 135 404 12:April-15:April
illwerke vkw AG TransnetBW Sonstiges positive 137 274 06:April-09:April
illwerke vkw AG TransnetBW Sonstiges positive 137 274 06:April-09:April
50H Hamburg Tiefstack 2 HKW SK 50Hertz Konventionell negative 50 251 22:April-20:April
50H Hamburg Tiefstack 2 HKW SK 50Hertz Konventionell negative 50 251 22:April-20:April
Boxberg (Standort) 50Hertz Konventionell negative 225 225 21:April-22:April
Boxberg (Standort) 50Hertz Konventionell negative 225 225 21:April-22:April
50H OWP Arcadis Ost 1 50Hertz Erneuerbar negative 52 208 04:April-09:April
50H OWP Arcadis Ost 1 50Hertz Erneuerbar negative 52 208 04:April-09:April
Linden GKL GT 1 TenneT DE Konventionell positive 46 196 05:April-09:April
Linden GKL GT 1 TenneT DE Konventionell positive 46 196 05:April-09:April
50H OWP Wikinger 50Hertz Erneuerbar negative 86 192 07:April-09:April
50H OWP Wikinger 50Hertz Erneuerbar negative 86 192 07:April-09:April
50H OWP Baltic Eagle 50Hertz Erneuerbar negative 55 164 12:April-15:April
50H OWP Baltic Eagle 50Hertz Erneuerbar negative 55 164 12:April-15:April
Markersbach (Standort) 50Hertz Sonstiges negative 200 150 08:April-08:April
Markersbach (Standort) 50Hertz Sonstiges negative 200 150 08:April-08:April
WALSUM_10 Amprion Konventionell positive 193 145 07:April-08:April
WALSUM_10 Amprion Konventionell positive 193 145 07:April-08:April
50H OWP Baltic Eagle 50Hertz Erneuerbar negative 141 141 08:April-09:April

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.13M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-04-21?

On 2026-04-21, estimated redispatch costs were approximately €0.42 million. This includes €0.21M for renewable curtailment compensation and €0.21M for conventional ramp-up costs.

Which power plants were most affected on 2026-04-21?

The most affected plant was Knapsack 1 (Amprion) with 5,611 MWh of positive redispatch.

What was the electricity spot price on 2026-04-21?

The EPEX Day-Ahead spot price for DE_LU ranged from -10 to 147 €/MWh with an average of 86 €/MWh.