← 2026-03-14

Sunday, March 15, 2026

2026-03-16 →
2,325MWh Curtailed
2,050MWh Ramped Up
€0.5MEst. Cost
145 MWPeak Positive

Day-Ahead Spot: 18-148 €/MWh (avg 86)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TenneT DE negative 12 17,718
Amprion positive 13 12,674
TenneT DE positive 15 10,202
TransnetBW positive 4 5,568
Amprion negative 8 4,255
50Hertz positive 9 2,061
50Hertz negative 9 1,984
TransnetBW negative 2 174

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
AVA Cluster Voslapp TenneT DE Erneuerbar negative 302 4,912 23:March-17:March
Börse TenneT DE Sonstiges positive 1100 4,400 19:March-23:March
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 518 4,148 15:March-23:March
Börse TenneT DE Sonstiges positive 682 4,094 23:March-17:March
UW Dörpen-West TenneT DE Erneuerbar negative 457 3,202 16:March-23:March
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 471 3,182 15:March-22:March
Emsland Block D Amprion Konventionell positive 426 2,768 15:March-22:March
HAMMUENTROP_10 Amprion Konventionell positive 262 1,967 15:March-22:March
UW Büttel TenneT DE Erneuerbar negative 316 1,893 23:March-05:March
AVA Cluster Voslapp TenneT DE Erneuerbar negative 437 1,750 19:March-23:March
HAMMUENTROP_20 Amprion Konventionell positive 223 1,671 15:March-23:March
Emsland Block D Amprion Konventionell positive 242 1,454 17:March-23:March
NEURATH_G Amprion Konventionell negative 360 1,080 20:March-23:March
Emsland Block B Amprion Konventionell positive 161 1,049 14:March-21:March
UW Büttel TenneT DE Erneuerbar negative 260 1,040 19:March-23:March
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 260 1,040 19:March-23:March
Emsland Block C Amprion Konventionell positive 191 1,002 15:March-21:March
Emsland Block C Amprion Konventionell positive 210 841 18:March-22:March
NIEDERAUSSEM_K Amprion Konventionell negative 265 795 20:March-23:March
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 147 734 15:March-21:March
UW Büttel TenneT DE Erneuerbar negative 191 669 18:March-23:March
50H Berlin Lichterfelde 50Hertz Konventionell positive 132 660 18:March-23:March
NEURATH_F Amprion Konventionell negative 300 600 21:March-23:March
WEISWEILER_H Amprion Konventionell negative 123 552 16:March-22:March
HAMMUENTROP_20 Amprion Konventionell positive 150 489 18:March-21:March
HAMMUENTROP_10 Amprion Konventionell positive 106 477 17:March-22:March
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 148 444 14:March-17:March
WEISWEILER_G Amprion Konventionell negative 144 434 19:March-22:March
Emsland Block D Amprion Konventionell positive 156 428 15:March-18:March
NEURATH_F Amprion Konventionell negative 103 413 19:March-23:March
50H Hamburg Wedel1 50Hertz Konventionell negative 68 410 17:March-23:March
STUMMHAFEN_10 Amprion Konventionell positive 190 380 20:March-22:March
OWP Nordergründe TenneT DE Erneuerbar negative 75 373 18:March-23:March
Schwarze Pumpe (Standort) 50Hertz Konventionell positive 341 341 22:March-23:March
50H Hamburg Wedel1 50Hertz Konventionell negative 48 334 23:March-06:March
Boxberg (Standort) 50Hertz Konventionell positive 190 332 16:March-23:March
Linden GKL GT 1 TenneT DE Konventionell positive 40 302 15:March-23:March
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 151 301 23:March-01:March
WEISWEILER_G Amprion Konventionell negative 122 275 18:March-21:March
Schkopau 50Hertz Konventionell positive 128 256 21:March-23:March
Linden GKL GT 3 TenneT DE Konventionell positive 33 242 15:March-23:March
Linden GKL DT TenneT DE Konventionell positive 36 214 17:March-23:March
Jänschwalde (Standort) 50Hertz Konventionell positive 177 177 22:March-23:March
OWP Nordergründe TenneT DE Erneuerbar negative 88 176 23:March-01:March
Linden GKL GT 3 TenneT DE Konventionell positive 26 171 16:March-23:March
Börse TransnetBW Sonstiges negative 136 170 15:March-22:March
Linden GKL GT 1 TenneT DE Konventionell positive 26 168 16:March-23:March
Linden GKL DT TenneT DE Konventionell positive 27 166 16:March-23:March
50H Berlin Marzahn 50Hertz Konventionell negative 72 143 16:March-18:March
50H InfraLeuna IKW 50Hertz Konventionell positive 35 140 18:March-22:March

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.15M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-03-15?

On 2026-03-15, estimated redispatch costs were approximately €0.5 million. This includes €0.23M for renewable curtailment compensation and €0.24M for conventional ramp-up costs.

Which power plants were most affected on 2026-03-15?

The most affected plant was AVA Cluster Voslapp (TenneT DE) with 4,912 MWh of negative redispatch.

What was the electricity spot price on 2026-03-15?

The EPEX Day-Ahead spot price for DE_LU ranged from 18 to 148 €/MWh with an average of 86 €/MWh.