2,325MWh Curtailed
2,050MWh Ramped Up
€0.5MEst. Cost
145 MWPeak Positive
Day-Ahead Spot: 18-148 €/MWh (avg 86)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| TenneT DE | negative | 12 | 17,718 |
| Amprion | positive | 13 | 12,674 |
| TenneT DE | positive | 15 | 10,202 |
| TransnetBW | positive | 4 | 5,568 |
| Amprion | negative | 8 | 4,255 |
| 50Hertz | positive | 9 | 2,061 |
| 50Hertz | negative | 9 | 1,984 |
| TransnetBW | negative | 2 | 174 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| AVA Cluster Voslapp | TenneT DE | negative | 302 | 4,912 | 23:March-17:March | |
| Börse | TenneT DE | Sonstiges | positive | 1100 | 4,400 | 19:March-23:March |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 518 | 4,148 | 15:March-23:March |
| Börse | TenneT DE | Sonstiges | positive | 682 | 4,094 | 23:March-17:March |
| UW Dörpen-West | TenneT DE | negative | 457 | 3,202 | 16:March-23:March | |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 471 | 3,182 | 15:March-22:March |
| Emsland Block D | Amprion | Konventionell | positive | 426 | 2,768 | 15:March-22:March |
| HAMMUENTROP_10 | Amprion | Konventionell | positive | 262 | 1,967 | 15:March-22:March |
| UW Büttel | TenneT DE | negative | 316 | 1,893 | 23:March-05:March | |
| AVA Cluster Voslapp | TenneT DE | negative | 437 | 1,750 | 19:March-23:March | |
| HAMMUENTROP_20 | Amprion | Konventionell | positive | 223 | 1,671 | 15:March-23:March |
| Emsland Block D | Amprion | Konventionell | positive | 242 | 1,454 | 17:March-23:March |
| NEURATH_G | Amprion | Konventionell | negative | 360 | 1,080 | 20:March-23:March |
| Emsland Block B | Amprion | Konventionell | positive | 161 | 1,049 | 14:March-21:March |
| UW Büttel | TenneT DE | negative | 260 | 1,040 | 19:March-23:March | |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 260 | 1,040 | 19:March-23:March |
| Emsland Block C | Amprion | Konventionell | positive | 191 | 1,002 | 15:March-21:March |
| Emsland Block C | Amprion | Konventionell | positive | 210 | 841 | 18:March-22:March |
| NIEDERAUSSEM_K | Amprion | Konventionell | negative | 265 | 795 | 20:March-23:March |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 147 | 734 | 15:March-21:March |
| UW Büttel | TenneT DE | negative | 191 | 669 | 18:March-23:March | |
| 50H Berlin Lichterfelde | 50Hertz | Konventionell | positive | 132 | 660 | 18:March-23:March |
| NEURATH_F | Amprion | Konventionell | negative | 300 | 600 | 21:March-23:March |
| WEISWEILER_H | Amprion | Konventionell | negative | 123 | 552 | 16:March-22:March |
| HAMMUENTROP_20 | Amprion | Konventionell | positive | 150 | 489 | 18:March-21:March |
| HAMMUENTROP_10 | Amprion | Konventionell | positive | 106 | 477 | 17:March-22:March |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 148 | 444 | 14:March-17:March |
| WEISWEILER_G | Amprion | Konventionell | negative | 144 | 434 | 19:March-22:March |
| Emsland Block D | Amprion | Konventionell | positive | 156 | 428 | 15:March-18:March |
| NEURATH_F | Amprion | Konventionell | negative | 103 | 413 | 19:March-23:March |
| 50H Hamburg Wedel1 | 50Hertz | Konventionell | negative | 68 | 410 | 17:March-23:March |
| STUMMHAFEN_10 | Amprion | Konventionell | positive | 190 | 380 | 20:March-22:March |
| OWP Nordergründe | TenneT DE | negative | 75 | 373 | 18:March-23:March | |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | positive | 341 | 341 | 22:March-23:March |
| 50H Hamburg Wedel1 | 50Hertz | Konventionell | negative | 48 | 334 | 23:March-06:March |
| Boxberg (Standort) | 50Hertz | Konventionell | positive | 190 | 332 | 16:March-23:March |
| Linden GKL GT 1 | TenneT DE | Konventionell | positive | 40 | 302 | 15:March-23:March |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 151 | 301 | 23:March-01:March |
| WEISWEILER_G | Amprion | Konventionell | negative | 122 | 275 | 18:March-21:March |
| Schkopau | 50Hertz | Konventionell | positive | 128 | 256 | 21:March-23:March |
| Linden GKL GT 3 | TenneT DE | Konventionell | positive | 33 | 242 | 15:March-23:March |
| Linden GKL DT | TenneT DE | Konventionell | positive | 36 | 214 | 17:March-23:March |
| Jänschwalde (Standort) | 50Hertz | Konventionell | positive | 177 | 177 | 22:March-23:March |
| OWP Nordergründe | TenneT DE | negative | 88 | 176 | 23:March-01:March | |
| Linden GKL GT 3 | TenneT DE | Konventionell | positive | 26 | 171 | 16:March-23:March |
| Börse | TransnetBW | Sonstiges | negative | 136 | 170 | 15:March-22:March |
| Linden GKL GT 1 | TenneT DE | Konventionell | positive | 26 | 168 | 16:March-23:March |
| Linden GKL DT | TenneT DE | Konventionell | positive | 27 | 166 | 16:March-23:March |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 72 | 143 | 16:March-18:March |
| 50H InfraLeuna IKW | 50Hertz | Konventionell | positive | 35 | 140 | 18:March-22:March |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.15M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-03-15?
On 2026-03-15, estimated redispatch costs were approximately €0.5 million. This includes €0.23M for renewable curtailment compensation and €0.24M for conventional ramp-up costs.
Which power plants were most affected on 2026-03-15?
The most affected plant was AVA Cluster Voslapp (TenneT DE) with 4,912 MWh of negative redispatch.
What was the electricity spot price on 2026-03-15?
The EPEX Day-Ahead spot price for DE_LU ranged from 18 to 148 €/MWh with an average of 86 €/MWh.