← 2026-09-01

Wednesday, September 2, 2026

2026-09-03 →
3,427MWh Curtailed
4,141MWh Ramped Up
€1.36MEst. Cost
248 MWPeak Positive

Day-Ahead Spot: 87-251 €/MWh (avg 164)

TSO Breakdown

TSODirectionMeasuresTotal MWh
Amprion positive 16 44,668
TenneT DE negative 5 16,131
50Hertz negative 13 11,059
TransnetBW positive 8 7,156
TransnetBW negative 6 3,605
Amprion negative 7 2,169
50Hertz positive 8 613

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 475 11,411 22:September-22:September
Knapsack 1 Amprion Konventionell positive 534 11,082 22:September-19:September
LAUSWARD_GUDF Amprion Konventionell positive 384 8,629 23:September-22:September
KNAPSACK_20 Amprion Konventionell positive 272 6,398 22:September-22:September
NIEHL-II Amprion Konventionell positive 262 5,762 23:September-21:September
HAMMUENTROP_20 Amprion Konventionell positive 305 4,960 23:September-22:September
Netzreservekraftwerk Bexbach A Amprion Konventionell positive 231 3,237 07:September-22:September
Boxberg (Standort) 50Hertz Konventionell negative 331 2,980 22:September-22:September
Grosskraftwerk Mannheim Block 9 TransnetBW Konventionell negative 178 2,976 22:September-22:September
Grosskraftwerk Mannheim Block 7 TransnetBW Konventionell positive 107 2,565 22:September-22:September
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 271 2,437 23:September-22:September
Jänschwalde (Standort) 50Hertz Konventionell negative 137 1,643 07:September-19:September
Irsching 5 TenneT DE Konventionell negative 236 1,593 04:September-21:September
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 335 1,425 23:September-03:September
50H Berlin Lichterfelde 50Hertz Konventionell negative 140 1,404 22:September-22:September
illwerke vkw AG TransnetBW Sonstiges positive 143 1,357 22:September-22:September
UW Emden-Ost TenneT DE Erneuerbar negative 301 1,354 23:September-04:September
Emsland Block B Amprion Konventionell positive 169 1,269 13:September-21:September
Emsland Block C Amprion Konventionell positive 193 1,258 14:September-21:September
Börse TransnetBW Sonstiges positive 161 1,244 14:September-22:September
Jänschwalde (Standort) 50Hertz Konventionell negative 211 1,162 12:September-18:September
Irsching 4 TenneT DE Konventionell negative 125 904 04:September-21:September
UW Diele TenneT DE Erneuerbar negative 193 870 23:September-04:September
Netzreservekraftwerk Bexbach A Amprion Konventionell positive 250 750 17:September-20:September
Boxberg (Standort) 50Hertz Konventionell negative 147 734 07:September-12:September
Netzreservekraftwerk Bexbach A Amprion Konventionell positive 179 580 14:September-17:September
GUD_HERNE_6 Amprion Konventionell negative 236 531 19:September-22:September
WEISWEILER_H Amprion Konventionell negative 146 475 17:September-20:September
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 36 422 05:September-22:September
WEISWEILER_H Amprion Konventionell negative 180 360 22:September-00:September
WALSUM_10 Amprion Konventionell negative 179 312 22:September-00:September
KMW_KW3 Amprion Konventionell positive 177 309 22:September-00:September
WEISWEILER_G Amprion Konventionell positive 151 303 12:September-14:September
WEISWEILER_G Amprion Konventionell negative 93 302 17:September-20:September
Marbach GT 4 (bnBm) TransnetBW Konventionell positive 216 270 06:September-07:September
Grosskraftwerk Mannheim Block 9 TransnetBW Konventionell negative 155 194 06:September-07:September
Börse TransnetBW Sonstiges negative 38 170 04:September-21:September
Thyrow D (KapRes) 50Hertz Konventionell positive 10 169 05:September-22:September
Thyrow C (KapRes) 50Hertz Konventionell positive 10 169 05:September-22:September
Thyrow E (KapRes) 50Hertz Konventionell positive 10 169 05:September-22:September
STUMMHAFEN_10 Amprion Konventionell negative 105 158 22:September-00:September
Börse TransnetBW Sonstiges positive 65 145 05:September-21:September
Grosskraftwerk Mannheim Block 7 TransnetBW Konventionell positive 14 139 12:September-22:September
Grosskraftwerk Mannheim Block 9 TransnetBW Konventionell negative 14 106 14:September-22:September
Jänschwalde (Standort) 50Hertz Konventionell negative 15 85 12:September-17:September
Börse TransnetBW Sonstiges negative 55 82 23:September-03:September
Rostock Kohlekraftwerk 50Hertz Konventionell negative 80 80 23:September-00:September
illwerke vkw AG TransnetBW Sonstiges negative 101 76 06:September-07:September
Emsland Block B Amprion Konventionell positive 41 61 16:September-17:September
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 15 60 22:September-02:September

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.41M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-09-02?

On 2026-09-02, estimated redispatch costs were approximately €1.36 million. This includes €0.34M for renewable curtailment compensation and €0.8M for conventional ramp-up costs.

Which power plants were most affected on 2026-09-02?

The most affected plant was Wilhelmshaven (ENGIE) (TenneT DE) with 11,411 MWh of negative redispatch.

What was the electricity spot price on 2026-09-02?

The EPEX Day-Ahead spot price for DE_LU ranged from 87 to 251 €/MWh with an average of 164 €/MWh.