Thyrow D (KapRes)

Konventionell • 50Hertz

353Total MWh
6Measures
14 MWAvg Power
0Curtailments
6Ramp-ups

Data: 2024-07-12 to 2026-09-02

Daily Redispatch Volume

DateMeasuresTotal MWh
2026-09-02 2 189
2026-06-18 1 41
2025-07-15 1 41
2024-08-28 1 41
2024-07-12 1 41

Recent Measures

DateTSODirAvg MWMWhTime
2026-09-02 50Hertz positive 5 20 22:September-02:September
2026-09-02 50Hertz positive 10 169 05:September-22:September
2026-06-18 50Hertz positive 16 41 14:June-16:June
2025-07-15 50Hertz positive 16 41 05:July-08:July
2024-08-28 50Hertz positive 18 41 05:August-07:August
2024-07-12 50Hertz positive 16 41 05:July-08:July

Frequently Asked Questions

What is the redispatch history of Thyrow D (KapRes)?

Thyrow D (KapRes) is a Konventionell power plant in the 50Hertz grid zone. It has received 6 redispatch instructions totaling 353 MWh since 2024-07-12.

Why is Thyrow D (KapRes) frequently redispatched?

Plants in the 50Hertz zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.