Thyrow C (KapRes)
Konventionell • 50Hertz
124Total MWh
3Measures
16 MWAvg Power
0Curtailments
3Ramp-ups
Data: 2024-07-12 to 2025-07-15
Daily Redispatch Volume
| Date | Measures | Total MWh |
|---|---|---|
| 2025-07-15 | 1 | 41 |
| 2024-08-28 | 1 | 42 |
| 2024-07-12 | 1 | 41 |
Recent Measures
| Date | TSO | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|
| 2025-07-15 | 50Hertz | positive | 16 | 41 | 05:July-08:July |
| 2024-08-28 | 50Hertz | positive | 17 | 42 | 05:August-08:August |
| 2024-07-12 | 50Hertz | positive | 16 | 41 | 05:July-08:July |
Frequently Asked Questions
What is the redispatch history of Thyrow C (KapRes)?
Thyrow C (KapRes) is a Konventionell power plant in the 50Hertz grid zone. It has received 3 redispatch instructions totaling 124 MWh since 2024-07-12.
Why is Thyrow C (KapRes) frequently redispatched?
Plants in the 50Hertz zone are frequently ramped up to compensate for curtailed renewables in Northern Germany. This is part of Germany's structural North-South grid bottleneck.