2,800MWh Curtailed
2,438MWh Ramped Up
€0.82MEst. Cost
181 MWPeak Positive
Day-Ahead Spot: -2-172 €/MWh (avg 98)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| TenneT DE | negative | 19 | 29,477 |
| TenneT DE | positive | 12 | 20,885 |
| Amprion | positive | 19 | 17,512 |
| TransnetBW | positive | 6 | 1,867 |
| 50Hertz | negative | 6 | 634 |
| TransnetBW | negative | 3 | 433 |
| 50Hertz | positive | 5 | 89 |
| Amprion | negative | 1 | 30 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Börse | TenneT DE | Sonstiges | positive | 1099 | 14,836 | 02:August-22:August |
| UW Dörpen-West | TenneT DE | negative | 613 | 7,201 | 04:August-16:August | |
| ReserveKW Staudinger 5 | TenneT DE | Konventionell | positive | 333 | 3,828 | 02:August-22:August |
| AVA Cluster Voslapp | TenneT DE | negative | 287 | 3,225 | 09:August-21:August | |
| HAMMUENTROP_20 | Amprion | Konventionell | positive | 234 | 2,696 | 00:August-22:August |
| WEISWEILER_H | Amprion | Konventionell | positive | 433 | 2,597 | 16:August-22:August |
| UW Dörpen-West | TenneT DE | negative | 282 | 2,324 | 07:August-16:August | |
| WEISWEILER_H | Amprion | Konventionell | positive | 323 | 2,264 | 22:August-05:August |
| Emsland Block B | Amprion | Konventionell | positive | 271 | 2,233 | 07:August-16:August |
| Emsland Block B | Amprion | Konventionell | positive | 184 | 2,075 | 02:August-20:August |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 305 | 1,830 | 16:August-22:August |
| BAG NWAK-Cluster 17 Altheim | TenneT DE | negative | 200 | 1,800 | 07:August-16:August | |
| BAG NWAK-Cluster 16 Regensburg-Sittling | TenneT DE | negative | 200 | 1,800 | 07:August-16:August | |
| BAG NWAK-Cluster 15 Pleinting | TenneT DE | negative | 200 | 1,800 | 07:August-16:August | |
| UW Büttel | TenneT DE | negative | 183 | 1,601 | 08:August-22:August | |
| SHN Cluster Heide West T411 T412 | TenneT DE | negative | 273 | 1,500 | 15:August-20:August | |
| UW Büttel | TenneT DE | negative | 420 | 1,155 | 07:August-10:August | |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 307 | 1,151 | 22:August-01:August |
| UW Diele | TenneT DE | negative | 221 | 1,107 | 08:August-16:August | |
| Hannover-Linden GuD | TenneT DE | Konventionell | positive | 83 | 1,104 | 02:August-22:August |
| UW Büttel | TenneT DE | negative | 180 | 1,080 | 11:August-17:August | |
| KMW_KW3 | Amprion | Konventionell | positive | 190 | 902 | 05:August-17:August |
| NIEDERAUSSEM_K | Amprion | Konventionell | positive | 291 | 874 | 13:August-16:August |
| HERDECKE_H6 | Amprion | Konventionell | positive | 227 | 850 | 14:August-18:August |
| SHN Cluster Süderdonn T412 T413 | TenneT DE | negative | 133 | 667 | 15:August-20:August | |
| SHN Cluster Handewitt T414 T415 | TenneT DE | negative | 136 | 612 | 15:August-20:August | |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 331 | 580 | 07:August-09:August |
| ReserveKW Staudinger 5 | TenneT DE | Konventionell | positive | 209 | 575 | 07:August-10:August |
| KNAPSACK_20 | Amprion | Konventionell | positive | 204 | 510 | 06:August-09:August |
| HAMMUENTROP_20 | Amprion | Konventionell | positive | 127 | 509 | 06:August-18:August |
| BIBLIS_GT (bnBm) | Amprion | Konventionell | positive | 127 | 412 | 09:August-17:August |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 115 | 402 | 15:August-19:August |
| STUMMHAFEN_10 | Amprion | Konventionell | positive | 112 | 392 | 09:August-13:August |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 127 | 382 | 19:August-22:August |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 78 | 372 | 05:August-19:August |
| Emsland Block B | Amprion | Konventionell | positive | 104 | 338 | 05:August-08:August |
| Heizkraftwerk_Pforzheim | TransnetBW | Konventionell | positive | 42 | 293 | 04:August-22:August |
| KMW_KW3 | Amprion | Konventionell | positive | 188 | 282 | 07:August-09:August |
| illwerke vkw AG | TransnetBW | Sonstiges | negative | 112 | 280 | 09:August-17:August |
| GUD_HERNE_6 | Amprion | Konventionell | positive | 200 | 250 | 06:August-08:August |
| UW Büttel | TenneT DE | negative | 137 | 205 | 02:August-04:August | |
| Kraftwerk Walheim GT D | TransnetBW | Konventionell | positive | 100 | 200 | 04:August-06:August |
| UW Büttel | TenneT DE | negative | 200 | 200 | 14:August-15:August | |
| AVA Cluster Helmstedt | TenneT DE | negative | 50 | 162 | 10:August-14:August | |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 156 | 156 | 16:August-17:August |
| KMW_KW5 | Amprion | Konventionell | positive | 74 | 147 | 17:August-19:August |
| Börse | TenneT DE | Sonstiges | positive | 98 | 122 | 22:August-09:August |
| SW München KW-Pool | TenneT DE | Sonstiges | positive | 39 | 116 | 05:August-18:August |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | negative | 37 | 111 | 19:August-22:August |
| Börse | Amprion | Konventionell | positive | 182 | 91 | 07:August-08:August |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.25M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-08-06?
On 2026-08-06, estimated redispatch costs were approximately €0.82 million. This includes €0.28M for renewable curtailment compensation and €0.31M for conventional ramp-up costs.
Which power plants were most affected on 2026-08-06?
The most affected plant was Börse (TenneT DE) with 14,836 MWh of positive redispatch.
What was the electricity spot price on 2026-08-06?
The EPEX Day-Ahead spot price for DE_LU ranged from -2 to 172 €/MWh with an average of 98 €/MWh.