← 2026-04-08

Thursday, April 9, 2026

2026-04-10 →
2,281MWh Curtailed
1,826MWh Ramped Up
€0.54MEst. Cost
173 MWPeak Positive

Day-Ahead Spot: -26-155 €/MWh (avg 75)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TenneT DE negative 23 42,826
Amprion positive 35 41,371
TenneT DE positive 17 28,220
TransnetBW positive 18 16,845
50Hertz negative 25 15,755
Amprion negative 8 1,889
TransnetBW negative 2 574
50Hertz positive 4 184

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
Börse TenneT DE Sonstiges positive 997 14,953 22:April-16:April
UW Büttel TenneT DE Erneuerbar negative 880 9,682 11:April-22:April
UW Diele TenneT DE Erneuerbar negative 649 7,298 06:April-22:April
UW Büttel TenneT DE Erneuerbar negative 1184 6,810 22:April-03:April
Knapsack 1 Amprion Konventionell positive 579 6,220 04:April-22:April
ReserveKW Staudinger 5 TenneT DE Konventionell positive 399 4,888 22:April-22:April
AVA Cluster Voslapp TenneT DE Erneuerbar negative 325 3,980 09:April-22:April
AVA Cluster Voslapp TenneT DE Erneuerbar negative 297 3,717 22:April-10:April
KMW_KW3 Amprion Konventionell positive 221 3,652 22:April-14:April
Emsland Block B Amprion Konventionell positive 199 3,490 00:April-22:April
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 262 3,400 22:April-11:April
Reservekraftwerk Heilbronn Block 7 TransnetBW Konventionell positive 356 3,205 13:April-22:April
Börse TenneT DE Sonstiges negative 314 2,905 22:April-22:April
Reservekraftwerk Heilbronn Block 7 TransnetBW Konventionell positive 284 2,844 22:April-08:April
Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 TransnetBW Konventionell positive 315 2,837 22:April-07:April
Boxberg (Standort) 50Hertz Konventionell negative 389 2,724 15:April-22:April
NIEHL-II Amprion Konventionell positive 243 2,676 11:April-22:April
Irsching 4 TenneT DE Konventionell positive 379 2,464 22:April-04:April
Knapsack 1 Amprion Konventionell positive 432 2,373 01:April-06:April
Knapsack 1 Amprion Konventionell positive 487 2,192 22:April-02:April
Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 TransnetBW Konventionell positive 346 2,164 15:April-22:April
KMW_KW3 Amprion Konventionell positive 308 2,159 15:April-22:April
Boxberg (Standort) 50Hertz Konventionell negative 401 2,104 22:April-03:April
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 334 2,086 22:April-04:April
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 334 2,002 15:April-22:April
illwerke vkw AG TransnetBW Sonstiges positive 317 1,899 04:April-22:April
GERSTEINW_F (KapRes) Amprion Konventionell positive 165 1,856 10:April-22:April
GUD_HERNE_6 Amprion Konventionell positive 254 1,780 15:April-22:April
Irsching 5 TenneT DE Konventionell positive 228 1,767 00:April-07:April
GERSTEINW_G (KapRes) Amprion Konventionell positive 164 1,679 11:April-22:April
Emsland Block C Amprion Konventionell positive 134 1,505 02:April-21:April
50H Berlin Marzahn 50Hertz Konventionell negative 117 1,404 22:April-10:April
GUD_HERNE_6 Amprion Konventionell positive 228 1,312 16:April-22:April
NIEHL-31-GUD Amprion Konventionell positive 250 1,252 22:April-03:April
BAG NWAK-Cluster 15 Pleinting TenneT DE Erneuerbar negative 200 1,200 09:April-15:April
Netzreservekraftwerk BERGKAMEN_A Amprion Konventionell positive 275 1,170 22:April-02:April
STUMMHAFEN_10 Amprion Konventionell positive 218 1,090 22:April-03:April
Heizkraftwerk Altbach/Deizisau Block 2 TransnetBW Konventionell positive 207 1,085 22:April-03:April
UW Emden-Ost TenneT DE Erneuerbar negative 298 1,041 18:April-22:April
BAG NWAK-Cluster 17 Altheim TenneT DE Erneuerbar negative 169 1,016 09:April-15:April
Niederrad 1 TenneT DE Konventionell positive 40 967 22:April-22:April
50H Berlin Marzahn 50Hertz Konventionell negative 94 941 00:April-22:April
NIEDERAUSSEM_K Amprion Konventionell negative 312 938 22:April-01:April
Linden GKL GT 1 TenneT DE Konventionell positive 65 925 01:April-22:April
Netzreservekraftwerk BERGKAMEN_A Amprion Konventionell positive 303 910 19:April-22:April
Jänschwalde (Standort) 50Hertz Konventionell negative 142 855 15:April-22:April
Heizkraftwerk Altbach/Deizisau Block 2 TransnetBW Konventionell positive 119 775 15:April-22:April
NIEDERAUSSEM_G Amprion Konventionell positive 172 774 22:April-02:April
Grosskraftwerk Mannheim Block 9 TransnetBW Konventionell positive 183 733 22:April-02:April
NIEHL-II Amprion Konventionell positive 161 723 22:April-02:April

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.16M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-04-09?

On 2026-04-09, estimated redispatch costs were approximately €0.54 million. This includes €0.23M for renewable curtailment compensation and €0.19M for conventional ramp-up costs.

Which power plants were most affected on 2026-04-09?

The most affected plant was Börse (TenneT DE) with 14,953 MWh of positive redispatch.

What was the electricity spot price on 2026-04-09?

The EPEX Day-Ahead spot price for DE_LU ranged from -26 to 155 €/MWh with an average of 75 €/MWh.