5,026MWh Curtailed
5,757MWh Ramped Up
€2.22MEst. Cost
314 MWPeak Positive
Day-Ahead Spot: 192-321 €/MWh (avg 248)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| Amprion | negative | 23 | 39,348 |
| TransnetBW | positive | 11 | 13,603 |
| Amprion | positive | 4 | 12,183 |
| TenneT DE | negative | 9 | 7,851 |
| TenneT DE | positive | 8 | 1,716 |
| TransnetBW | negative | 1 | 392 |
| 50Hertz | negative | 1 | 86 |
| 50Hertz | positive | 1 | 35 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Netzreservekraftwerk Bexbach A | Amprion | Konventionell | positive | 488 | 7,312 | 06:November-21:November |
| Börse | Amprion | Konventionell | negative | 488 | 7,312 | 06:November-21:November |
| Knapsack 1 | Amprion | Konventionell | negative | 323 | 6,452 | 23:November-23:November |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 4 | TransnetBW | Konventionell | positive | 240 | 5,760 | 23:November-23:November |
| Netzreservekraftwerk HERNE_4 | Amprion | Konventionell | positive | 234 | 4,855 | 23:November-19:November |
| WALSUM_10 | Amprion | Konventionell | negative | 174 | 4,171 | 23:November-23:November |
| Irsching 5 | TenneT DE | Konventionell | negative | 179 | 3,215 | 23:November-22:November |
| NIEDERAUSSEM_G | Amprion | Konventionell | negative | 179 | 2,910 | 23:November-23:November |
| WEISWEILER_G | Amprion | Konventionell | negative | 192 | 2,588 | 04:November-22:November |
| Grosskraftwerk Mannheim Block 7 | TransnetBW | Konventionell | positive | 119 | 2,555 | 01:November-23:November |
| Wilhelmshaven | TenneT DE | Konventionell | negative | 100 | 2,400 | 23:November-23:November |
| WALSUM_10 | Amprion | Konventionell | negative | 124 | 2,350 | 00:November-23:November |
| NEURATH_G | Amprion | Konventionell | negative | 225 | 2,250 | 23:November-09:November |
| Irsching 4 | TenneT DE | Konventionell | negative | 171 | 1,885 | 23:November-21:November |
| WEISWEILER_G | Amprion | Konventionell | negative | 183 | 1,783 | 04:November-17:November |
| HAMMUENTROP_10 | Amprion | Konventionell | negative | 123 | 1,475 | 02:November-23:November |
| NIEDERAUSSEM_G | Amprion | Konventionell | negative | 145 | 1,412 | 00:November-09:November |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 348 | 1,394 | 23:November-03:November |
| HAMMUENTROP_20 | Amprion | Konventionell | negative | 121 | 1,120 | 02:November-23:November |
| Datteln_4 | Amprion | Konventionell | negative | 131 | 1,080 | 06:November-23:November |
| Grosskraftwerk Mannheim Block 7 | TransnetBW | Konventionell | positive | 120 | 1,080 | 23:November-08:November |
| NIEDERAUSSEM_K | Amprion | Konventionell | negative | 200 | 1,052 | 23:November-04:November |
| KMW_KW3 | Amprion | Konventionell | negative | 109 | 814 | 05:November-22:November |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 108 | 756 | 05:November-17:November |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 180 | 719 | 00:November-04:November |
| ReserveKW Plattling | TenneT DE | Konventionell | positive | 58 | 582 | 23:November-09:November |
| WEISWEILER_H | Amprion | Konventionell | negative | 137 | 582 | 06:November-16:November |
| ReserveKW Plattling | TenneT DE | Konventionell | positive | 39 | 524 | 05:November-23:November |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 4 | TransnetBW | Konventionell | positive | 102 | 510 | 06:November-14:November |
| Datteln_4 | Amprion | Konventionell | negative | 56 | 450 | 00:November-15:November |
| Börse | TransnetBW | Sonstiges | negative | 38 | 392 | 23:November-20:November |
| LAUSWARD_GUDF | Amprion | Konventionell | negative | 123 | 370 | 23:November-02:November |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 100 | 348 | 08:November-19:November |
| Grosskraftwerk Mannheim Block 7 | TransnetBW | Konventionell | positive | 93 | 325 | 04:November-08:November |
| LAUSWARD_GUDF | Amprion | Konventionell | negative | 96 | 289 | 02:November-22:November |
| WEISWEILER_H | Amprion | Konventionell | negative | 86 | 280 | 05:November-11:November |
| LAUSWARD_GUDF | Amprion | Konventionell | negative | 125 | 250 | 06:November-11:November |
| Braunschweig HKWM GT31 | TenneT DE | Konventionell | positive | 44 | 231 | 23:November-04:November |
| Emsland Block D | Amprion | Konventionell | negative | 70 | 209 | 05:November-08:November |
| Eltmann | TenneT DE | Konventionell | negative | 30 | 152 | 05:November-21:November |
| Emsland Block D | Amprion | Konventionell | negative | 49 | 148 | 01:November-07:November |
| Eltmann | TenneT DE | Konventionell | positive | 29 | 116 | 23:November-03:November |
| Wilhelmshaven | TenneT DE | Konventionell | negative | 35 | 115 | 19:November-23:November |
| Gebersdorf GT | TenneT DE | Konventionell | positive | 104 | 104 | 23:November-00:November |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 43 | 86 | 06:November-21:November |
| Grosskraftwerk Mannheim Block 6 | TransnetBW | Konventionell | positive | 40 | 80 | 06:November-08:November |
| Gebersdorf 2 | TenneT DE | Konventionell | positive | 38 | 76 | 06:November-08:November |
| Grosskraftwerk Mannheim Block 7 | TransnetBW | Konventionell | positive | 50 | 75 | 08:November-09:November |
| Wilhelmshaven | TenneT DE | Konventionell | negative | 13 | 52 | 10:November-14:November |
| Niederrad 1 | TenneT DE | Konventionell | positive | 13 | 52 | 10:November-14:November |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.67M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-11-04?
On 2026-11-04, estimated redispatch costs were approximately €2.22 million. This includes €0.5M for renewable curtailment compensation and €1.6M for conventional ramp-up costs.
Which power plants were most affected on 2026-11-04?
The most affected plant was Netzreservekraftwerk Bexbach A (Amprion) with 7,312 MWh of positive redispatch.
What was the electricity spot price on 2026-11-04?
The EPEX Day-Ahead spot price for DE_LU ranged from 192 to 321 €/MWh with an average of 248 €/MWh.