← 2026-10-14

Thursday, October 15, 2026

2026-10-16 →
3,629MWh Curtailed
4,648MWh Ramped Up
€1.61MEst. Cost
296 MWPeak Positive

Day-Ahead Spot: 89-270 €/MWh (avg 188)

TSO Breakdown

TSODirectionMeasuresTotal MWh
Amprion positive 34 61,648
TenneT DE negative 18 58,941
TenneT DE positive 6 17,808
50Hertz negative 15 16,131
TransnetBW positive 10 9,205
Amprion negative 5 4,412
TransnetBW negative 1 520
50Hertz positive 1 29

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
UW Dörpen-West TenneT DE Erneuerbar negative 1068 19,226 04:October-22:October
Börse TenneT DE Sonstiges positive 979 14,688 22:October-22:October
UW Diele TenneT DE Erneuerbar negative 466 8,394 04:October-22:October
Emsland Block C Amprion Konventionell positive 376 8,278 00:October-22:October
Wilhelmshaven TenneT DE Konventionell negative 397 6,846 02:October-20:October
Emsland Block B Amprion Konventionell positive 294 6,477 00:October-22:October
Wilhelmshaven TenneT DE Konventionell negative 412 5,764 22:October-12:October
NIEHL-II Amprion Konventionell positive 246 5,418 00:October-22:October
HERDECKE_H6 Amprion Konventionell positive 245 5,143 01:October-22:October
WEISWEILER_G Amprion Konventionell positive 250 4,866 22:October-22:October
NIEHL-II Amprion Konventionell positive 193 4,448 23:October-22:October
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 273 4,363 02:October-22:October
Netzreservekraftwerk HERNE_4 Amprion Konventionell positive 286 4,006 22:October-12:October
UW Dörpen-West TenneT DE Erneuerbar negative 570 3,420 22:October-04:October
Schkopau 50Hertz Konventionell negative 290 3,191 06:October-22:October
UW Büttel TenneT DE Erneuerbar negative 247 3,086 04:October-22:October
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 402 2,818 22:October-05:October
LAUSWARD_GUDF Amprion Konventionell positive 342 2,564 07:October-15:October
WEISWEILER_G Amprion Konventionell positive 206 2,424 05:October-22:October
Netzreservekraftwerk HERNE_4 Amprion Konventionell positive 294 2,356 14:October-22:October
Rostock Kohlekraftwerk 50Hertz Konventionell negative 129 2,328 22:October-22:October
UW Emden-Ost TenneT DE Erneuerbar negative 421 2,318 07:October-12:October
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 384 2,301 16:October-22:October
Datteln_4 Amprion Konventionell negative 201 2,210 04:October-15:October
NIEHL-II Amprion Konventionell positive 204 2,044 22:October-08:October
Wilhelmshaven TenneT DE Konventionell negative 499 1,995 18:October-22:October
GERSTEINW_F (KapRes) Amprion Konventionell positive 174 1,960 10:October-22:October
UW Emden-Ost TenneT DE Erneuerbar negative 315 1,888 22:October-04:October
UW Emden-Ost TenneT DE Erneuerbar negative 205 1,746 06:October-15:October
50H Hamburg Tiefstack 2 HKW SK 50Hertz Konventionell negative 82 1,731 22:October-22:October
Rostock Kohlekraftwerk 50Hertz Konventionell negative 161 1,614 06:October-22:October
HERDECKE_H6 Amprion Konventionell positive 181 1,449 22:October-22:October
HAMMUENTROP_20 Amprion Konventionell positive 182 1,318 22:October-22:October
Kiel (Küstenkraftwerk gesamt) TenneT DE Konventionell negative 112 1,232 22:October-21:October
WALSUM_10 Amprion Konventionell negative 168 1,174 05:October-16:October
50H Berlin Marzahn 50Hertz Konventionell negative 73 1,165 22:October-22:October
Emsland Block C Amprion Konventionell positive 184 1,107 23:October-05:October
Emsland Block C Amprion Konventionell positive 328 1,067 22:October-01:October
Hannover-Linden GuD TenneT DE Konventionell positive 174 1,041 16:October-22:October
50H Hamburg Wedel1 50Hertz Konventionell negative 54 969 22:October-22:October
Hannover-Linden GuD TenneT DE Konventionell positive 68 939 04:October-17:October
ReserveKW Staudinger 4 TenneT DE Konventionell positive 230 920 08:October-12:October
NIEDERAUSSEM_H Amprion Konventionell negative 124 866 08:October-15:October
UW Diele TenneT DE Erneuerbar negative 200 851 07:October-12:October
illwerke vkw AG TransnetBW Sonstiges positive 211 846 22:October-10:October
UW Dörpen-West TenneT DE Erneuerbar negative 211 845 07:October-11:October
Börse Amprion Konventionell positive 233 758 12:October-16:October
Datteln_4 Amprion Konventionell positive 178 756 07:October-12:October
50H Berlin Mitte 50Hertz Konventionell negative 68 753 22:October-22:October
KNAPSACK_20 Amprion Konventionell positive 231 752 09:October-12:October

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.48M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-10-15?

On 2026-10-15, estimated redispatch costs were approximately €1.61 million. This includes €0.36M for renewable curtailment compensation and €1.01M for conventional ramp-up costs.

Which power plants were most affected on 2026-10-15?

The most affected plant was UW Dörpen-West (TenneT DE) with 19,226 MWh of negative redispatch.

What was the electricity spot price on 2026-10-15?

The EPEX Day-Ahead spot price for DE_LU ranged from 89 to 270 €/MWh with an average of 188 €/MWh.