3,872MWh Curtailed
3,995MWh Ramped Up
€1.42MEst. Cost
222 MWPeak Positive
Day-Ahead Spot: 124-222 €/MWh (avg 166)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| Amprion | positive | 6 | 5,571 |
| Amprion | negative | 15 | 4,884 |
| TenneT DE | positive | 2 | 2,569 |
| TenneT DE | negative | 6 | 2,360 |
| TransnetBW | positive | 3 | 1,685 |
| 50Hertz | positive | 5 | 305 |
| TransnetBW | negative | 2 | 220 |
| 50Hertz | negative | 3 | 129 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| GERSTEINW_DTF2 (KapRes) | Amprion | Konventionell | positive | 156 | 3,740 | 22:August-22:August |
| WALSUM_10 | Amprion | Konventionell | negative | 96 | 1,685 | 22:August-22:August |
| Börse | TenneT DE | Sonstiges | positive | 777 | 1,554 | 05:August-07:August |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 299 | 1,195 | 16:August-20:August |
| ReserveKW Staudinger 4 | TenneT DE | Konventionell | positive | 369 | 1,015 | 22:August-00:August |
| Börse | TenneT DE | Sonstiges | negative | 369 | 1,015 | 22:August-00:August |
| GERSTEINW_GTF1 (KapRes) | Amprion | Konventionell | positive | 42 | 1,008 | 22:August-22:August |
| Irsching 5 | TenneT DE | Konventionell | negative | 179 | 760 | 14:August-19:August |
| LAUSWARD_GUDF | Amprion | Konventionell | negative | 126 | 758 | 22:August-07:August |
| CHEMIEPARK_MARL_KRAFTWERKE | Amprion | Konventionell | negative | 36 | 630 | 22:August-22:August |
| BAG NWAK-Cluster 17 Altheim | TenneT DE | negative | 100 | 550 | 10:August-16:August | |
| Emsland Block C | Amprion | Konventionell | positive | 127 | 509 | 01:August-05:August |
| Börse | TransnetBW | Sonstiges | positive | 44 | 466 | 00:August-18:August |
| HAMMUENTROP_20 | Amprion | Konventionell | negative | 141 | 389 | 15:August-18:August |
| WALSUM_10 | Amprion | Konventionell | negative | 171 | 342 | 14:August-16:August |
| KNAPSACK_20 | Amprion | Konventionell | negative | 148 | 333 | 13:August-16:August |
| INFRA_HOE_GTX1 | Amprion | Konventionell | negative | 12 | 184 | 22:August-22:August |
| GERSTEINW_GTF1 (KapRes) | Amprion | Konventionell | positive | 40 | 169 | 17:August-22:August |
| EGM_DTS | Amprion | Sonstiges | negative | 7 | 168 | 22:August-22:August |
| 50H Berlin Marzahn | 50Hertz | Konventionell | positive | 40 | 161 | 01:August-05:August |
| GERSTEINW_DTF2 (KapRes) | Amprion | Konventionell | positive | 70 | 140 | 20:August-22:August |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | negative | 64 | 129 | 13:August-15:August |
| CHEMIEPARK_MARL_KRAFTWERKE | Amprion | Konventionell | negative | 29 | 123 | 17:August-22:August |
| 50H InfraLeuna IKW | 50Hertz | Konventionell | positive | 32 | 96 | 01:August-04:August |
| Börse | TransnetBW | Sonstiges | negative | 45 | 91 | 05:August-19:August |
| HERDECKE_H6 | Amprion | Konventionell | negative | 55 | 82 | 16:August-18:August |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 38 | 77 | 13:August-16:August |
| NIEHL-II | Amprion | Konventionell | negative | 32 | 56 | 20:August-22:August |
| LAUSWARD_GUDF | Amprion | Konventionell | negative | 27 | 54 | 20:August-22:August |
| EGM_DTS | Amprion | Sonstiges | negative | 12 | 46 | 18:August-22:August |
| 50H Dresden-Nossen | 50Hertz | Konventionell | positive | 34 | 34 | 07:August-08:August |
| 50H Halle-Dieselstr HKW-BlockB | 50Hertz | Konventionell | negative | 8 | 32 | 13:August-17:August |
| HERDECKE_H6 | Amprion | Konventionell | negative | 39 | 30 | 21:August-22:August |
| Heizkraftwerk_Pforzheim | TransnetBW | Konventionell | positive | 8 | 24 | 01:August-04:August |
| Börse | 50Hertz | Sonstiges | negative | 40 | 20 | 22:August-02:August |
| UW Garrel-Ost alpha | TenneT DE | negative | 25 | 18 | 10:August-11:August | |
| OWP Borkum Riffgrund 3 | TenneT DE | negative | 25 | 12 | 12:August-12:August | |
| Börse | 50Hertz | Sonstiges | positive | 50 | 12 | 03:August-04:August |
| BIBLIS_GT (bnBm) | Amprion | Konventionell | positive | 10 | 5 | 10:August-11:August |
| WP Wilstermarsch | TenneT DE | negative | 10 | 5 | 11:August-12:August | |
| CHEMIEPARK_MARL_KRAFTWERKE | Amprion | Konventionell | negative | 4 | 4 | 13:August-14:August |
| 50H Bernburg | 50Hertz | Konventionell | positive | 2 | 2 | 07:August-08:August |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.43M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-08-19?
On 2026-08-19, estimated redispatch costs were approximately €1.42 million. This includes €0.39M for renewable curtailment compensation and €0.78M for conventional ramp-up costs.
Which power plants were most affected on 2026-08-19?
The most affected plant was GERSTEINW_DTF2 (KapRes) (Amprion) with 3,740 MWh of positive redispatch.
What was the electricity spot price on 2026-08-19?
The EPEX Day-Ahead spot price for DE_LU ranged from 124 to 222 €/MWh with an average of 166 €/MWh.