3,071MWh Curtailed
3,371MWh Ramped Up
€0.99MEst. Cost
200 MWPeak Positive
Day-Ahead Spot: 59-221 €/MWh (avg 138)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| TenneT DE | negative | 13 | 9,493 |
| Amprion | negative | 23 | 4,569 |
| TransnetBW | positive | 7 | 3,722 |
| TenneT DE | positive | 2 | 3,210 |
| Amprion | positive | 2 | 1,001 |
| 50Hertz | negative | 1 | 2 |
| 50Hertz | positive | 1 | 2 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| ReserveKW Staudinger 4 | TenneT DE | Konventionell | positive | 275 | 3,090 | 10:July-21:July |
| BAG NWAK-Cluster 15 Pleinting | TenneT DE | negative | 300 | 2,175 | 08:July-16:July | |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 299 | 2,168 | 14:July-21:July |
| BAG NWAK-Cluster 17 Altheim | TenneT DE | negative | 150 | 1,088 | 08:July-16:July | |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 229 | 1,029 | 08:July-13:July |
| NEURATH_F | Amprion | Konventionell | negative | 173 | 822 | 07:July-12:July |
| AVA Cluster Dipperz | TenneT DE | negative | 132 | 757 | 09:July-15:July | |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 167 | 750 | 08:July-13:July |
| BAG NWAK-Cluster 16 Regensburg-Sittling | TenneT DE | negative | 100 | 725 | 08:July-16:July | |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 464 | 696 | 14:July-16:July |
| GERSTEINW_DTG2 (KapRes) | Amprion | Konventionell | positive | 142 | 674 | 07:July-12:July |
| AVA Cluster Twistetal | TenneT DE | negative | 117 | 646 | 09:July-15:July | |
| WEISWEILER_G | Amprion | Konventionell | negative | 93 | 607 | 03:July-20:July |
| WEISWEILER_H | Amprion | Konventionell | negative | 82 | 552 | 03:July-20:July |
| AVA Cluster Elsen | TenneT DE | negative | 95 | 524 | 09:July-15:July | |
| NEURATH_F | Amprion | Konventionell | negative | 64 | 513 | 09:July-17:July |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 410 | 512 | 14:July-15:July |
| NEURATH_G | Amprion | Konventionell | negative | 72 | 414 | 09:July-14:July |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 200 | 400 | 15:July-17:July |
| Notfall-RD mit AVA | TenneT DE | negative | 70 | 385 | 08:July-14:July | |
| AVA Cluster Mehringen | TenneT DE | negative | 87 | 348 | 11:July-15:July | |
| AVA Cluster Würgassen | TenneT DE | negative | 66 | 329 | 10:July-15:July | |
| GERSTEINW_GTG1 (KapRes) | Amprion | Konventionell | positive | 41 | 327 | 04:July-12:July |
| WALSUM_10 | Amprion | Konventionell | negative | 172 | 214 | 14:July-16:July |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 73 | 200 | 08:July-11:July |
| NEURATH_G | Amprion | Konventionell | negative | 40 | 180 | 04:July-09:July |
| NEURATH_F | Amprion | Konventionell | negative | 120 | 150 | 14:July-15:July |
| NIEDERAUSSEM_K | Amprion | Konventionell | negative | 113 | 141 | 14:July-16:July |
| Heizkraftwerk Stuttgart-Münster GT 87 | TransnetBW | Konventionell | positive | 54 | 135 | 14:July-17:July |
| Börse | Amprion | Konventionell | negative | 179 | 134 | 14:July-16:July |
| WEISWEILER_G | Amprion | Konventionell | negative | 71 | 125 | 15:July-17:July |
| Börse | TenneT DE | Sonstiges | negative | 165 | 124 | 14:July-14:July |
| Frankfurt West 4 | TenneT DE | Konventionell | positive | 60 | 120 | 12:July-14:July |
| NIEDERAUSSEM_K | Amprion | Konventionell | negative | 120 | 120 | 14:July-15:July |
| UW Büttel | TenneT DE | negative | 60 | 120 | 12:July-14:July | |
| AVA Cluster Gießen Nord T413 T414 | TenneT DE | negative | 28 | 104 | 11:July-15:July | |
| WALSUM_10 | Amprion | Konventionell | negative | 134 | 100 | 14:July-15:July |
| WEISWEILER_H | Amprion | Konventionell | negative | 50 | 75 | 15:July-17:July |
| NEURATH_G | Amprion | Konventionell | negative | 56 | 70 | 14:July-16:July |
| AMP_WESTNETZ_TRIER_CR_WIND | Amprion | negative | 42 | 63 | 14:July-15:July | |
| NEURATH_F | Amprion | Konventionell | negative | 59 | 59 | 15:July-16:July |
| Börse | Amprion | Konventionell | negative | 117 | 58 | 14:July-15:July |
| WEISWEILER_G | Amprion | Konventionell | negative | 48 | 48 | 14:July-15:July |
| WEISWEILER_H | Amprion | Konventionell | negative | 96 | 48 | 15:July-16:July |
| CHEMIEPARK_MARL_KRAFTWERKE | Amprion | Konventionell | negative | 57 | 28 | 15:July-16:July |
| WEISWEILER_H | Amprion | Konventionell | negative | 35 | 26 | 14:July-15:July |
| AMP_WESTNETZ_NAHE_CR_WIND | Amprion | negative | 14 | 22 | 14:July-15:July | |
| Börse | 50Hertz | Sonstiges | positive | 2 | 2 | 06:July-07:July |
| 50H Köthen | 50Hertz | Konventionell | negative | 2 | 2 | 06:July-07:July |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.3M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-07-15?
On 2026-07-15, estimated redispatch costs were approximately €0.99 million. This includes €0.31M for renewable curtailment compensation and €0.57M for conventional ramp-up costs.
Which power plants were most affected on 2026-07-15?
The most affected plant was ReserveKW Staudinger 4 (TenneT DE) with 3,090 MWh of positive redispatch.
What was the electricity spot price on 2026-07-15?
The EPEX Day-Ahead spot price for DE_LU ranged from 59 to 221 €/MWh with an average of 138 €/MWh.