← 2026-07-20

Tuesday, July 21, 2026

2026-07-22 →
3,023MWh Curtailed
2,673MWh Ramped Up
€0.9MEst. Cost
176 MWPeak Positive

Day-Ahead Spot: 0-177 €/MWh (avg 113)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TenneT DE positive 5 20,202
TenneT DE negative 9 17,512
Amprion positive 9 11,077
50Hertz negative 17 2,292
TransnetBW positive 2 606
TransnetBW negative 2 393
50Hertz positive 4 234
Amprion negative 2 85

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
Börse TenneT DE Sonstiges positive 901 14,873 23:July-22:July
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 417 9,284 23:July-22:July
Irsching 4 TenneT DE Konventionell positive 328 2,545 22:July-22:July
HAMMUENTROP_20 Amprion Konventionell positive 261 2,414 23:July-08:July
BAG NWAK-Cluster 15 Pleinting TenneT DE Erneuerbar negative 250 2,250 08:July-17:July
HERDECKE_H6 Amprion Konventionell positive 223 2,010 23:July-08:July
HUCKINGEN_A Amprion Konventionell positive 80 1,900 22:July-22:July
BAG NWAK-Cluster 17 Altheim TenneT DE Erneuerbar negative 200 1,800 08:July-17:July
GERSTEINW_F (KapRes) Amprion Konventionell positive 144 1,580 22:July-09:July
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 270 1,418 22:July-03:July
Börse TenneT DE Sonstiges negative 248 1,362 14:July-20:July
Börse TenneT DE Sonstiges positive 363 1,361 15:July-19:July
ReserveKW Staudinger 5 TenneT DE Konventionell positive 240 1,258 14:July-19:July
Emsland Block B Amprion Konventionell positive 148 1,112 23:July-07:July
GERSTEINW_G (KapRes) Amprion Konventionell positive 123 1,046 22:July-07:July
UW Büttel TenneT DE Erneuerbar negative 108 623 22:July-04:July
LAUSWARD_GUDF Amprion Konventionell positive 265 596 06:July-08:July
illwerke vkw AG TransnetBW Sonstiges positive 57 579 22:July-22:July
BAG NWAK-Cluster 16 Regensburg-Sittling TenneT DE Erneuerbar negative 50 450 08:July-17:July
50H_EDIS_CR_LV_WU 50Hertz Erneuerbar negative 81 425 07:July-13:July
50H_EDIS_CR_WU_NORD 50Hertz Erneuerbar negative 81 425 07:July-13:July
Börse TransnetBW Sonstiges negative 224 392 22:July-15:July
Jänschwalde (Standort) 50Hertz Konventionell negative 202 354 06:July-08:July
GUD_HERNE_6 Amprion Konventionell positive 267 334 07:July-08:July
Irsching 4 TenneT DE Konventionell negative 113 310 22:July-00:July
50H_EDIS_CR_SOW_Sued 50Hertz Erneuerbar negative 92 275 10:July-13:July
Lippendorf 50Hertz Konventionell negative 124 216 06:July-08:July
Börse 50Hertz Sonstiges positive 37 167 22:July-22:July
Braunschweig HKWM GT31 TenneT DE Konventionell positive 39 166 04:July-08:July
50H Berlin Marzahn 50Hertz Konventionell negative 45 135 04:July-08:July
50H Berlin Lichterfelde 50Hertz Konventionell negative 60 120 06:July-08:July
50H_EDIS_CR_PAS 50Hertz Erneuerbar negative 69 120 13:July-15:July
GERSTEINW_F (KapRes) Amprion Konventionell positive 38 85 19:July-22:July
Jänschwalde (Standort) 50Hertz Konventionell negative 135 68 06:July-07:July
50H_EDIS_CR_HND 50Hertz Erneuerbar negative 36 62 09:July-15:July
CHEMIEPARK_MARL_KRAFTWERKE Amprion Konventionell negative 26 58 19:July-22:July
Boxberg (Standort) 50Hertz Konventionell positive 10 30 22:July-01:July
INFRA_HOE_GTX2 Amprion Konventionell negative 12 27 19:July-22:July
50H Dresden-Reick 50Hertz Konventionell positive 27 27 23:July-00:July
Börse TransnetBW Sonstiges positive 35 27 04:July-06:July
50H PV Witznitz 50Hertz Erneuerbar negative 100 25 08:July-08:July
50H Erfurt-Ost HKW GuD 50Hertz Konventionell negative 21 21 07:July-08:July
UW Büttel TenneT DE Erneuerbar negative 55 14 23:July-23:July
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 50 12 08:July-08:July
50H PV Bartow 50Hertz Erneuerbar negative 50 12 08:July-08:July
Boxberg (Standort) 50Hertz Konventionell positive 10 10 04:July-05:July
50H Halle-Dieselstr HKW-BlockB 50Hertz Konventionell negative 9 9 07:July-08:July
50H BASF Schwarzheide 50Hertz Konventionell negative 7 7 07:July-08:July
50H Dresden-Reick 50Hertz Konventionell negative 6 6 07:July-08:July
Börse TransnetBW Sonstiges negative 1 1 06:July-08:July

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.27M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-07-21?

On 2026-07-21, estimated redispatch costs were approximately €0.9 million. This includes €0.3M for renewable curtailment compensation and €0.38M for conventional ramp-up costs.

Which power plants were most affected on 2026-07-21?

The most affected plant was Börse (TenneT DE) with 14,873 MWh of positive redispatch.

What was the electricity spot price on 2026-07-21?

The EPEX Day-Ahead spot price for DE_LU ranged from 0 to 177 €/MWh with an average of 113 €/MWh.