2,084MWh Curtailed
1,512MWh Ramped Up
€0.44MEst. Cost
137 MWPeak Positive

Day-Ahead Spot: -3-164 €/MWh (avg 65)

TSO Breakdown

TSODirectionMeasuresTotal MWh
TenneT DE negative 28 85,620
Amprion positive 26 36,489
TransnetBW positive 10 10,194
50Hertz negative 14 7,365
TenneT DE positive 12 3,268
50Hertz positive 12 2,607
Amprion negative 1 175

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
UW Büttel TenneT DE Erneuerbar negative 949 17,081 05:March-23:March
AVA Cluster Voslapp TenneT DE Erneuerbar negative 756 11,529 07:March-23:March
UW Dörpen-West TenneT DE Erneuerbar negative 636 11,449 05:March-23:March
AVA Cluster Voslapp TenneT DE Erneuerbar negative 731 8,412 23:March-10:March
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 371 6,589 23:March-16:March
Emsland Block D Amprion Konventionell positive 413 5,779 23:March-13:March
Emsland Block D Amprion Konventionell positive 335 4,521 03:March-22:March
SHN Cluster Handewitt T414 T415 TenneT DE Erneuerbar negative 373 4,475 11:March-23:March
50H_EDIS_CR_PAS 50Hertz Erneuerbar negative 255 4,150 23:March-15:March
UW Dörpen-West TenneT DE Erneuerbar negative 649 3,892 23:March-05:March
SHN Cluster Handewitt T414 T415 TenneT DE Erneuerbar negative 315 3,775 23:March-11:March
UW Büttel TenneT DE Erneuerbar negative 605 3,630 23:March-05:March
UW Dörpen-West TenneT DE Erneuerbar negative 269 3,230 04:March-17:March
Emsland Block D Amprion Konventionell positive 317 3,014 04:March-22:March
UW Diele TenneT DE Erneuerbar negative 338 2,784 09:March-22:March
HAMMUENTROP_10 Amprion Konventionell positive 308 2,620 13:March-21:March
NEURATH_G Amprion Konventionell positive 324 2,596 15:March-23:March
GUD_HERNE_6 Amprion Konventionell positive 250 2,500 09:March-19:March
SHN Cluster Heide West T411 T412 TenneT DE Erneuerbar negative 291 2,475 23:March-07:March
LAUSWARD_GUDF Amprion Konventionell positive 290 2,245 02:March-20:March
AVA Cluster Sottrum T411 T413 TenneT DE Erneuerbar negative 198 2,125 23:March-09:March
SHN Cluster Heide West T411 T412 TenneT DE Erneuerbar negative 304 2,050 16:March-23:March
Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 TransnetBW Konventionell positive 228 1,880 08:March-23:March
Emsland Block D Amprion Konventionell positive 248 1,795 10:March-22:March
AVA Cluster Lehrte TenneT DE Erneuerbar negative 98 1,648 01:March-18:March
HAMMUENTROP_20 Amprion Konventionell positive 235 1,529 23:March-05:March
Emsland Block C Amprion Konventionell positive 170 1,528 06:March-20:March
HAMMUENTROP_20 Amprion Konventionell positive 209 1,512 14:March-21:March
AVA Cluster Sottrum T411 T413 TenneT DE Erneuerbar negative 200 1,450 15:March-23:March
UW Diele TenneT DE Erneuerbar negative 154 1,382 06:March-16:March
Emsland Block C Amprion Konventionell positive 205 1,283 01:March-08:March
GUD_HERNE_6 Amprion Konventionell positive 349 1,046 04:March-10:March
Emsland Block D Amprion Konventionell positive 366 1,008 07:March-10:March
Schwarze Pumpe (Standort) 50Hertz Konventionell positive 313 938 15:March-23:March
50H_EDIS_CR_PAS 50Hertz Erneuerbar negative 203 915 18:March-23:March
Boxberg (Standort) 50Hertz Konventionell positive 435 870 21:March-23:March
Niederrad 1 TenneT DE Konventionell positive 43 856 23:March-19:March
WP Schafflund TenneT DE Erneuerbar negative 95 853 09:March-23:March
NIEDERAUSSEM_K Amprion Konventionell positive 255 827 19:March-23:March
UW Diele TenneT DE Erneuerbar negative 151 756 23:March-04:March
Niederrad 1 TenneT DE Konventionell positive 44 667 08:March-23:March
illwerke vkw AG TransnetBW Sonstiges positive 152 607 04:March-09:March
SHN Cluster Süderdonn T411 TenneT DE Erneuerbar negative 207 570 14:March-17:March
SHN Cluster Heide West T413 TenneT DE Erneuerbar negative 95 568 14:March-22:March
NIEHL-II Amprion Konventionell positive 110 521 08:March-20:March
HAMMUENTROP_20 Amprion Konventionell positive 236 471 21:March-23:March
UW Diele TenneT DE Erneuerbar negative 236 471 21:March-23:March
50H_EDIS_CR_WU 50Hertz Erneuerbar negative 97 438 09:March-13:March
Frankfurt West 4 TenneT DE Konventionell positive 72 431 03:March-09:March
illwerke vkw AG TransnetBW Sonstiges positive 88 396 04:March-17:March

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.13M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-03-12?

On 2026-03-12, estimated redispatch costs were approximately €0.44 million. This includes €0.21M for renewable curtailment compensation and €0.14M for conventional ramp-up costs.

Which power plants were most affected on 2026-03-12?

The most affected plant was UW Büttel (TenneT DE) with 17,081 MWh of negative redispatch.

What was the electricity spot price on 2026-03-12?

The EPEX Day-Ahead spot price for DE_LU ranged from -3 to 164 €/MWh with an average of 65 €/MWh.