2,568MWh Curtailed
2,442MWh Ramped Up
€0.62MEst. Cost
138 MWPeak Positive
Day-Ahead Spot: 86-151 €/MWh (avg 111)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| TenneT DE | negative | 16 | 27,884 |
| TenneT DE | positive | 12 | 13,494 |
| Amprion | positive | 9 | 8,816 |
| TransnetBW | positive | 12 | 5,115 |
| Amprion | negative | 6 | 2,015 |
| 50Hertz | negative | 6 | 435 |
| 50Hertz | positive | 2 | 422 |
| TransnetBW | negative | 2 | 109 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 465 | 8,483 | 04:February-23:February |
| ReserveKW Staudinger 5 | TenneT DE | Konventionell | positive | 317 | 4,441 | 02:February-16:February |
| UW Büttel | TenneT DE | negative | 417 | 4,166 | 05:February-15:February | |
| ReserveKW Zolling 5 | TenneT DE | Konventionell | positive | 216 | 3,890 | 23:February-17:February |
| Börse | TenneT DE | Sonstiges | negative | 413 | 3,824 | 13:February-23:February |
| Emsland Block C | Amprion | Konventionell | positive | 220 | 3,133 | 03:February-18:February |
| Netzreservekraftwerk BERGKAMEN_A | Amprion | Konventionell | positive | 281 | 2,462 | 00:February-09:February |
| Börse | TenneT DE | Sonstiges | negative | 241 | 2,106 | 14:February-23:February |
| ReserveKW Zolling 5 | TenneT DE | Konventionell | positive | 247 | 2,100 | 14:February-23:February |
| Irsching 4 | TenneT DE | Konventionell | negative | 179 | 1,656 | 23:February-10:February |
| Grosskraftwerk Mannheim Block 7 | TransnetBW | Konventionell | positive | 123 | 1,574 | 05:February-18:February |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 171 | 1,026 | 14:February-20:February |
| SHN Cluster Handewitt T414 T415 | TenneT DE | negative | 164 | 1,025 | 04:February-11:February | |
| Emsland Block C | Amprion | Konventionell | positive | 182 | 911 | 17:February-22:February |
| SHN Cluster Klixbüll | TenneT DE | negative | 162 | 850 | 05:February-11:February | |
| SHN Cluster Husum Nord | TenneT DE | negative | 162 | 850 | 05:February-11:February | |
| SHN Cluster Heide West T411 T412 | TenneT DE | negative | 162 | 850 | 05:February-11:February | |
| ReserveKW Staudinger 5 | TenneT DE | Konventionell | positive | 198 | 840 | 05:February-10:February |
| ReserveKW Staudinger 5 | TenneT DE | Konventionell | positive | 272 | 815 | 23:February-02:February |
| Börse | TenneT DE | Sonstiges | negative | 272 | 815 | 23:February-02:February |
| Emsland Block C | Amprion | Konventionell | positive | 94 | 756 | 11:February-20:February |
| KMW_KW5 | Amprion | Konventionell | positive | 71 | 712 | 05:February-15:February |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 109 | 682 | 23:February-08:February |
| NIEHL-31-GUD | Amprion | Konventionell | negative | 186 | 650 | 05:February-09:February |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 251 | 628 | 23:February-01:February |
| Irsching 5 | TenneT DE | Konventionell | negative | 68 | 610 | 05:February-22:February |
| Kraftwerk Walheim GT D | TransnetBW | Konventionell | positive | 120 | 480 | 07:February-11:February |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 61 | 476 | 05:February-14:February |
| Reservekraftwerk Marbach GT 3 | TransnetBW | Konventionell | positive | 77 | 460 | 05:February-11:February |
| Irsching 4 | TenneT DE | Konventionell | negative | 114 | 455 | 11:February-15:February |
| SHN Cluster Süderdonn T411 | TenneT DE | negative | 100 | 450 | 05:February-10:February | |
| Grosskraftwerk Mannheim Block 7 | TransnetBW | Konventionell | positive | 56 | 447 | 07:February-15:February |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 118 | 414 | 05:February-09:February |
| WEISWEILER_VGTG3 | Amprion | Konventionell | positive | 136 | 408 | 15:February-18:February |
| ReserveKW Ingolstadt 4 | TenneT DE | Konventionell | positive | 79 | 394 | 11:February-16:February |
| Knapsack 1 | Amprion | Konventionell | negative | 96 | 362 | 05:February-09:February |
| Netzreservekraftwerk GTKW-DA-POOL | Amprion | Konventionell | positive | 70 | 351 | 06:February-11:February |
| Würzburg GT 2 | TenneT DE | Konventionell | positive | 32 | 350 | 05:February-16:February |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 138 | 344 | 12:February-15:February |
| HAMMUENTROP_10 | Amprion | Konventionell | negative | 114 | 343 | 20:February-23:February |
| Gebersdorf GT | TenneT DE | Konventionell | positive | 48 | 311 | 05:February-12:February |
| HAMMUENTROP_20 | Amprion | Konventionell | negative | 78 | 310 | 23:February-08:February |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | positive | 95 | 262 | 02:February-05:February |
| Markersbach (Standort) | 50Hertz | Sonstiges | positive | 200 | 250 | 05:February-08:February |
| HAMMUENTROP_10 | Amprion | Konventionell | negative | 110 | 220 | 23:February-01:February |
| Heizkraftwerk Heilbronn Block 7 | TransnetBW | Konventionell | positive | 82 | 206 | 04:February-07:February |
| Schkopau | 50Hertz | Konventionell | positive | 86 | 172 | 00:February-05:February |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 51 | 154 | 01:February-04:February |
| 50H Hamburg Wedel1 | 50Hertz | Konventionell | negative | 23 | 138 | 05:February-11:February |
| Knapsack 1 | Amprion | Konventionell | negative | 130 | 130 | 06:February-07:February |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.19M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-02-05?
On 2026-02-05, estimated redispatch costs were approximately €0.62 million. This includes €0.26M for renewable curtailment compensation and €0.34M for conventional ramp-up costs.
Which power plants were most affected on 2026-02-05?
The most affected plant was Wilhelmshaven (ENGIE) (TenneT DE) with 8,483 MWh of negative redispatch.
What was the electricity spot price on 2026-02-05?
The EPEX Day-Ahead spot price for DE_LU ranged from 86 to 151 €/MWh with an average of 111 €/MWh.