← 2026-01-30

Saturday, January 31, 2026

2026-02-01 →
2,480MWh Curtailed
2,724MWh Ramped Up
€0.9MEst. Cost
146 MWPeak Positive

Day-Ahead Spot: 90-142 €/MWh (avg 109)

TSO Breakdown

TSODirectionMeasuresTotal MWh
Amprion positive 22 57,648
TenneT DE negative 12 35,801
TenneT DE positive 7 33,131
50Hertz negative 15 22,559
Amprion negative 6 10,907
TransnetBW positive 13 8,350
TransnetBW negative 1 22

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
Börse TenneT DE Sonstiges positive 1094 26,266 23:January-23:February
Wilhelmshaven (ENGIE) TenneT DE Konventionell negative 701 16,826 23:January-23:February
Emsland Block D Amprion Konventionell positive 539 12,946 23:January-23:February
UW Büttel TenneT DE Erneuerbar negative 710 12,776 05:January-23:January
KMW_KW3 Amprion Konventionell positive 328 7,870 23:January-23:February
WALSUM_10 Amprion Konventionell negative 327 6,546 00:January-22:January
Jänschwalde (Standort) 50Hertz Konventionell negative 317 5,390 06:January-23:January
Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 TransnetBW Konventionell positive 220 5,280 23:January-23:February
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 319 5,109 07:January-23:January
HAMMUENTROP_10 Amprion Konventionell positive 288 4,754 06:January-23:January
Knapsack 1 Amprion Konventionell positive 408 4,078 06:January-22:January
HAMMUENTROP_20 Amprion Konventionell positive 263 3,873 07:January-21:January
Knapsack 1 Amprion Konventionell positive 461 3,686 11:January-19:January
HAMMUENTROP_10 Amprion Konventionell positive 236 3,659 23:January-23:February
Knapsack 1 Amprion Konventionell positive 306 3,364 12:January-23:January
UW Dörpen-West TenneT DE Erneuerbar negative 187 3,360 05:January-23:January
WEISWEILER_G Amprion Konventionell negative 181 2,720 00:January-15:January
Emsland Block B Amprion Konventionell positive 209 2,716 05:January-18:January
Irsching 5 TenneT DE Konventionell positive 230 2,648 03:January-14:January
Irsching 5 TenneT DE Konventionell positive 195 2,636 07:January-23:January
Rostock Kohlekraftwerk 50Hertz Konventionell negative 179 2,512 07:January-21:January
KNAPSACK_20 Amprion Konventionell positive 229 2,409 05:January-23:January
50H Berlin Lichterfelde 50Hertz Konventionell negative 148 2,368 07:January-23:January
Emsland Block C Amprion Konventionell positive 210 2,310 23:January-10:February
Rostock Kohlekraftwerk 50Hertz Konventionell negative 128 1,538 00:January-23:January
Boxberg (Standort) 50Hertz Konventionell negative 254 1,526 12:January-18:January
Emsland Block B Amprion Konventionell positive 210 1,260 23:January-05:February
Emsland Block B Amprion Konventionell positive 168 1,259 15:January-23:January
WALSUM_10 Amprion Konventionell negative 170 1,106 23:January-17:February
ReserveKW Ingolstadt 4 TenneT DE Konventionell positive 133 1,098 06:January-20:January
UW Büttel TenneT DE Erneuerbar negative 315 944 02:January-05:January
50H Berlin Lichterfelde 50Hertz Konventionell negative 61 920 23:January-14:February
50H Berlin Marzahn 50Hertz Konventionell negative 60 900 07:January-22:January
50H Berlin Mitte 50Hertz Konventionell negative 53 897 05:January-23:January
Heizkraftwerk Heilbronn Block 7 TransnetBW Konventionell positive 149 857 07:January-12:January
KMW_KW3 Amprion Konventionell positive 116 810 16:January-23:January
UW Dörpen-West TenneT DE Erneuerbar negative 216 702 23:January-02:February
KNAPSACK_20 Amprion Konventionell positive 216 702 23:January-02:February
Emsland Block D Amprion Konventionell positive 120 602 05:January-12:January
50H Berlin Marzahn 50Hertz Konventionell negative 46 556 23:January-14:February
illwerke vkw AG TransnetBW Sonstiges positive 165 496 02:January-05:January
KNAPSACK_20 Amprion Konventionell positive 167 460 10:January-12:January
UW Dörpen-West TenneT DE Erneuerbar negative 190 380 06:January-08:January
Rostock Kohlekraftwerk 50Hertz Konventionell negative 125 376 23:January-02:February
OWP Nordergründe TenneT DE Erneuerbar negative 84 337 01:January-05:January
illwerke vkw AG TransnetBW Sonstiges positive 96 335 12:January-22:January
HAMMUENTROP_10 Amprion Konventionell positive 101 304 20:January-23:January
WEISWEILER_G Amprion Konventionell negative 100 300 23:January-02:February
NIEHL-31-GUD Amprion Konventionell positive 46 278 08:January-23:January
Heizkraftwerk Altbach/Deizisau Block 2 TransnetBW Konventionell positive 93 278 02:January-05:January

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.27M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-01-31?

On 2026-01-31, estimated redispatch costs were approximately €0.9 million. This includes €0.25M for renewable curtailment compensation and €0.38M for conventional ramp-up costs.

Which power plants were most affected on 2026-01-31?

The most affected plant was Börse (TenneT DE) with 26,266 MWh of positive redispatch.

What was the electricity spot price on 2026-01-31?

The EPEX Day-Ahead spot price for DE_LU ranged from 90 to 142 €/MWh with an average of 109 €/MWh.