2,200MWh Curtailed
2,218MWh Ramped Up
€0.63MEst. Cost
116 MWPeak Positive
Day-Ahead Spot: 81-121 €/MWh (avg 95)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| TransnetBW | positive | 17 | 32,748 |
| Amprion | negative | 17 | 20,262 |
| TenneT DE | negative | 8 | 18,577 |
| TenneT DE | positive | 3 | 17,470 |
| 50Hertz | negative | 9 | 4,533 |
| 50Hertz | positive | 9 | 2,525 |
| Amprion | positive | 2 | 502 |
| TransnetBW | negative | 1 | 35 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Börse | TenneT DE | Sonstiges | positive | 760 | 15,190 | 23:January-21:January |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 536 | 12,868 | 23:January-23:January |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 516 | 12,382 | 23:January-23:January |
| Emsland Block D | Amprion | Konventionell | negative | 554 | 9,966 | 23:January-23:January |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 280 | 6,722 | 23:January-23:January |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 478 | 4,778 | 13:January-23:January |
| Reservekraftwerk Rheinhafen-Dampfkraftwerk Karlsruhe Block 7 | TransnetBW | Konventionell | positive | 349 | 2,618 | 15:January-23:January |
| 50H_EDIS_CR_PAS | 50Hertz | negative | 177 | 2,612 | 00:January-15:January | |
| Börse | TenneT DE | Sonstiges | positive | 555 | 2,220 | 19:January-23:January |
| Grosskraftwerk Mannheim Block 8 | TransnetBW | Konventionell | positive | 156 | 1,952 | 10:January-23:January |
| UW Büttel | TenneT DE | negative | 282 | 1,690 | 23:January-05:January | |
| HAMMUENTROP_20 | Amprion | Konventionell | negative | 162 | 1,498 | 23:January-21:January |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 130 | 1,433 | 12:January-23:January |
| NEURATH_G | Amprion | Konventionell | negative | 340 | 1,358 | 18:January-22:January |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 117 | 1,348 | 10:January-23:January |
| HAMMUENTROP_20 | Amprion | Konventionell | negative | 126 | 1,256 | 13:January-23:January |
| HAMMUENTROP_10 | Amprion | Konventionell | negative | 130 | 1,039 | 13:January-22:January |
| NIEHL-II | Amprion | Konventionell | negative | 106 | 954 | 23:January-23:January |
| Knapsack 1 | Amprion | Konventionell | negative | 248 | 868 | 17:January-21:January |
| 50H Hamburg Wedel1 | 50Hertz | Konventionell | negative | 45 | 836 | 23:January-23:January |
| AVA Cluster Voslapp | TenneT DE | negative | 101 | 784 | 23:January-07:January | |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 77 | 691 | 23:January-22:January |
| Rheinhafen-Dampfkraftwerk Karlsruhe Block 8 | TransnetBW | Konventionell | positive | 200 | 652 | 17:January-21:January |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 178 | 624 | 13:January-17:January |
| illwerke vkw AG | TransnetBW | Sonstiges | positive | 141 | 600 | 17:January-22:January |
| Jänschwalde (Standort) | 50Hertz | Konventionell | positive | 144 | 577 | 23:January-03:January |
| 50H_WEMA_CR_GOE | 50Hertz | negative | 47 | 550 | 00:January-12:January | |
| Schkopau | 50Hertz | Konventionell | positive | 145 | 543 | 19:January-22:January |
| Emsland Block D | Amprion | Konventionell | negative | 190 | 475 | 19:January-23:January |
| Boxberg (Standort) | 50Hertz | Konventionell | positive | 156 | 468 | 23:January-06:January |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | positive | 50 | 448 | 23:January-18:January |
| KNAPSACK_20 | Amprion | Konventionell | negative | 175 | 437 | 18:January-21:January |
| HAMMUENTROP_10 | Amprion | Konventionell | negative | 143 | 430 | 23:January-23:January |
| Datteln_4 | Amprion | Konventionell | negative | 171 | 385 | 16:January-19:January |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 99 | 370 | 18:January-22:January |
| NIEHL-II | Amprion | Konventionell | negative | 121 | 362 | 18:January-21:January |
| Grosskraftwerk Mannheim Block 9 | TransnetBW | Konventionell | positive | 167 | 334 | 20:January-22:January |
| Grosskraftwerk Mannheim Block 9 | TransnetBW | Konventionell | positive | 88 | 330 | 19:January-23:January |
| NIEHL-31-GUD | Amprion | Konventionell | negative | 52 | 324 | 23:January-23:January |
| Grosskraftwerk Mannheim Block 8 | TransnetBW | Konventionell | positive | 161 | 322 | 21:January-23:January |
| NIEHL-31-GUD | Amprion | Konventionell | negative | 150 | 300 | 19:January-21:January |
| Heizkraftwerk Altbach/Deizisau Block 2 | TransnetBW | Konventionell | positive | 59 | 297 | 18:January-23:January |
| NIEHL-II | Amprion | Konventionell | negative | 95 | 284 | 20:January-23:January |
| Netzreservekraftwerk GTKW-DA-POOL | Amprion | Konventionell | positive | 90 | 270 | 17:January-20:January |
| UW Büttel | TenneT DE | negative | 123 | 246 | 18:January-20:January | |
| KMW_KW5 | Amprion | Konventionell | positive | 58 | 232 | 17:January-21:January |
| Datteln_4 | Amprion | Konventionell | negative | 98 | 196 | 18:January-20:January |
| Boxberg (Standort) | 50Hertz | Konventionell | negative | 165 | 165 | 17:January-18:January |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 36 | 145 | 15:January-19:January |
| Schkopau | 50Hertz | Konventionell | positive | 134 | 134 | 20:January-21:January |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.19M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-01-11?
On 2026-01-11, estimated redispatch costs were approximately €0.63 million. This includes €0.22M for renewable curtailment compensation and €0.28M for conventional ramp-up costs.
Which power plants were most affected on 2026-01-11?
The most affected plant was Börse (TenneT DE) with 15,190 MWh of positive redispatch.
What was the electricity spot price on 2026-01-11?
The EPEX Day-Ahead spot price for DE_LU ranged from 81 to 121 €/MWh with an average of 95 €/MWh.