← 2026-07-28

Wednesday, July 29, 2026

2026-07-30 →
2,907MWh Curtailed
2,984MWh Ramped Up
€0.96MEst. Cost
326 MWPeak Positive

Day-Ahead Spot: 0-352 €/MWh (avg 126)

TSO Breakdown

TSODirectionMeasuresTotal MWh
Amprion positive 8 7,654
TenneT DE negative 4 5,359
Amprion negative 3 1,743
TransnetBW negative 3 628
50Hertz negative 4 573
50Hertz positive 1 6

Plant-Level Redispatch Measures

PlantTSOFuelDirAvg MWMWhTime
GERSTEINW_DTG2 (KapRes) Amprion Konventionell positive 153 3,669 22:July-22:July
BAG NWAK-Cluster 15 Pleinting TenneT DE Erneuerbar negative 250 2,125 07:July-16:July
BAG NWAK-Cluster 17 Altheim TenneT DE Erneuerbar negative 250 2,125 07:July-16:July
HAMMUENTROP_20 Amprion Konventionell positive 238 2,083 22:July-07:July
LAUSWARD_GUDF Amprion Konventionell negative 156 1,400 22:July-07:July
GERSTEINW_GTG1 (KapRes) Amprion Konventionell positive 42 1,008 22:July-22:July
BAG NWAK-Cluster 16 Regensburg-Sittling TenneT DE Erneuerbar negative 100 850 07:July-16:July
Heizkraftwerk Altbach/Deizisau Block 2 TransnetBW Konventionell negative 128 542 22:July-03:July
GUD_HERNE_6 Amprion Konventionell positive 333 500 06:July-08:July
Schwarze Pumpe (Standort) 50Hertz Konventionell negative 278 418 06:July-08:July
Datteln_4 Amprion Konventionell negative 73 309 17:July-22:July
Irsching 4 TenneT DE Konventionell negative 86 259 23:July-02:July
GERSTEINW_GTG1 (KapRes) Amprion Konventionell positive 40 169 17:July-22:July
GERSTEINW_DTG2 (KapRes) Amprion Konventionell positive 70 140 20:July-22:July
Lippendorf 50Hertz Konventionell negative 112 112 07:July-08:July
Börse TransnetBW Sonstiges negative 23 73 22:July-09:July
WEISWEILER_H Amprion Konventionell positive 58 73 06:July-08:July
50H PV Witznitz 50Hertz Erneuerbar negative 143 36 08:July-08:July
CHEMIEPARK_MARL_KRAFTWERKE Amprion Konventionell negative 34 34 22:July-23:July
illwerke vkw AG TransnetBW Sonstiges negative 10 12 12:July-14:July
BIBLIS_GT (bnBm) Amprion Konventionell positive 10 12 12:July-14:July
Jänschwalde (Standort) 50Hertz Konventionell negative 29 7 08:July-08:July
Börse 50Hertz Sonstiges positive 24 6 16:July-16:July

How BESS Can Reduce These Costs

Battery Energy Storage Systems at congestion points could have avoided an estimated €0.29M of today's redispatch costs by absorbing excess wind energy locally.

Learn BESS Arbitrage (Free) Stromfee AI Platform

Frequently Asked Questions

How much did redispatch cost on 2026-07-29?

On 2026-07-29, estimated redispatch costs were approximately €0.96 million. This includes €0.29M for renewable curtailment compensation and €0.47M for conventional ramp-up costs.

Which power plants were most affected on 2026-07-29?

The most affected plant was GERSTEINW_DTG2 (KapRes) (Amprion) with 3,669 MWh of positive redispatch.

What was the electricity spot price on 2026-07-29?

The EPEX Day-Ahead spot price for DE_LU ranged from 0 to 352 €/MWh with an average of 126 €/MWh.