3,133MWh Curtailed
3,317MWh Ramped Up
€1.06MEst. Cost
172 MWPeak Positive
Day-Ahead Spot: 98-177 €/MWh (avg 139)
TSO Breakdown
| TSO | Direction | Measures | Total MWh |
|---|---|---|---|
| TenneT DE | negative | 5 | 10,472 |
| Amprion | positive | 4 | 2,603 |
| 50Hertz | negative | 8 | 2,185 |
| TransnetBW | positive | 3 | 799 |
| Amprion | negative | 6 | 771 |
| TransnetBW | negative | 2 | 195 |
Plant-Level Redispatch Measures
| Plant | TSO | Fuel | Dir | Avg MW | MWh | Time |
|---|---|---|---|---|---|---|
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 553 | 8,012 | 23:July-22:July |
| HERDECKE_H6 | Amprion | Konventionell | positive | 211 | 2,106 | 23:July-22:July |
| Wilhelmshaven (ENGIE) | TenneT DE | Konventionell | negative | 156 | 972 | 13:July-20:July |
| 50H_EDIS_CR_WU_NORD | 50Hertz | negative | 206 | 875 | 10:July-15:July | |
| Börse | TransnetBW | Sonstiges | positive | 104 | 701 | 23:July-21:July |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 91 | 639 | 23:July-22:July |
| BAG NWAK-Cluster 15 Pleinting | TenneT DE | negative | 150 | 638 | 11:July-16:July | |
| BAG NWAK-Cluster 17 Altheim | TenneT DE | negative | 150 | 638 | 11:July-16:July | |
| HAMMUENTROP_20 | Amprion | Konventionell | positive | 205 | 308 | 07:July-09:July |
| Jänschwalde (Standort) | 50Hertz | Konventionell | negative | 300 | 300 | 08:July-09:July |
| HAMMUENTROP_20 | Amprion | Konventionell | negative | 189 | 236 | 23:July-00:July |
| WEISWEILER_G | Amprion | Konventionell | negative | 81 | 222 | 15:July-18:July |
| WEISWEILER_H | Amprion | Konventionell | negative | 78 | 215 | 15:July-18:July |
| BAG NWAK-Cluster 16 Regensburg-Sittling | TenneT DE | negative | 50 | 212 | 11:July-16:July | |
| NIEHL-II | Amprion | Konventionell | positive | 180 | 180 | 08:July-09:July |
| Börse | TransnetBW | Sonstiges | negative | 95 | 142 | 09:July-19:July |
| 50H_EDIS_CR_LV_WU | 50Hertz | negative | 92 | 138 | 12:July-14:July | |
| WALSUM_10 | Amprion | Konventionell | negative | 82 | 82 | 14:July-15:July |
| Börse | TransnetBW | Sonstiges | positive | 46 | 80 | 13:July-19:July |
| 50H Berlin Marzahn | 50Hertz | Konventionell | negative | 76 | 76 | 08:July-09:July |
| 50H_EDIS_CR_WU_SUED | 50Hertz | negative | 100 | 75 | 10:July-11:July | |
| Schwarze Pumpe (Standort) | 50Hertz | Konventionell | negative | 54 | 54 | 08:July-09:July |
| Börse | TransnetBW | Sonstiges | negative | 18 | 53 | 23:July-14:July |
| Schkopau | 50Hertz | Konventionell | negative | 110 | 28 | 07:July-08:July |
| Heizkraftwerk_Pforzheim | TransnetBW | Konventionell | positive | 18 | 18 | 17:July-18:July |
| BIBLIS_GT (bnBm) | Amprion | Konventionell | positive | 7 | 9 | 07:July-09:July |
| INFRA_HOE_GTX3 | Amprion | Konventionell | negative | 10 | 8 | 15:July-15:July |
| INFRA_HOE_GTX2 | Amprion | Konventionell | negative | 10 | 8 | 15:July-15:July |
How BESS Can Reduce These Costs
Battery Energy Storage Systems at congestion points could have avoided an estimated €0.32M of today's redispatch costs by absorbing excess wind energy locally.
Learn BESS Arbitrage (Free) Stromfee AI PlatformFrequently Asked Questions
How much did redispatch cost on 2026-07-17?
On 2026-07-17, estimated redispatch costs were approximately €1.06 million. This includes €0.31M for renewable curtailment compensation and €0.56M for conventional ramp-up costs.
Which power plants were most affected on 2026-07-17?
The most affected plant was Wilhelmshaven (ENGIE) (TenneT DE) with 8,012 MWh of negative redispatch.
What was the electricity spot price on 2026-07-17?
The EPEX Day-Ahead spot price for DE_LU ranged from 98 to 177 €/MWh with an average of 139 €/MWh.